Whakataunga Kirimana
Mā te whakatau i raro i ngā Ture Whakatau BDT ka taea e ngā rōpū e tautohetohe ana te whai hua, te pakari hoki o tētahi tukanga whakatau tautohe, ā, ka puta he whakataunga mā tētahi kaiwhakawā motuhake, i roto i ngā rā mahi 35. He pai tēnei tukanga mēnā kāore e wātea ana te Whakatau CCA ture, ā,/e whakaae ana rānei ngā rōpū ki te whakamahi i tēnei tukanga.
Tirohanga Whānui o te Tukanga
Te tīmatanga o te tukanga
Me whakaae ngā rōpū ki te whakamahi i te tukanga. Ka taea e rātou te mahi i tēnei i mua atu, i muri rānei i te putanga mai o te tautohe. (Mēnā kāore ngā rōpū e whakaae, ā, e pā ana te tautohe ki tētahi kirimana hanga, ka taea e tētahi rōpū te tīmata i te Whakataunga CCA hei utu)
Te Whakatūnga o tētahi Kaiwhakawā
Mā BDT e whakaingoa he kaiwhakawā, ā, ka whakamōhiotia ngā rōpū mō te whakatūnga. Ko te rā e mahia ai tēnei ko te Rā Tīmatanga.
Kereme
Me tuku e te Kaitono te Kereme i roto i ngā rā mahi e 5 mai i te Rā Tīmatanga
Whakautu
Ka taea e te Kaiwhakautu te tuku Whakautu ki te Kereme i roto i ngā rā mahi 10 mai i te Rā Tīmatanga.
Whakautu
Mena ka tukuna he Whakautu, ka taea e te Kaitono te tuku Whakautu i roto i ngā Rā Mahi 15 mai i te Rā Tīmatanga.
Whakautu
Mena ka tukuna he Whakautu, ka taea e te Kaiwhakautu te tuku Whakautu i roto i ngā rā mahi 18 mai i te Rā Tīmatanga.
Whakataunga
Ko te whakataunga a te Kaiwhakawā e kiia ana he Whakataunga. Ka tukuna i roto i ngā rā mahi 25 i muri i te whiwhinga o te Whakautu (arā, i roto i ngā rā mahi 35 i muri i te Rā Tīmatanga).
Hipanga 1. Te tīmatanga o te tukanga
Hei tīmatanga i te tukanga, me whakaae ngā rōpū ki te tuku i tā rātou tautohe ki te whakawakanga.
Ka taea e rātou tēnei mā te whakauru ki tētahi whakaaetanga whakatau. Mā tēnei whakaaetanga ka whakatauhia te tautohe i raro i ngā Ture Whakatau BDT.
Heoi anō, mēnā kei roto i te whakaaetanga a ngā rōpū te wāhanga whakatau tauira BDT, ā, i whakaurua i mua i te putanga mai o te tautohe, me tuku e te Kaitono he Pānui Whakatau ki ngā rōpū kē atu hei whakamōhio atu kei te tīmata te tukanga. Kāore e hiahiatia tēnei mēnā i hainatia e ngā rōpū he whakaaetanga whakatau i muri i te putanga mai o te tautohe.
Ka whakapau kaha a BDT ki te whakatū i tētahi kaiwhakawā motuhake, he tika hoki ōna tohu, i roto i ngā rā mahi e toru i muri i te whiwhinga o te whakaaetanga whakatau, te pānui whakatau rānei.
Ka whai whakaaro te whakatūnga ki ngā paearu katoa i whakaaetia e ngā rōpū, te āhua me te uara o te tautohe, te maha o ngā rōpū, ō rātou wāhi noho, me ngā reo, te wātea o ngā kaiwhakawā ā muri ake nei, me ētahi atu mōhiohio i whakaratohia e ngā rōpū, e pā ana rānei ki te take.
Ka whakaae pea ngā rōpū ki te whakaingoa i tētahi kaiwhakawā. Mā te BDT taua tangata e whakatū, ki te aromatawaitia rātou e te BDT he tangata whai mana, he tika, ā, kāore he taupatupatu pānga.
