Adjudication Judgements
2025
Queensland Supreme Court sets aside determination due to jurisdictional error
In Forme Two Pty Ltd v McNab Developments (Qld) Pty Ltd [2025] QSC 96, the Queensland Supreme Court (the Court) declared an adjudication determination void after finding a judicial error. The question for the Court concerned whether a payment claim under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act) was valid, given that it was made outside the statutory time limits.
Forme Two had engaged McNab Developments under an unsigned contract to assist with a property development in New Farm. In January 2024, McNab submitted a payment claim under the BIF Act. Forme Two responded with a payment schedule for $nil, disputing the claim. McNab then applied for adjudication and was successful, with an adjudicator awarding $162,505.08 in McNab’s favour.
Forme Two challenged the decision. It argued that the payment claim was not valid because it did not include any claims for work done within six months of its submission, as required under section 75(2)(b) of the BIF Act. The Court established that none of the work McNab sought payment for had been performed within that six-month period.
The Court addressed two key legal issues: (1) whether the timing requirement under section 75(2) (b) means that a claim must relate to work actually done within the six-month period, and (2) whether compliance with this requirement is a jurisdictional fact (a “category 1” matter) or a matter for the adjudicator’s opinion (“category 2”).
The Court held that section 75(2)(b) requires that some work claimed must have been performed within six months prior to the claim being made. Furthermore, the Court classified this as a jurisdictional fact — a requirement that must objectively exist for an adjudicator to have jurisdiction. Since McNab conceded that none of the work claimed was completed in the relevant period, the payment claim was invalid, and the adjudicator had no jurisdiction to make the decision.
2024
Rogers Construction Group Pty Ltd v Mirage Interiors & Construction Pty Ltd [2024] NSWSC 1344, – Supreme Court of New South Wales addresses an application to set aside an adjudication determination over concerns raised regarding procedural fairness.
The facts
Rogers Construction Group Pty Ltd (the Builder) engaged Mirage Interiors & Construction Pty Ltd (Mirage) to supply and install walls, ceilings, and partitions at the Busby Fire Station under a written lump sum contract established in December 2023. Subsequently, Mirage contended that on 16 February 2024, the parties entered into a separate oral agreement that superseded the original contract, transitioning the arrangement to a cost-plus basis. The Builder disputed the existence of this oral contract.
Mirage served a payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) for work purportedly performed under the alleged oral contract. An adjudicator determined that Mirage was entitled to a progress payment of $108,451.13, accepting the existence of the oral contract as a separate agreement from the original written contract.
The decision
The Builder sought judicial review of the adjudication determination, asserting a denial of procedural fairness. Specifically, the Builder argued that the adjudicator’s decision was based on reasons not advanced by either party and that they could not have reasonably anticipated these reasons. The primary contentions were firstly, that the adjudicator found an overlap between the original written contract and the subsequent oral contract; and that secondly, the adjudicator considered the oral contract as a variation to the original agreement.
The Builder contended that it was denied the opportunity to address these points, constituting a lack of procedural fairness.
The Supreme Court examined whether the adjudicator had denied the Builder procedural fairness. The Court noted that under the Act, an adjudicator must accord procedural fairness to the parties. However, due to the Act’s structure and intent to provide a “rough and ready” process, the requirements for procedural fairness are reduced. The Court held that the determination will only be invalidated if there is
- a significant departure from what would ordinarily be the requirements of procedural fairness for a person exercising a statutory power, and where the departure could be characterised as leading to substantial practical injustice in all the circumstances.
In this case, the Court found that the Builder was aware of the potential overlap between the contracts and had anticipated the argument that the oral contract could be viewed as a variation. The Builder had made submissions on these issues during the adjudication process. Therefore, the Court concluded that there was no denial of procedural fairness, as the Builder had the opportunity to address the points in question. The application to quash the adjudication determination was dismissed.
Conclusion
This decision reinforces the principle that courts will rarely overturn an adjudicator’s determination on the grounds of procedural fairness under the Act. It underscores the importance for parties to comprehensively present their cases during adjudication, anticipating potential interpretations and arguments.
High Court sets aside statutory demand in defective building case
In Your Builder Limited v Ruban, the owners of a property entered into a contract with Your Builder Ltd (Your Builder) on 24 July 2022 to renovate and extend their house. They paid the $124,478.66 deposit on 9 February 2023. Fast-forward to September—the owners sought to cancel the contract and get back the deposit on the basis that there were serious defects in Your Builder’s work.
Your Builder disputed the owners’ right to the deposit. It argued that the amount should be applied to unpaid invoices, contractual interest, lost profit, and legal fees. Your Builder also sought to cancel the contract on the basis that the owners had repudiated the agreement when they engaged another builder to carry out remedial works.
The owners subsequently issued a statutory demand and served Your Builders with a claim for adjudication under the Construction Contracts Act 2002. The issue for the High Court (the Court) was whether there had been a genuine and substantial dispute over the existence of the debt.
The Court found that, under the contract terms, Your Builder was entitled to use the deposit towards the final invoice and, by implication, any remaining undisputed amounts. As the owners did not dispute the invoices, the Court found that of the $124,478.66 deposit, $47,940.31 plus legal costs were not owed as a debt.
Regarding the remaining deposit, the Court found that Your Builder met the threshold of showing a genuine and substantial dispute. This is because there were factual disputes regarding (1) the nature and extent of the defects, (2) whether Your Builder was given a reasonable opportunity to remedy the defects, and (3) whether Your Builder could have remedied the issues within the required timeframe. As a result, the High Court set the statutory demand aside and ordered the owners to pay costs.
2023
Dem Home Ltd v New Gate Ltd [2023] NZHC 2709
The High Court considered whether a payment claim had been validly served under the Construction Contracts Act 2002 (the CCA).
Background Dem Home Limited engaged New Gate Limited to build terrace houses in Point England, Auckland. Before construction was complete, Dem Home alleged breach of contract by New Gate and so sought to cancel the contract. New Gate issued a payment claim for $242,500.50 which Dem Home ignored.
The ignored payment claim prompted New Gate to serve a statutory demand on Dem Home.2 In response, Dem Home applied to the High Court to set aside the statutory demand. New Gate opposed the application.
Issues for the High Court
Dem Home identified three reasons why the payment claim was not valid under the CCA:
- The payment claim failed to comply with the formal requirements.
- New Gate was not entitled to issue the payment claim at that point.
- It was issued after Dem Home cancelled the construction contract.
Decision of the High Court
A starting point for the High Court was the purpose of the CCA. Referring to Demasol v South Pacific Industrial Limited, the High Court summarised the approach to be taken. Any analysis of the CCA must reject a “technocratic” or “formalistic” interpretation as this would undercut Parliament’s intent that cashflow in the construction industry be maintained.
Did the payment claim fail to comply with the formal requirements?
Sections 20(2)(3) and (4) of the CCA contain the requirements for a payment claim to be valid. Some of these include that the payment claim be in writing and that the claim states that it is made under the CCA.
The Court found that the claim in fact was made in writing. The claim was not verbal and contained a range of information tying the claim to the payment sought. Dem Home had also argued that the necessary information was in small font, but a comparison of the font sizes found this to be untrue.
Was New Gate unable at that time to issue a payment claim?
New Gate and Dem Home had agreed in their contract that New Gate was entitled to issue payment claims when certain work was complete. Dem Home argued that this had not occurred.
The Court again looked to Demasol. In its view, the decision decisively rejected the approach Dem Home had taken to halt the payment claim. The payment claim should have been challenged by Dem Home in the form of a payment schedule. Dem Home’s failure to issue the payment schedule within time meant that it could not then use the contended matter in an attempt to set aside the statutory demand.
Would the payment claim be invalid if it was issued after Dem Home cancelled the contract?
New Gate raised two arguments in response to this matter. The first was that the contract had not in fact been cancelled. The second was that even if the contract had been cancelled, the payment schedule regime in the CCA still applied. Although the Court did not address whether the contract had been cancelled, it again found that any dispute had to be served by way of a response to the payment claim.
The Court dismissed Dem Home’s application to set aside the statutory demand.
2022
Supreme Court of Queensland considers correspondence complexities in payment schedule dispute
In Demex Pty Ltd v John Holland Pty Ltd [2022] QSC 259, a subcontractor claimed a payment schedule sent to them by the principal was invalid because it had been sent after the date contractually agreed upon. In considering the application, the Supreme Court of Queensland looked at what circumstances are necessary for a claim to be properly served.
