Ngā Ture Whakatau Tohunga
Te tukanga taunoa mō te Whakataunga Tohunga
Ki te kore ngā rōpū me te Tohunga e whakaae ki tētahi atu mea, ki te kore rānei e tohutohuhia e te Tohunga, ka whai mana te tukanga mō te Whakataunga Tohunga i roto i te Tāpiritanga 2 o te Whakaaetanga .
1.0 Me tautuhi, me whakamārama hoki ngā rōpū i ngā take e tautohetia ana i roto i ngā rā mahi e rima (5) mai i te whakatutukitanga o tēnei Whakaaetanga mā te whakarite i tētahi tauākī tahi mō ngā take, i tētahi atu huarahi rānei;
2.0 Me tuku e te Kaitono i roto i ngā rā mahi tekau (10) o te whakatutukitanga o tēnei Whakaaetanga ki te Kaiwhakautu me te Tohunga mā te kaikawe karere, he kape o āna tuku e pā ana ki ngā take tautohe me ngā tuhinga tautoko katoa me ngā taunakitanga e whakawhirinakihia ana.
Ko ngā tono a te kaitono me whakauru atu ki:
- He kōrero tuhituhi e whakaatu ana i te āhua me te pūtake o te tautohe, ngā take ture me ngā take pono e pā ana, ngā tautohe a te Kaitono e pā ana ki aua take me te nui o tana kereme;
- Te whakaoranga, te rongoā rānei e rapua ana;
- He tārua o te kirimana, o ngā wāhanga rānei e pā ana ki taua kirimana, i te wā rānei he kōrero ā-waha te kirimana, he wāhanga kōrero rānei, he whakapuakitanga ā-ture mō ngā tikanga o te kirimana;
- Ngā pūrongo, ngā kōrero rānei a ngā tohunga i whakawhirinakihia;
- I whakawhirinakihia ngā tuhinga tautoko katoa me ngā taunakitanga kē atu;
- Ngā tuhinga a te Kaitono mō ngā take ture me ngā take pono e pā ana ki tāna kereme.
3.0 Me tuku e te Kaiwhakautu i roto i ngā rā mahi e rima (5) i muri i te whiwhinga o ngā tono a te Kaitono mō ngā take tautohe, he whakautu tuhituhi ki te Kaitono me te Tohunga mā te kaikawe karere, ki ngā tono a te Kaitono.
4.0 Ko ngā whakautu tuhituhi a te Kaiwhakautu ki ngā tono a te Kaitono mō ngā take tautohenga me whakauru atu ki:
- He kōrero whakautu tuhituhi e whakaatu ana mēnā e whakaae ana, e kore rānei e whakaae ki te kōrero a te Kaitono i raro i te wāhanga 2.0 i runga ake nei, ā, ki te kore, ko tāna whakautu mō te āhua me te pūtake o te tautohe me ōna tautohetohe e pā ana ki ngā take me ngā take ture me te rahinga o ngā take e tautohetia ana;
- Mēnā he tautohenga mō ngā tikanga o te kirimana: he kape o te kirimana kei te kaipupuri kōrero, ngā wāhanga rānei e pā ana ki reira, mēnā he kōrero ā-waha te kirimana, he wāhanga kōrero rānei, he whakapuakitanga ā-ture mō ngā tikanga o te kirimana;
- Ngā pūrongo, ngā kōrero rānei a ngā tohunga i whakawhirinakihia;
- I whakawhirinakihia ngā tuhinga tautoko katoa me ngā taunakitanga kē atu;
- Ngā whakautu ā-tuhi mō ngā take ture me ngā take meka e pā ana.
5.0 Ka taea e te Tohunga te tono ki tētahi rōpū kia whakarato i ētahi atu tuku kōrero, i ngā rauemi taunakitanga rānei, me tuku ki te Tohunga me te rōpū kē atu i roto i ngā rā mahi e toru (3) i muri i te whiwhinga o tētahi tono pērā, me te huarahi hoki i tonoa e te Tohunga.
6.0 Ka taea e te rōpū kē te tuku urupare ki te Tohunga me te rōpū kē i roto i ētahi atu rā mahi e toru (3).
7.0 Kātahi ka whakatauhia e te Tohunga ngā take tautohe i te wā e taea ai i muri i te whiwhinga o ngā kōrero a ngā rōpū me ngā taunakitanga.