Mā te Kai-rehita e whakamōhio te whakatūnga ki ngā rōpū. Ko taua rā ko te Rā Tīmatanga . Ko ngā rā katoa mō te tukanga ka tīmata mai i te Rā Tīmatanga.
Hipanga 2. Te Whakatūnga o tētahi Kaiwhakawā
Ka whakapau kaha a BDT ki te whakatū i tētahi Kaiwhakawā motuhake, he tika hoki ōna tohu, i roto i ngā Rā Mahi e 3 i muri i te whiwhinga o te whakaaetanga ki te whakatau, te pānui whakatau rānei.
Ka whai whakaaro ngā whakatūnga katoa ki ngā paearu kua whakaaetia e ngā rōpū ki te tautohe, te āhua me te uara o te tautohe, te maha o ngā rōpū, ō rātou wāhi noho, me ngā reo, te wātea o ngā kaitono, me ētahi atu mōhiohio i whakaratohia e ngā rōpū, e pā ana rānei ki te take.
Ka taea hoki e ngā rōpū, mā te whakaaetanga, te whakaingoa i tētahi Kaiwhakawā mō te whakatūnga. I runga anō i te aromatawai a BDT he tika, he āhei, ā, kāore he tautohe o te kaitono, ka whakatūria e BDT taua tangata.
Ka whakamōhiotia te whakatūnga ki ngā rōpū e te Kai-rehita, ā, ko te rā o taua whakamōhiotanga ko te Rā Tīmatanga . Ka tīmata ngā rā katoa mō te tukanga mai i te Rā Tīmatanga.
Hipanga 3. Kereme
Me tuku e te Kaitono te Kereme i roto i ngā rā mahi e 5 mai i te Rā Tīmatanga.
Me whakauru ngā mōhiohio e whai ake nei ki te Kereme:
- Te āhua me te pūtake o te Kereme;
- Te nui o te utu i tonoa, te awhina, te rongoā rānei i tonoa, tae atu ki tētahi kereme huamoni;
- Ngā tārua o ngā pūrongo a ngā tohunga, ngā kōrero a ngā kaiwhakaatu, ngā tuhinga rānei e whakawhirinakihia ana e te Kaitono; ā,
- Ngā tuku kōrero mō ngā take me ngā take ture e pā ana ki te Kereme.
Me whakamārama mārama e te Kereme te mea e rapuhia ana e te Kaitono me te take e kī ai rātou he tika ki a rātou, me te whakahua hoki i ngā taunakitanga e tautoko ana i taua tūnga.
Hipanga 4. Whakautu
Ka taea e te Kaiwhakautu te tuku whakautu ki te Kereme. Me tuku whakautu i roto i ngā Rā Mahi 10 mai i te Rā Tīmatanga.
Me whakauru ngā mōhiohio e whai ake nei ki te Whakautu:
- Ko ngā mea nui o te Kereme ka whakaaetia, ka whakaaetia rānei;
- He mea tautohetohe ngā mea nui, me te take;
- Tetahi parenga ki te Kereme;
- Ngā tārua o ngā pūrongo a ngā tohunga, ngā kōrero a ngā kaiwhakaatu, ngā tuhinga rānei e whakawhirinakihia ana e te Kaiwhakautu; ā
- Ngā whakaaetanga mō ngā take me ngā take ture e pā ana ki te Kereme me te Whakautu.
Mā te Whakautu ka taea e te Kaiwhakautu te whakamārama i tōna tūnga me te whakamārama ko ēhea ngā take e tautohetia ana, ko tā te Kaiwhakautu i kī ai ko te whakautu, me te take, me te whakahua hoki i ngā taunakitanga e tautoko ana i taua tūnga.
Hipanga 5. Whakautu
Ka taea e te Kaitono te tuku Whakautu ki te Whakautu i roto i ngā Rā Mahi 15 mai i te Rā Tīmatanga .
Mena ka tukuna he Whakautu e te Kaitono, me tino whakautu noa iho ki te Whakautu, ā, kaua e ara ake he take hou. Tērā pea kei roto i te Whakautu ngā tuhinga tautoko e tika ana.