The construction contract between John Holland Pty Ltd (the principal) and Demex Pty Ltd (the subcontractor) contained a clause under which a payment schedule would have to be delivered to the subcontractor by the principal within 10 working days of the principal having received the payment claim. Compliance with this correspondence timetable was to occur if the principal believed the sum requested by the subcontractor was too high.
On Saturday, 25 September 2021, the subcontractor sent a payment claim to the principal. The corresponding payment schedule was sent to the subcontractor on Tuesday, 12 October 2021, establishing they believed the cost to be substantially lower. Having noticed the schedule had not been given 10 working days after the claim had been sent, the subcontractor claimed the schedule was invalid. The subcontractor subsequently filed an application for the full cost.
The principal contended that the payment schedule had indeed been issued within the agreed upon period. It argued that although the claim had been sent on Saturday it could not be said that this was the day on which it was received. Saturday was outside the working hours specified in the contract.
The Court centred its decision on the fact that the service period is not effected until the party receives the payment claim. Looking at whether the claim was received on that Saturday or that Monday, the Court took note of the enormity of the consequences for non-compliance. Where the stakes are so high, the party looking to serve the payment claim must have firm evidence that the claim was received on the day they are asserting. The subcontractor did not have this; and so the Court found in favour of the principal. The subcontractor was not entitled to the full cost it had originally claimed.
Supreme Court of New South Wales asks how many payment claims can be served
In BCFK Holdings Pty Ltd v Rork Projects Pty Ltd [2022] NSWSC 1706, a builder served a payment claim on its principal. The payment dispute went to adjudication, but the award given was challenged by the principal in the Court on the basis that one of the payment claims was invalid. In determining the matter, the Court considered the interpretation of section 13(c) of the Building and Construction Industry Security of Payment Act 1999 (the SOP Act).
BCFK Holdings Pty Ltd (the principal) and Rork Projects Pty Ltd (the builder) had entered into a construction contract which was terminated in May 2022. That July, the builder served a payment claim on the superintendent of the project. Under the contract, the superintendent was unable to accept service of documents; accordingly, they notified the principal of the claim. The corresponding payment schedule was then served on the builder. In express terms, the payment schedule stated that the payment claim to which it was responding was invalid. Due to confusion as to whether that payment claim had been effectively served, the builder decided not to proceed with adjudication. Instead, a second payment claim was served on the principal, this time straight to the principal with confidence as to its validity. The principal responded with a payment schedule.
At the adjudication stage, a determination was made in favour of the builder. This determination was challenged on the basis that the first payment claim, was in fact served validly, and thus the second could not be.
The Supreme Court of New South Wales (the Court) found in favour of the principal. This was done by considering two related matters:
- Which of the two payment claims was valid?
- Can a party serve more than one payment claim?
On the first issue, the Court cited Piety Constructions Pty Ltd v Hville FCP Pty Ltd [2022] NSWSC 1318, to find that a payment claim is not invalid simply because the correspondence was undertaken improperly. The wrong person had been contacted, but ultimately it had been received by the correct person. This had made effective the serving of the first payment claim.
Section 13(1C) of the SOP Act was assessed to reach a conclusion on the second matter. The provision directs that [i]n the case of a construction contract that has been terminated, a payment claim may be served on and from the date of termination. The Court read this section to mean that at the contract’s termination, only one payment claim can be made.
As the Court had held that the first payment claim was validly served, it followed that the second payment claim was invalid. Consequently, the adjudicator could not have had jurisdiction to adjudicate on the second payment claim. The adjudicator’s determination therefore had to be quashed.
2021
Hellaby Resources Services Limited (HRS) v Body Corporate (BC) 197281 [2021] NZHC 554 (NZ High Court)
TBS and BC had a construction contract to undertake remediation for weathertightness issues. The BC later refused to pay the balance of the agreed price on the basis that certain areas of work remained defective.
TBS applied for summary judgment against the BC for payment of the balance of the debt and for a stay of the counterclaim by BC for defective works, on the basis it be pursued separately through arbitration.
BC opposed summary judgment, contending the Court should exercise its residual discretion to decline summary judgment to avoid oppression or injustice to the BC, or a stay of enforcement pending resolution of the BC’s counterclaim, as enforcement would result in a substantial miscarriage of justice.
High Court found the BC had no arguable defence to TBS’s application for summary judgment because the amount claimed was a scheduled amount and therefore a debt due pursuant to s 24 of the CCA. Nevertheless, the Court decided to order a stay of execution of the summary judgment because the BC had a credible counterclaim that the remediation work was defective and there was a real risk that the BC would be unable to pursue the counterclaim due to a lack of funds; or if it was able; it would be fruitless because TBS had already sold its business and was now a shell company. Arbitration only available for one month after final payment schedule issued. BC could not rely protections for consumers under s 11 Arbitration Act 1996 as BC was not a natural person.
Development Construction Company Limited (DCL) v Mackenzie (DM) [2021] NZHC 546 (NZ High Court)
Application to sustain caveat – relying on reservation of title clause found in contract
Application by DCL to sustain a caveat. DCL had obtained adjudication under Construction Contracts Act 2002 against DM for failure to pay for earthworks in a subdivision. Whether DCL had a caveatable interest in residential property registered to DM, under a reservation of title clause in the construction contract. The Court found a reservation of title clause without an express right to enter could not give rise to an interest in land, therefore there was no caveatable interest in DM’s property. Application to sustain caveat dismissed and order for removal of caveat.
Arnerich v DHC Assets Ltd [2021] NZCA 225 (NZ Court of Appeal)
Companies Act – whether director had breached duty to act in best interests of company -avoidance of Construction Contracts Act adjudication award
DHC was an unpaid creditor of Vaco Investments Ltd following an adjudication under the Construction Contracts Act 2002. Vaco was placed into voluntary liquidation by its sole director, Arnerich.
DHC brought proceedings under s301 of the Companies Act 1993 alleging that Arnerich had breached his duty to act in the best interests of Vaco (as required by s131 of the Companies Act) by causing Vaco to make substantial distributions before DHC’s contractual claims had been ascertained and paid by Vaco. DHC sought an order under section 301 that Arnerich pay the amount DHC was owed by Vaco direct to DHC. Court of Appeal found Arnerich breached s131 by causing Vaco to distribute its remaining funds, without ensuring that Vaco retained sufficient funds to meet contingent claims by DHC. Matter remitted back to the High Court to determine the amount of any further claim by DHC against Vaco under the construction contract, and in light of that, to make such further orders against Arnerich under s301 as appropriate.
KME Services NZ Pty Limited v CBP Contractors Pty Limited [2021] NZHC 212 (NZ High Court)
Implied obligation in a construction contract – right for damages for delay sought
CPB was head contractor for building work and KME was a subcontractor. Due to delays, CPB twice exercised its contractual right to extend the date for substantial completion. KME attributed delays to CPB’s failure to coordinate trades, failure to allow access to site, and failure to provide timely responses to enquiries over life of job. KME lodged 2 extension of time (EOT) claims which were rejected by CPB. CPB sought to strike out KME’s claims. Whether the Court should grant a declaration that CPB breached contract by failing to grant EOT claims. Court held that contract provided the onus rested on KME to work with other contractors and to call upon CBP to make an EOT ruling only when they were unsuccessful. Process did not leave room for an implied term that the obligation to co-ordinate tradespeople on site was on CBP. Implying terms as pleaded would create a right to damages for delay where none presently existed. Application to strike-out both causes of action granted as they were inconsistent with entire agreement clause dealing with EOTs.
2020
Jade Residential Limited v Paul [2020] NZCA 477 (NZ Court of Appeal)
Whether a dispute resolution clause was a bar to exercise of right to terminate contract – whether contractor’s action amounted to repudiation entitling cancellation without an express term providing for such
Jade was contracted to build Pauls’ house. Pauls cancelled the contract after Jade, which had not met two construction milestones, refused to return to work until Pauls paid for the milestones. Jade alleged the construction contract had not been validly cancelled. Whether the dispute resolution clause in contract was a bar to anything other than the issue of court or arbitral proceedings or delayed a right to cancel for repudiation? Court held there were no express words in the dispute resolution clause requiring Pauls to defer exercising right of cancellation until dispute resolution was complete. Termination provisions under s37 of the Contract and Commercial Law Act 2017 applied – cancellation of contract was valid as Jade’s actions amounted to repudiation of contract, despite the absence of a provision in the contract entitling either party to terminate.
Cubo Projects Limited v S & S Import Solutions Limited [2020] NZHC 3234 (NZ High Court)
The importance of payment schedules – consent judgment – issue of costs
Dispute under the Construction Contracts Amendment Act 2015. Import Solutions engaged Cubo to carry out construction work. Cubo issued payment claims. Import Solutions paid portion and disputed balance and did not respond with payment schedules. Cubo served statutory demand for the balance – ignored by Import Solutions. Parties sought to resolve matter, and settled on the terms set out in a consent judgment with costs still to be resolved. Cubo sought scale costs on a 2B basis with a 50% uplift. Import Solutions had forced Cubo to take steps incurring related costs and did not acknowledge Cubo’s entitlement to outstanding amount until court hearing. Court awarded costs to Cubo on 2B scale.
Alaska Construction + Interiors Auckland Limited v Lahatte [2020] NZHC 1481 (NZ High Court)
Judicial review application challenging adjudicator’s determination under Construction Contracts Act 2002
Application by Alaska seeking judicial review of adjudicator’s CCA determination, on the basis that it was incomplete, failed to address all the issues the adjudicator was asked to determine, breached natural justice, and the adjudicator failed to discharge the statutory functions provided for in ss 38, 47 & 48 of the CCA and unreasonably exercised a statutory power. Alaska also alleged adjudicator awarded other party indemnity costs without providing reasons as to why it was reasonable. The Court held that although judicial review was available to challenge an adjudicator’s determination under the CCA, such relief will be available only rarely. The adjudicator’s determination accorded with his statutory functions, nor did he unreasonably exercise his statutory power, nor had Alaska persuaded on judicial review the award and amount of costs was flawed.</p?
2019
Bethell v Papanui Properties Limited [2019] NZHC 3169 (NZ High Court)
Voluntary liquidation – application for directions – project and construction management contract – whether there was an implied express trust in place for funds being paid to third parties
Application for directions by liquidators of Arrow, concerning the status of client’s funds paid to Arrow prior to it being placed into voluntary liquidation. Arrow acted as agent under a project management and construction management contract (PMCM) where clients paid funds to Arrow which paid funds as client’s agent to third parties. Distinction between agent having fiduciary duties and agent having a trust obligation to keep trust assets separate. Accepted that agents such as Arrow had fiduciary obligations. Relationship between Arrow and its PMCM clients was not a trust relationship in its purest sense as Arrow profited from contracts. Extent of fiduciary duties owed by Arrow to PMCM clients was determined by their contract and nature of tasks Arrow undertook. Not the intention of the parties that funds sought by Arrow for the purpose of meeting PMCM clients’ indebtedness to third parties would become the property of Arrow. There was an implied express trust in favour of the PMCM clients in respect of funds paid to Arrow by PMCM clients for payment to trade contractors under contracts made by Arrow on behalf of PMCM clients.
Cromi Investments Limited v CMP Construction Limited [2019] NZHC 2142 (NZ High Court)
Setting aside statutory demand – whether payment claim satisfied CCA requirements as due date not noted in payment claim
Application to set aside statutory demand. Argument between principal (Cromi) and contractor (CMP) over remedial works and release of retention monies held by Cromi under the construction contract governed by Construction Contracts Act 2002. Cromi claimed it was not caught by the sudden death regime under the CCA, as CMP’s payment claim did not meet requirements under the CCA, and there was a genuine dispute about the entire amount claimed by CMP in its statutory demand – payment claim did not satisfy requirements in s 20 CCA as it did not indicate the due date for the payment claimed – as requirements were mandatory and cumulative, there were no corresponding obligations triggered on Cromi – there was a substantial dispute as to the debt which was sufficient to set the statutory demand aside under s 290 Companies Act 1993. Genuine dispute between parties which should be returned to dispute resolution procedure provided for under contract. Application granted – statutory demand set aside.
Oceania Football Confederation Incorporated v Engineered Solutions & Systems Limited [2019] NZHC 1439 (NZ High Court)
Payment claims and payment schedules – Construction Contracts Act 2002
Application by OFC seeking to have a statutory demand by ESSL set aside. EFFC issued invoices to OFC it said constituted payment claims under the CCA. Alleged that OFC issued no payment schedules. Whether invoiced amounts became a debt due and payable in accordance the CCA. The High Court held that any challenge must be based on an alleged defect in the payee’s compliance with the statutory requirements of the CCA, not with some additional requirements the construction contract might impose. Payments structured to address reasonable value of work being claimed qualified as valid payment claims. Instalments were agreed proportions of lump sum contract price, payable on stipulated dates.
2018
Anderson v Swindells [2018] NZHC 1803 (NZ High Court)
Judicial review – breach of natural justice or significant error or law by adjudicator – quashing of adjudicator’s determination
Application seeking judicial review of adjudicator’s determination under the Construction Contracts Act 2002, on the grounds the determination was made without jurisdiction, on the basis of mistaken fact, errors of law, failing to take into account relevant considerations, taking into account irrelevant considerations, failing to give coherent and adequate reasons and failing to reach conclusions on issues raised by the parties. Applicant had to demonstrate the Adjudicator had made a significant and substantial error of law or that there was a fundamental and substantial breach of natural justice. Adjudicator determined an issue that was not contained in either of the parties’ adjudication claims and so acted beyond and without jurisdiction. Adjudicator failed to give adequate reasons for determination, and deprived both parties from addressing and making submissions on the issue of compliance or non-compliance with CCA which was a breach of natural justice and contrary to s 41(c) and took into account irrelevant considerations. Order made quashing the adjudicator’s determination.
Body Corporate 200012 v Naylor Love Construction Limited [2018] NZHC 569 (NZ High Court)
Determination under CCA 2002 – what costs were recoverable where adjudicator’s decision enforced by entry as a judgment of the District Court.
Dispute between parties to a construction contract was resolved by adjudicator’s determination under the Construction Contracts Act 2002. District Court entered adjudicator’s determination as a judgment, and awarded the adjudication creditor its actual and reasonable costs. Appeal to the High Court against the costs decision which found the adjudication creditor may recover the outstanding payment from the adjudication debtor as a debt due in any Court: s 59(2)(a). Secondly, it may serve notice of its intention to suspend any further construction work under the contract: s 59(2)(b). Thirdly, it may apply for the adjudicator’s decision to be enforced by entry as a judgment: s 59(2)(c). Where the adjudication creditor chose to use the enforcement route under s 59(2)(c), the provisions of s 59(2)(a)(ii) did not apply. Instead, costs will be at the discretion of the District Court in the usual way. Appeal allowed – issue of costs remitted to District Court for determination in accordance with usual principles relating to costs in civil proceedings in the District Court.
Buchanan Construction Limited v Watson [2018] NZDC 4570 (NZ District Court)
Details of payment claim and serving of payment claim – strict adherence to requirements under CCA 2002.
Claim by BCL against Watson pursuant to a construction contract – whether the payment claim by BCL complied with requirements of the Construction Contracts Act 2002 – whether payment claim served by email met service requirements of Construction Contracts Regulations 2003. Court noted a payment claim must be sufficiently detailed and comprehensible to enable a payer to understand the basis on which the claim is made. Only then could the payer decide whether to accept it or to put the payee on notice of a dispute by providing a payment schedule in response explaining the payer’s reasons for disagreeing with the claim. BCL’s payment claim was not sufficiently detailed and comprehensible to enable Watson to understand basis on which various claims were made – Watson unable to respond in accordance with s 21 CCA. While the parties used email to communicate on day-to-day matters related to the contract, it did not follow under r 10(2)(b) CCR, that it could be reasonably inferred from such conduct, that Watson consented to the service of a payment claim by email. BLC’s claim dismissed.
2017
Body Corporate 200012 v Keene & Ors [2017] NZHC 2953 30 November 2017 (NZ High Court)
Application for judicial review of adjudication determinations
The Court dismissed the application for judicial review and the appeal, holding that BC12’s claims did not in fact go to the jurisdiction of the adjudicator’s decisions, but rather related to contractual interpretation, which plainly fell outside the scope of judicial review. To succeed in an application for judicial review, BC12 would have needed to show: a genuine excess of jurisdiction by the adjudicator; a serious breach of natural justice; or some apparent and significant error of law. BC12 had not succeeded on any of these three points. Accordingly, the Court refused to allow BC12 to undermine the CCA by using the judicial review process as a deliberate strategy to avoid the CCA’s “pay now, argue later” policy.