Hipanga 6. Whakautu
Mena ka tukuna e te Kaitono he Whakautu, ka taea e te Kaiwhakautu te tuku Whakautu i roto i ngā Rā Mahi 18 mai i te Rā Tīmatanga .
Mena ka tukuna he whakautu e te Kaiwhakautu, me whakautu tika ki te Whakautu, ā, kāore e taea te whakaara ake i tētahi take hou. Tērā pea ka uru atu ki te Whakautu ētahi tuhinga tautoko e tika ana.
Hipanga 7. Whakatau
He 'whakataunga' te whakatau a te kaiwhakawā. Ka whakapau kaha te kaiwhakawā ki te whakaputa i te whakatau i roto i ngā rā mahi 25 mai i te Whakautu, arā, 35 Ngā Rā Mahi i muri i te Rā Tīmatanga (mehemea he whakaroa ki te rārangi wā).
Ka herea ngā rōpū e te whakataunga mō tēnei wā. Ka taea te whakamana hei nama e tika ana kia tae rā anō ki te wā e whakatauhia ai te tautohe e te whakatau tautohe, e ngā tukanga ture i roto i te kōti, i te taraipiunara rānei, e te whakaaetanga rānei a ngā rōpū i muri mai.
Ka whakaarohia e te kaiwhakawā ngā kōrero me ngā taunakitanga a ngā rōpū. Ka whakaarohia e rātou te ture e pā ana, ka paunatia ngā taunakitanga whakataetae, ā, ka whakamahia te ture ki ngā meka e kitea ana e rātou.
Te whakatikatika i ngā hapa ('ture paheke')
I roto i ngā rā mahi e rua i muri i te tukunga o te whakataunga ki ngā rōpū, ka taea e te rōpū te tono ki te kaiwhakawā kia whakatikahia ngā hapa i roto i te tatau, ngā hapa tuhituhi, ngā hapa tātuhi rānei o tētahi āhua rite (ture 7.22). Ka whakapau kaha te kaiwhakawā ki te whakatika me te tuku anō i te whakataunga i roto i ngā rā mahi e 3 i muri i te tukunga o te whakataunga.
Waihoki, ka taea e te kaiwhakawā te whakatika i te whakataunga i runga i tana ake whakaaro i roto i ngā rā mahi e 3 i muri i te whakaputanga (ture 7.25).
He rite tēnei tukanga ki te 'ture paheke', e āhei ai ngā kōti me ngā kaiwhakawa ki te whakatika i tētahi paheke, i tētahi hapa tūpono rānei ina puta he hapa tuhituhi, hapa tātai, hapa mīhini rānei. Kāore e taea te whakamahi hei whakarerekē i te whakataunga, ahakoa he mārama noa te hapa i te tirohanga tuatahi.
Me tirotiro tonu e ngā rōpū te whakataunga, ā, me tono kia whakatikatikaina i te wā e taea ai kia taea ai e te kaiwhakawa te whakaaro me te mahi i ngā whakatikatika i roto i ngā rā mahi e toru.
Te Arotake i te Whakataunga a te Kaiwhakawa
E whakapau kaha ana te Taraipiunara Taupatupatu Hanga Whare ki te whakarato i ngā ratonga kounga teitei rawa atu. Ka tirotirohia ngā whakataunga katoa e tētahi tangata whai mātauranga ture. Mā tēnei tukanga whakapūmau kounga ka whakaitihia te tūponotanga o ngā hapa e hiahia ana kia whakatikatikaina, kia whakamāramahia rānei, ka whakawhiwhia ki ngā rōpū he whakamanawa anō i roto i te tukanga me ngā putanga. Heoi anō, ko te whakataunga tonu a te kaiwhakawā, ko ia anake te kawenga mō te tukanga whakatau me te putanga.
Ngā taahiraa e whai ake nei
Whakapā mai
Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:
Waea: +64 9 486 7143
Waea Koreutu: 0508 WHARE
Waea Koreutu: 0508 284 534
Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)