ELTEK AUSTRALIA PTY LTD v FIRTH & ANOR [2017] NZHC 480 16 March 2017 (NZ High Court)
judicial review of ruling on jurisdiction – arbitration clause – contractual right to refer to adjudication – right to refer disputes to adjudication – international construction contract
Subcontract contained clause providing that disputes may be dealt with by adjudication as provided for in the Construction Contracts Act 2002. Adjudicator held that this clause permitted the contracting parties to invoke the adjudication procedure and that consent was given at the time of entering into the subcontract. Court not persuaded the adjudicator erred in his decision finding that the clause in the subcontract recorded in advance the parties consent to the use of adjudication as required by s25(3) of the Act. Application for review declined.
2016
PAK HOLDINGS LIMITED (T/A HUMPHRIES CONSTRUCTION) v PROLIANT NZ LIMITED [2016] NZDC 15368 17 August 2016 (NZ District Court)
Construction Contracts Act – summary judgment – statutory debt – scheduled amount unpaid – defence s24 and s29 of CCA not applicable
Summary judgment brought on basis that, in terms of the contract and the provisions of the CCA, the sum the subject of the final payment schedule was a debt due to Humphries from Proliant and that Proliant had no defence to the claim. Proliant argued that it had a counter-claim or set-off exceeding the sum sought by Humphries and pleaded that s24 and s29 of the CCA were not applicable. Summary judgment entered. The Court was satisfied that the technical payment procedure steps had been followed and Proliant had no arguable defence.
CENTRAL LAKES HOMES LTD v CLARK [2016] NZDC 396 1 February 2016 (NZ District Court)
summary judgment – BDT adjudicator’s decision made under s48(1)(a) – payment claimed under a contract – damages
Application for summary judgment opposed on the basis that the determination was said to properly have been made under s48(1)(b) of the Act, rather than s48(1)(a), with the result being that the plaintiff was not entitled to recover payment because s59 of the Act did not apply to any awards made under s48(1)(b). The Court found that the damages is question must arise out of the default of the defendant. His repudiation of the contract and the resulting termination meant that the damages must arise out of the contract repudiation. Summary judgment entered for the plaintiff.
** NB: the construction contract the subject of this decision pre-dates the amendments to the CCA in December 2015 regarding enforcement.
MANCHESTER INDUSTRIAL HOLDINGS LIMITED v HAZELTON [2016] NZHC 211 (NZ High Court)
Application (by Manchester) for judicial review alleging errors of law by adjudicator in a determination under the Construction Contracts Act 2002. Judge found there had been an error of law in the adjudicator ruling that a payment schedule had to be contained in a single document, but despite this, the Court considered Manchester had still provided inadequate communications to constitute a payment schedule. Accordingly, application for judicial review dismissed.
CENTRAL LAKES HOMES LIMITED v CLARK [2016] NZDC 396 (NZ High Court)
Fixed price contract for construction of property by Central Lakes Homes. Determination by Building Disputes Tribunal ordering defendant to pay claimed sum. Plaintiff (Central Lakes) now seeking summary judgment against defendant. BDT adjudication determination upheld – Judge considered that the defendant had only raised factual disputes which had already been dealt with in the adjudication determination, and the fact that someone is aggrieved by a determination is not, of itself, sufficient for a Judge to revisit the factual scenario upon which a determination was made. Judgment for the plaintiff.
2015
R T VINCENT LTD v WATTS & HUGHES CONSTRUCTION LTD [2015] NZHC 424 10 March 2015 (NZ High Court)
DAVID ROSS PETTERSON AS LIQUIDATOR OF POLYETHYLENE PIPE SYSTEMS LIMITED (IN LIQUIDATION) v DAVID CHARLES BROWNE [2015] NZHC 866 29 April 2015 (NZ High Court)
V J MADSEN REIS AND H D LEVIN v DONOVAN DRAINAGE AND EARTH MOVING LIMITED [2015] NZHC 1081 20 May 2015 (NZ High Court)
CAN BUILD LTD v KIRKPATRICK and PURVIS as trustees of the LAURA KIRKPATRICK FAMILY TRUST [2015] NZHC 1161 27 May 2015 (NZ High Court)
GROYNES DEVELOPMENT (2012) LTD v COLLIS MURDOCH EARTHMOVERS LTD [2015] NZHC 1206 2 June 2015 (NZ High Court)
JAMON CONSTRUCTION LTD v BRICON ASBESTOS LTD [2015] NZHC 1926 13 August 2015 (NZ High Court)
MDS DEVELOPMENTS LIMITED v APPLEBY HOLDINGS LIMITED [2015] NZHC 2145 4 September 2015 (NZ High Court)
TEAK CONSTRUCTION LIMITED v ANDREW BRANDS LIMITED [2015] NZHC 2312 23 September 2015 (NZ High Court)
C.J. PARKER CONSTRUCTION LTD v KETAN & ORS [2015] NZHC 2421 5 October 2015 (NZ High Court)
HALEY CONSTRUCTION LIMITED v EVOLVING PROJECTS LIMITED [2015] NZHC 2490 12 October 2015 (NZ High Court)
LEE v WHANGAREI DISTRICT COUNCIL [2015] NZHC 2777 10 November 2015 (NZ High Court)
DHC ASSETS LIMITED v TOON (AS LIQUIDATOR OF VACO INVESTMENTS) LIMITED [2015] NZHC 140 12 February 2016 (NZ High Court)
2014
WEST CITY CONSTRUCTION LTD v HENRY DAVID LEVIN AND DAVID STUART VANCE AS LIQUIDATORS OF ST GEORGE DEVELOPMENTS LTD (IN LIQUIDATION) [2014] NZSC 183 15 December 2014 (NZ Supreme Court)
WATTS HUGHES CONSTRUCTION LIMITED v COMPLETE SITEWORKS COMPANY LIMITED [2014] NZCA 564 26 November 2014 (NZ Court of Appeal)
WAIORA TRADING LTD v O’SULLIVAN [2014] NZHC 304 26 February 2014 (NZ High Court)
Application for judicial review of adjudicator’s determination – respondent of adjudication arguably not party to the construction contract – arguments not assessed by the adjudicator – Adjudicator error – Judicial review.
SEALEY v CRAIG [2014] NZHC 520 12 March 2014 (NZ High Court)
Appeal against order striking out part of claim – inadequate legal advice for payment schedule – implied term in contract of retainer – actual loss.
SARDAN TRUSTEES LIMITED v MAGSON’S HARDWARE LIMITED HC AK CIV-2013-404-4684 [2014] NZHC 460 13 March 2014 (NZ High Court)
P3PEOPLE LIMITED v QS BUIILDING LIMITED [2014] NZHC 1455 26 June 2014 (NZ High Court)
SOL TRUSTEES LIMITED v GILES CIVIL LIMITED [2014] NZHC 1813 4 August 2014 (NZ High Court)
PEDESTAL LIMITED v CITY BUILD CONSTRUCTION LIMITED [2014] NZHC 1783 5 August 2014 (NZ High Court)
MARAC FINANCE LTD v BODY CORPORATE 361477 [2014] NZHC 1898 [12 August 2014] (NZ High Court)
CONCRETE STRUCTURES (NZ) LIMITED v NZ WINDFARMS LIMITED [2014] NZHC 2118 3 September 2014 (NZ High Court)
QUAY PARK ARENA MANAGEMENT LIMITED v GREAT LAKES REINSURANCE (UK) PLC [2014] NZHC 2204 11 September 2014 (NZ High Court)
SOL TRUSTEES LTD v GILES CIVIL LTD CA 4542014 [2014] NZCA 539 10 November 2014 (NZ High Court)
WATTS & HUGHES CONSTRUCTION LIMITED v COMPLETE SITEWORKS COMPANY LIMITED CA444 2014 [2014] NZCA 564 26 November 2014 (NZ High Court)
LEIGHTON CONTRACTORS PTY LIMITED v SHARP CONCRETE CUTTERS & DRILLERS LIMITED [2014] NZHC 3090 5 December 2014 (NZ High Court)
COMPLETE CONSTRUCTION LIMITED v LYON ELECTRICAL LIMITED [2014] NZHC 3116 8 December 2014 (NZ High Court)
2013
BLAIN v EVAN JONES CONSTRUCTION LTD – NZCA 680 December 2013 (NZ Court of Appeal)
Application to set aside third party notice – does the law recognize a cause of action in negligence against the builder of a commercial building – do the terms of the contract consist of the respondent owing a duty of care in tort – whether the Construction Contracts Act dispute procedure means that obligations are to be governed exclusively by the contract.
ADDIS CONTAINERS LTD v ALUMINIUM CITY LTD CIV-2012-004-1745 24 May 2013 (NZ District Court)
summary judgment – construction contract – whether shipping containers formed part of the land – natural justice
Application opposed on basis contract was not a construction contract to which the CCA applies (shipping containers) and that the adjudicator failed to observe the rules of natural justice in failing to take into account the respondent’s protests as to jurisdiction. Temporary nature of containers nor relevant given that construction work may be permanent or not. On the facts the Court found that the containers came within the meaning of construction work under the CCA. The District Court does not possess the jurisdiction to review a determination where allegations of breaches of natural justice are made by a party (only the High Court may do so). Application opposing entry of determination as judgment dismissed.
DTB CONSTRUCTION LIMITED v HOLDGATE HC AK CIV-2013-404-426 26 February 2013 (NZ High Court)
Application for stay of insolvency proceedings Canam Construction Ltd v Ormiston Hospital Investments Ltd – Service Donovan Drainage and Earthworking Ltd v Kaipara District Council, Bills v Arnold Jensen (2005) Ltd – Section 79 Volcanic Investments Ltd v Dempsey & Wood Civil Contractors Ltd – Unfairness
HERBERT CONSTRUCTION COMPANY LIMITED v REINFORCING STEEL & MESH LIMITED HC NP CIV-2012-441-602 8 March 2013 (NZ High Court)
Application to set aside statutory demand – Genuine and substantial dispute – Insolvency – CCA application George Developments Ltd v Canam Construction Ltd – Payment Claim – Payment due date Winslow Properties Ltd v Wooding Construction Ltd, Loveridge Ltd v Watson Construction Ltd, McAlpine Hussman Ltd v Cooke Industries Ltd – Payment Schedule Marsden Villas Ltd v Wooding Construction Ltd.
HOLDGATE (TA JR CONSTRUCTION) v DTB CONSTRUCTION LIMITED HC AK CIV-2013-404-426 8 March 2013 (NZ High Court)
Costs – Section 24 Volcanic Investments, Laywood v Homes Construction Wellington Ltd
GREY DISTRICT COUNCIL v BLAIN HC GY CIV-108-000060 CIV-418-000123 19 March 2013 (NZ High Court)
Application to set aside third party notice and summary judgement notice – Indemnity – Concurrent liability.
GILLIES ELECTRICAL & REFRIGERATION LIMITED v AL-MARIDI HC RT CIV-2012-463-000640 20 March 2013 (NZ High Court)
Application to set aside statutory demand – Payment claim – Payment schedule – Estoppel – Section 70 – Substantial dispute – Set-off/counterclaim.
HUTT CITY COUNCIL v THE LOWER HUTT DISTRICT COUNCIL HC WN CIV-485-001662 10 April 2013 (NZ High Court)
Property suspension – Council authority – Judicial review – ‘Land’ definition – ‘Construction work’ definition from CCA.
HOLDGATE (TA JR CONSTRUCTION LIMITED) v DTB CONSTRUCTION LIMITED HC AK CIV-2013-404-426 22 April 2013 (NZ High Court)
Costs – Primary relief Sunglass Hut New Zealand Ltd v Amtrust Properties Ltd
MCCLOY V MANUKAU INSTITUTE OF TECHNOLOGY HC AK CIV-2013-404-001526 1 May 2013 (NZ High Court)
ENERGY EFFICIENT HEALTHY HOMES LIMITED v GREENWOOD NATURAL LIMITED HC AK CIV-2013-404-1083 21 May 2013 (NZ High Court)
Application to set aside statutory demand – Service – Nullity
CAPITAL CONSTRUCTION LTD v PRIME COMMERCIAL LTD HC WG CIV-2013-485-000879 5 August 2013 (NZ High Court)
Application to set aside statutory demand – Payment claim – Set-off, Counter claim Volcanic Investments Ltd v Dempsey & Wood Civil Contractors
Ltd – Section 79 Laywood v Holmes Construction Wellington Ltd – Oppressive/unfair proceeding
CMP CONSTRUCTION LTD v ALUMINIUM TECHNOLOGY LTD HC AK CIV-2013-404-2692 23 September 2013 (NZ High Court)
Application to set aside statutory demand – Entitlement to revised claims – Payment schedule Marsden Villas Ltd v Wooding Construction Ltd – Legal effects of a void contract.
ELLIS BUILD 2008 LTD v NZ CHEMICAL CARE & STORAGE LTD HC AK CIV-2013-404-03143 3 December 2013 (NZ High Court)
Right to adjudication – Section 76 – Jurisdiction
FINESSE RESIDENTIAL LTD v VASANTHAN HC AK CIV-2013-404-3026 3 December 2013 (NZ High Court)
Application for summary judgment – Construction contract definition.
2012
TAUBER & ORS v THE COMMISSIONER OF INLAND REVENUE COA CA564/2011 7 September 2012 (NZ Court of Appeal)
Judicial review of decision for execution of warrants of seized documents.
JFC BUILDERS PTE LTD v LIONCITY CONSTRUCTION CO PTY LTD 8 August 2012 (Singapore High Court)
BOAT HARBOUR HOLDINGS LTD v STEVE MOWAT BUILDING LTD COA CA146/2011 13 July 2012 (NZ Court of Appeal)
Caveatable interests – Remedial constructive trust Fortex Group Ltd (in rec and liq) v MacIntosh
MCNAMARA AND ORS v AUCKLAND CITY COUNCIL SC 852010 9 May 2012 (NZ Supreme Court)
MARLBOROUGH DISTRICT COUNCIL v ALTIMARLOCH JOINT VENTURE LIMITED SC 33/2010 5 March 2012 (NZ Supreme Court)
SCANDLE v FAR NORTH DISTRICT COUNCIL COA CA619 2010 1 MARCH 2012 (NZ Court of Appeal)
LOVERIDGE LIMITED V WATTS & HUGHES CONSTRUCTION LTD HC TAU CIV-2011-470-275 16 February 2012 (NZ High Court)
Costs – Awarded to the defendant in part
FLAT BUSH PROPERTY LIMITED (IN LIQUIDATION) V POLGLASE HC CIV-2011-404-1328 21 February 2012 (NZ High Court)
Security of costs – Awarded to defendant – Court’s discretion
CAPITAL CONSTRUCTION LIMITED v LUXTA LIMITED HC WN CIV 2011-485-1622 23 February 2012 (NZ High Court)
Application for award as judgement – Discretion Gold and Resource Developments (NZ) Ltd v Doug Hood Ltd – Stand down period
HERBERT CONSTRUCTION COMPANY LIMITED V P I ALEXANDER, B E ALEXANDER, M J MOLLIER AND MP WARD HC NAP CIV-2011-441-500 29 February 2012 (NZ High Court)
Costs Auckland Waterproofing Ltd v TPS Consulting Ltd – Indemnification Westpac Banking Corporation v Topless – Awarded to plaintiff
GONVILLE SERVICE STN 1970 LIMITED v PETROLEUM SOLUTIONS LIMITED HC WANG CIV-2011-483-144 9 March 2012 (NZ High Court)
Application to set aside statutory demand – Not granted
GILLIES ELECTRICAL & REFRIGERATION LIMITED v MOHAMMAD AL-MARIDI HC ROT CIV 20 MARCH 2012 (NZ High Court)
MCALPINE HUSSMANN LIMITED v COOKE INDUSTRIES LIMITED HC AK CIV 2011-404-5663 16 March 2012 (NZ High Court)
Application to set aside statutory demand – Not granted – Payment schedule – Must specify amount – Payment claim – Reference to order number sufficient identification for construction work
ABSOLUTE QS LIMITED v ASCOT ALUMINIUM LIMITED HC AK CIV 2011-404-006062 4 April 2012 (NZ High Court)
Application to set aside statutory demand – Agency – Not granted
SOUTH PACIFIC INDUSTRIAL LIMITED v UNITED TELECOMS LIMITED HC WHA CIV 2012-488-202 13 April 2012 (NZ High Court)
Application for freezing order – International
SOUTH PACIFIC INDUSTRIAL LIMITED v UNITED TELECOMS LIMITED HC WHA CIV 2012-488-202 16 April 2012 (NZ High Court)
SOUTH PACIFIC INDUSTRIAL LIMITED v UNITED TELECOMS LIMITED HC WHA CIV 2012-488-202 26 April 2012 (NZ High Court)
MCALPINE HUSSMANN LIMITED v COOKE INDUSTRIES LIMITED HC AK CIV-2011-404-5663 7 May 2012 (NZ High Court)
Costs – Awarded to plaintiff
BOUNTIFUL HOLDINGS LIMITED v UNIVERSITY OF AUCKLAND HC AK CIV-2012-404-581 8 May 2012 (NZ High Court)
Application to set aside statutory demand – No set-off clause Brown’s Real Estate Ltd, Simply Logistics Ltd v Real Foods Ltd
SOUTH PACIFIC INDUSTRIAL LIMITED v UNITED TELECOMS LIMITED HC WHA CIV 2012-488-202 9 May 2012 (NZ High Court)
OSBORNE AND OSBORNE v AUCKLAND CITY COUNCIL (NOW AUCKLAND COUNCIL) COA CA841/2011 17 May 2012 (NZ High Court)
Application for leave to appeal from a decision of the HC of no right to appeal under the WHRS Act Siemer v Heron – Not granted.
STERLING PARK DEVELOPMENTS LIMITED v DOWNER NEW ZEALAND LIMITED DC CIV-2010-016-000481 28 May 2012 (NZ High Court)
VEGAR-FITZGERALD v NOYCE AND MAWDSLEY HC AK CIV-2012-404-1683 29 May 2012 (NZ High Court)
Application to maintain finance agreement
RJ VIALL BUILDERS LIMITED v PARTRIDGE HC AK CIV-2012-404-1482 6 July 2012 (NZ High Court)
Costs – Awarded to plaintiff
BODY CORPORATE 173457 v DESPY HC AK CIV-2010-044-999 19 July 2012 (NZ High Court)
Summary judgment for levies
239 QUEEN STREET DEVELOPMENTS LIMITED v WATTS & HUGHES CONSTRUCTION LIMITED HC AK CIV-2012-404-2159 19 July 2012 (NZ High Court)
Application for statutory demand – Immediate liquidation order – ‘Pay now argue later’ arguments not absolute
SEATING SYSTEMS LIMITED v KIDSON CONSTRUCTION LIMITED HC NEL CIV-2012-442-000013 30 August 2012 (NZ High Court)
Payment schedule – Email – Non-compliance with requirements – Cannot set-aside statutory demand because of substantial dispute
READY MARK LIMITED v JILL GRANT COA CA440/2011 28 September 2012 (NZ High Court)
Judicial review
H&H CONTRACTORS LTD v LEIGHTON CONTRACTORS PTY – HC 19 November 2012 (NZ High Court)
SPURR v CRT FUEL LIMITED HC TIM CIV-2012-476-000237 7 December 2012 (NZ High Court)
Application to set aside bankruptcy notice – Agreement to exclude crossclaims
2011
REES v FIRTH COA CA328/2011 20 December 2011 (NZ Court of Appeal)
Judicial review of determination Speymill Contracts Ltd v Baskind – Standing
DONOVAN DRAINAGE & EARTHMOVING LIMITED v HALLS EARTHWORKS LIMITED (IN LIQUIDATION) COA CA403/2011 29 August 2011 (NZ Court of Appeal)
Application for second appealREES v FIRTH COA CA328/2011 29 July 2011 (NZ Court of Appeal)
Unconditional stay granted – Scope of judicial reviewP R JOLLANDS AND R T JOLIFFE v MITCHILL COMMUNICATIONS LTD HC AK CIV-2009-404-008146 18 January 2011 (NZ High Court)
InsolvencyOGILVIE v L STEVENS BUILDERS LIMITED CIV-2010-063-000299 18 February 2011 (NZ District Court)
HERON’S FLIGHT LTD v NZ PROPERTIES INTERNATIONAL LTD HC AK CIV-2010-404-005878 7 February 2011 (NZ High Court)
Application for liquidation of defendant – Section 310 of Insolvency Act overrides CCAPAUL MARK COKER v PHIL BROWN BUILDING LIMITED HC BLE CIV 2010-406-235 17 February 2011 (NZ High Court)
Payment claims – Progress paymentsSTEVE MOWAT BUILDING & CONSTRUCTION LIMITED v BOAT HARBOUR HOLDINGS LIMITED HC CHCH CIV 2010-409-002698 17 February 2011 (NZ High Court)
Caveat – Prejudicial dispositionSTOLLERY & ORS v FRUIT 2GO LIMITED (FORMERLY MOYLE CONSTRUCTION LIMITED) HC TAU CIV-2009-470-283 10 March 2011 (NZ High Court)
Costs – Equal apportionmentCONCRETE STRUCTURES (NZ) LTD v INFRAMAX CONSTRUCTION LTD HC HAM CIV 2010-419-385 30 March 2011 (NZ High Court)
Costs – Awarded to plaintiffPAUL MARK COKER v PHIL BROWN BUILDING LIMITED HC WN CIV 2010-406-235 2 May 2011 (NZ High Court)
Costs – Reduced amount awarded to plaintiffHOLMES CONSTRUCTION WELLINGTON LTD v FIRTH HC AK CIV-2010-404-007674 3 May 2011 (NZ High Court)
Estoppel – Res judicata – Jurisdiction of ‘party’ – Collateral contractsCHOW GROUP LTD v JOHN GEOFFREY WALTON AND CLEARWATER CONSTRUCTION LTD CIV-2011-404-3148 9 June 2011 (NZ High Court)
Interim relief declined Concrete Structures (NZ) Ltd v Palmer, Construct Interiors v JonesPayment claim – Contract payment due date for payment – Payment otherwise due being payable – Bad faith Cube Building Solutions Ltd v King – Payment schedule – Must specify reasons and amount – Breach of natural justice – Discretionary relief
INCONSTRUCTION LIMITED v H GLAUSER HC WN CIV-2011-485-443 14 June 2011 (NZ High Court)
Application to set aside bankruptcy notice Laywood v Holmes Construction Ltd – Not granted.READY MARK LIMITED v JILL GRANT HC AK CIV 2010-404-008264 17 June 2011 (NZ High Court)
Summary judgement; granted, reasonable defence. Potential claim as residential owner under CCANCB 2000 LTD v HURLSTONE EARTH MOVING LTD civ-2010-404-008096 23 June 2011 (NZ High Court)
Application to set aside statutory demand – Payment claim invalid – Set aside – Payment schedule – Letter – Content non-compliant with technicalities but valid – Course of conduct – Service – Section 80 not mandatory requirements
CHOW GROUP LIMITED v CLEARWATER CONSTRUCTION LIMITED HC AK CIV-2011-404-3382 30 June 2011 (NZ High Court)
Costs – Awarded to plaintiffWAIPIPI SCHOOL BOARD OF TRUSTEES v XTREMEBUILD LIMITED (IN LIQ) HC AK CIV-2010-404-4874 1 July 2011 (NZ High Court)
Costs – Awarded to defendantHOLMES CONSTRUCTION WELLINGTON LIMITED v FIRTH HC AK CIV-2010-404-007674 6 July 2011 (NZ High Court)
Application to stay judgement – Injuriously affected – Granted conditionallyCHOW GROUP LIMITED v WALTON HC AK CIV-2011-404-3148 14 July 2011 (NZ High Court)
Early fixture applicationHERBERT CONSTRUCTION COMPANY LIMITED v TUCK CONTRACTORS LIMITED (IN LIQUIDATION) HC NAP CIV-2011-441-54 22 July 2011 (NZ High Court)
Application to set aside statutory demand – Not grantedCHOW GROUP LIMITED v WALTON HC AK CIV-2011-404-003148 19 August 2011 (NZ High Court)
Judicial review of determination – Bad faith Cube Buildings Solutions Ltd v King – Payment schedule – Content – Natural justice Construct Interiors NZ Ltd v JonesM Van der Wal Builders & Contractors Limited v Walker CIV 2011-004-000083 26 August 2011 (NZ High Court)
Associate Judge Christianson
construction contract – whether contract entered into – jurisdiction – summary judgment – judicial review – debt due – genuinely arguable
Adjudicator determined a binding contract had been entered into and breached by the defendants. Summary judgment was declined on the basis that there was an arguable case that a construction contract had not been concluded and it followed therefore that there was an arguable case the adjudicator had no jurisdiction for the determination he made.
AMSTAR INTERIORS LIMITED v AIS INSULATION LIMITED (IN LIQUIDATION) HC AK CIV-2011-404-3320 8 September 2011 (NZ High Court)
Set aside statutory demand; partially granted; invalidity of payment schedule, substantial dispute provenSIMPLY LOGISTICS LIMITED V REAL FOODS LIMITED HC AK CIV-2011-404-3497 14 September 2011 (NZ High Court)
Application to set aside statutory demand – No set-off contract clause Grant v NZMC Ltd, Browns Real Estate Ltd v Grand Lakes Properties Ltd – No clause concerning counterclaim and cross-demand – GrantedLOVERIDGE LIMITED V WATTS & HUGHES CONSTRUCTION LTD HC TAU CIV-2011-470-275 29 September 2011 (NZ High Court)
Application for summary judgment – Payment claim – Invalid due date – Cannot amend defect through subsequent payment claimTHREE CHICKS LIMITED V NZ BUILDING AND PROJECTS LIMITED HC AK CIV-2011-404-005417 30 September 2011 (NZ High Court)
Application to remove caveatHERBERT CONSTRUCTION COMPANY LIMITED V PI ALEXANDER, BE ALEXANDER, MJ MOLLIER AND MP WARD IN PARTNERSHIP TRADING AS THE CHRISTIE CROWN PARTNERSHIP HC NAP CIV-2011-441-500 21 October 2011 (NZ High Court)
Application for summary judgment – Payment claim – Payment schedule – Failure to issue does not alter payment due dateCHEN V ZHONG & ANOR HC AK CIV 2010-404-001995 14 November 2011.PDF
ASB BANK LIMITED V STEVENS & Anor HC AK CIV-2011-404-1621 11 November 2011 (NZ High Court)
Application for set-off and counterclaim under PLABRC LIMITED V R PATEL & NG PATEL HC WN CIV-2011-485-1322 11 November 2011 (NZ High Court)
Application to set aside bankruptcy notice – Set-off not a liquidated sum or disputed – Section 79 – Not granted – Amount in bankruptcy notice amended to be GST exclusiveREADY MARK LIMITED V GRANT HC AK CIV-2010-404-008264 18 November 2011 (NZ High Court)
Judicial review – Strike-out principles – Issue estoppelWESTPARK MARINA LIMITED V AUTOMATED SOLUTIONS LIMITED HC AK CIV-2011-404-7295 30 November 2011 (NZ High Court)
Application to set aside statutory demand – Court discretion – Construction work definition not – Installation of softwareCLEARWATER CONSTRUCTION LIMITED v CHOW GROUP LIMITED HC WN CIV-2011-485-001320 2 December 2011 (NZ High Court)
Costs – Awarded to plaintiffCAMBRIA COMMERCIAL 2009 LIMITED V MILTON CHARLES PEDLEY AND JEAN MARGOT PEDLEY HC PMN CIV-2011-454-457 7 December 2011 (NZ High Court)
Summary judgment – Addition of ‘parties’EXAPL LTD and ANOR v PACT GROUP (NZ) LTD HC AK CIV-2011-404-005919 12 December 2011 (NZ High Court)
Expert Determination – Application for stay of proceedings – Completion statementsSTEPHEN MACKFALL V GORDON AND KATHRYN BEATTIE HC WN CIV 2011-485-82 [22 December 2011] (NZ High Court)
Weathertight Homes Tribunal appeal – Individual liability2010
CONCRETE STRUCTURES (NZ) LIMITED v NZ WINDFARMS LIMITED CA CA239/2009 4 October 2010 (NZ Court of Appeal)
Notice of adjudication – Costs – Awarded to the defendantBROWNS REAL ESTATE LIMITED v GRAND LAKES PROPERTIES LIMITED CA157/2010 20 September 2010 (NZ Court of Appeal)
Application to set aside statutory demand (not CCA) – Reference to Laywood v Homes Construction Wellington Ltd.DORIC INTERIORS & CONSTRUCTION LIMITED (IN LIQUIDATION) v MAGSONS HARDWARE LIMITED AND ANOR CA CA547/2009 1 June 2010 (NZ Court of Appeal)
Statutory demand – Company now in liquidation – Appeal as to parties to the contract – Substantial dispute – Construction Contracts Act regime – Was there a construction contract – Appeal dismissed
Origin Energy Resources (Kupe) Limited v Tenix Alliance New Zealand Limited HC AK CIV 2010-404-00106 19 January 2010 (NZ High Court)
Potter JApplication for interim injunction – Jurisdiction of adjudicator – Referral of disputes to arbitration – International Arbitration
Origin contended that the dispute could not be referred to adjudication as the contract provided for disputes to be referred to arbitration which would be an international arbitration as defined in Schedule 1 of the Arbitration Act 1996. It was argued that the question of jurisdiction ought to be determined by the High Court. Potter J considered that the appropriate procedure was for the matter to proceed to adjudication before the appointed adjudicator, for the parties to make their submission to the adjudicator and for him to determine the issue of jurisdiction.
FOGGO AND ORS V R J MERRIFIELD LIMITED HC CHCH CIV-2009-409-000605 8 February 2010 (NZ High Court)
79 MANNERS STREET LIMITED V BJ PYE SHEET METALS LIMITED HC WN CIV-2008-485-1907 10 February 2010 (NZ High Court)
LUXTA LIMITED V CAPITAL CONSTRUCTION LIMITED HC WN CIV-2009-485-1957 10 February 2010 (NZ High Court)
CLAVERDON DEVELOPMENTS LTD V HOUSING NEW ZEALAND LTD HC AK CIV-2009-404-007159 19 February 2010
ANDREW LAWSON BUILDING LTD V JP SWENNEN & V GIELEN HC BLE CIV-2009-406-286 19 February 2010 (NZ High Court)
HOUSING NEW ZEALAND LIMITED V CLAVERDON DEVELOPMENTS LIMITED HC AK CIV-2009-404-6292 19 February 2010
YUN CORPORATION LIMITED V YQT LIMITED (FORMERLY CANAM CONSTRUCTION (1955) LIMITED) HC AK CIV 2009-404-007656 26 February 2010 (NZ High Court)
NEWSOME V RAY DENNIS CONSTRUCTION LIMITED HC HAM CIV-2009-419-001467 9 March 2010 (NZ High Court)
MACENNOVY TRUST LTD V SEFTON CONSTRUCTION LTD (IN LIQUIDATION) HC AK CIV-2009-404-007659 28 April 2010 (NZ High Court)
DONOVAN DRAINAGE & EARTHMOVING LTD V HALLS EARTHWORKS LTD (IN LIQUIDATION) HC AK CIV-2010-404-29 3 May 2010 (NZ High Court)
CENTRAL HOUSE MOVERS LIMITED V DAVID RENNIE RUSSELL AND KAREN LEANNE RUSSELL HC PMN CIV 2010-454-000103 20 May 2010 (NZ High Court)
Costs – Awarded to the plaintiff – Construction work definition – Includes relocation of villaDRIFTWOOD DEVELOPMENTS LIMITED V PIMLICO PROPERTIES LIMITED HC CHCH CIV-2010-409-000301 3 June 2010 (NZ High Court)
Application to set aside statutory demand – Court’s discretionLUND SOUTH LIMITED V AAA TOUGH PLUMBING & DRAINAGE LIMITED HC DUN CIV 2009 412 000949 4 June 2010 (NZ High Court)
Application to set aside default statutory demand – Failure to appear – Incorrect defendant – Parties’ conductJACK TAGGART AND PATRICIA TAGGART V JIM VISSER LIMITED HC AK CIV-2010-404-3149 30 July 2010 (NZ High Court)
Application to set aside determination – Court intervention Gold and Resource Developments (NZ) Ltd v Doug Hood LtdCANAN CONSTRUCTION LTD V ORMISTON HOSPITAL INVESTMENT LTD HC AK CIV 2010-404-000291 10 August 2010 (NZ High Court)
Liquidation of defendant – Application to stay proceedings Taxi Trucks Ltd v Nicholson – Genuine/substantial dispute – Section 79 – Irretrievable prejudice Concrete Structures (NZ) Ltd v Palmer, Yun Corporation Ltd v YQT
LtdMOYLE CONSTRUCTION LIMITED V STOLLERY & ORS HC TAU CIV 2009-470-889 12 August 2010 (NZ High Court)
Costs – Awarded to plaintiff – InterestDONOVAN DRAINAGE & EARTHMOVING LTD V KAIPARA DISTRICT COUNCIL HC WHA CIV-2010-488-000319 18 August 2010 (NZ High Court)
Summary judgement – Service – Equates ‘giving a schedule’ with ‘providing a schedule’ – Postal rule
HERBERT CONSTRUCTION COMPANY LIMITED V MICHAEL FEATHERSTON TOOGOOD HC NAP CIV-2010-441-283 20 August 2010 (NZ High Court)
Summary judgement – Service – No requirement for address to payer – Section 80 not mandatory requirements – Costs – Reduction due to lack of proportionality – Payment claim – Payment scheduleCONSTRUCT INTERIORS NZ LIMITED V JONES AND ANOR HC AK CIV-2010-404-897 23 August 2010 (NZ High Court)
Application for judicial review of determinationMAGSONS HARDWARE LIMITED AND ANOR V PRITISH PATEL AND ANOR HC AK CIV-2010-404-2891 10 September 2010 (NZ High Court)
Costs – Equal apportionmentREDICAN ALLWOOD LIMITED V RAB CONTRACTING LIMITED HC WN CIV-2010-485-912 9 November 2010 (NZ High Court)
Costs – Claim for indemnity – Awarded to plaintiffCONCRETE STRUCTURES (NZ) LTD V INFRAMAX CONSTRUCTION LTD HC HAM 9 November 2010 (NZ High Court)
Summary judgement – Determination does not create an issue estoppel or activate the doctrine of res judicata Marsden Villas Ltd v Wooding Construction Ltd, Donovan Drainage and Earthmoving Ltd v Halls Earthworks Ltd – Use of determination in subsequent court proceedings – Confidentiality – Payment schedule – Nil value – Invalid – Costs – Cannot include prior adjudication costs – Awarded to plaintiff
DONOVAN DRAINAGE & EARTHMOVING LTD V HALLS EARTHWORKS LTD HC AK CIV-2010-404-000029 10 November 2010 (NZ High Court)
Judicial review – Determination – Issue estoppel – Doctrine of res judicata – Costs – Indemnity costs – Increased costs judgement Bradbury v Westpac Banking Corp
REAL COOL HOLDINGS LTD & REAL COOL LTD V PAGE & MACRAE LTD HC TAU CIV-2010-470-685 12 November 2010 (NZ High Court)
InterestKARIITI LTD V DONOVAN DRAINAGE & EARTHMOVING LTD HC WHA CIV-2010-488-000613 19 November 2010 (NZ High Court)
Interim order – Risk of non-payment Total M and E Services Ltd v ABB Building Technologies, Jerscel Engineering Ltd v Breen Property Ltd – Strength of payer’s cause Wilsons (NZ) Portland Cement Ltd v Gatx-Fuller Australasia Pty LtdTHE COMMISSIONER OF INLAND REVENUE V THE FISHING COMPANY LTD HC AK CIV-2010-404-004955 14 December 2010 (NZ High Court)
Application for liquidation of defendant – GST input credit claim – ‘Pay first, argue later’.CONCRETE STRUCTURES (NZ) LTD V INFRAMAX CONSTRUCTION LTD HC HAM CIV-2010-419-909 17 December 2010 (NZ High Court)
QuantumLUXTA LIMITED V PARAGON BUILDERS LIMITED HC WN CIV-2010-485-1825 17 December 2010 (NZ High Court)
Application to set aside statutory demand – Section 79 does not prohibit reduction of the amount claimed/set-off – Service – Section 80 not mandatory requirements.2009
HEB CONTRACTORS LTD v REDHILL DEVELOPMENTS (NZ) LTD CIV-2009-044-1266 26 November 2009 (NZ District Court)
DONOVAN DRAINAGE AND EARTHMOVING LTD v STEININGER CIV-2009-027-000035 27 October 2009 (NZ District Court)
DONALD JOHN MACRITCHIE v TRUSTEES EXECUTORS LTD CIV-2009-085-359 12 August 2009 (NZ District Court)
BLENHEIM BUILDING CENTRE LTD v DALLAS HEMPHILL CIV-2009-006-000034 7 August 2009 (NZ District Court)
IQ HOMES LTD v GAEME NEIL SMITH, RICHARD DOUGLAS FISHER AND BELINDA MAY FISHER AS TRUSTEES OF THE FISHER FAMILY TRUST CIV-2209-009-1314 31 July 2009 (NZ District Court)
GRANT HAMILTON CONSTRUCTION LTD v TRUSTEES OF THE JAPEK TRUST CIV-2008-019-1630 25 March 2009 (NZ District Court)
TROAKE WALLBOARDS SERVICES LIT v TNR CONTRACTING LTD CIV-2008-004-002235 19 January 2009 (NZ District Court)
QUEENSTOWN LAKES DISTRICT COUNCIL v CHARTERHALL TRUSTEES LTD CA CA441/2008 25 August 2009 (NZ Court of Appeal)
LAYWOOD AND REES v HOLMES CONSTRUCTION WELLINGTON LTD SC 23/2009 15 May 2009 (NZ Supreme Court)
IAN LAYWOOD AND GARY REES v HOLMES CONSTRUCTION WELLINGTON LIMITED CA CA83/2008 25 February 2009 (NZ Court of Appeal)
HAWKINS CONSTRUCTION LTD V ECOSSE AFRIQUE ENTERPRISES LTD HC WN CIV 2008-485-2327 25 February 2009 (NZ High Court)
INVENT SOLUTIONS LIMITED V CHAN DEVELOPMENTS TRUSTEE LIMITED HC WN CIV 2008-485-2834 1 April 2009 (NZ High Court)
Application for Summary Judgment – Payment Claims – Payment Schedule – Requirements for valid Payment ScheduleNZ WINDFARMS LIMITED V CONCRETE STRUCTURES (NZ) LIMITED HC ROT CIV 2008-463-566 7 April 2009 (NZ High Court)
SOLUTION TEXTURES LIMITED V COLEMAN HC AK CIV 2009-404-001052 23 April 2009 (NZ High Court)
Patel v Pearson Group Limited CIV 2008-485-2571 24 April 2009 (NZ High Court)
Opposition to application to enforce judgment – jurisdiction of adjudicator – correct parties to contract – extension of jurisdiction – application refused
Appeal from District Court decision that a determination should be entered as a judgment. Appellant argued that entry ought to have been refused because there was no contract between her and Pearson Group Limited, but rather, that the builder was a Mr Pearson, the director and principal shareholder of Pearson Group Limited, the latter company only having been incorporated after the relevant contract was entered into. The Court held the District Court has jurisdiction to refuse to enter a determination as a judgment on the ground that there is no contract between the parties to the adjudication. However, the Judge was right to enter the determination as a judgment in this case, for the parties had conferred jurisdiction on the adjudicator.
THYLACINE CONSTRUCTION V CAPITAL MERCHANT FINANCE LIMITED AK CIV 2008-404-7683 7 May 2009 (NZ High Court)
NASH PROPERTIES LIMITED V HARRIS HOLDINGS CONSTRUCTION LIMITED HC AK CIV 2009-404-001013 11 June 2009 (NZ High Court)
GREYS AVENUE INVESTMENTS LTD V HARBOUR CONSTRUCTION LTD HC AK CIV 2009-404-002026 12 June 2009 (NZ High Court)
SPARK IT UP LIMITED V DIMAC CONTRACTORS LIMITED AND ANOR HC WN CIV-2008-485-1706 12 June 2009 (NZ High Court)
SOLUTION TEXTURES LIMITED V COLEMAN AND COLEMAN HC AK CIV 2009-404-001052 1 July 2009
MUDGWAY V THE WINDOW COMPANY (2003) LIMITED HC AK CIV 2008-404-5818 1 July 2009 (NZ High Court)
PLIMMERTON COURTYARD LIMITED V MA FRANKLIN HC WN CIV 2008-485-2613 2 July 2009 (NZ High Court)
GOODACRE V PACIFIC ABODE HOMES (2004) LIMITED HC AK CIV-2009-404-002164 2 July 2009
PLIMMERTON COURTYARD LIMITED V KEITH RICHARD HUNTINGTON AND ANOR HC WN CIV 2009-485-772 14 July 2009
HOLMES CONSTRUCTION WELLINGTON LTD V REES HC AK CIV 2006-404-004219 17 July 2009 (NZ High Court)
REDHILL DEVELOPMENT (NZ) LTD AND ORS V GREEN AND ANOR HC AK CIV-2009-404-3784 5 August 2009 (NZ High Court)
MAGSONS HARDWARE LIMITED V DORIC INTERIORS & CONSTRUCTION LIMITED HC AK CIV 2008-404-006861 10 August 2009 (NZ High Court)
MACRITCHIE V TRUSTEES EXECUTORS LIMITED HC WN CIV-2009-485-1563 26 August 2009 (NZ High Court)
AKV2 LIMITED V AUCKLAND CONCRETE HOMES LIMITED HC AK CIV 2008-404-005972 31 August 2009 (NZ High Court)
FOGGO AND ORS V R J MERRIFIELD LIMITED HC CHCH CIV-2009-409-000605 21 September 2009 (NZ High Court)
AINSWORTH & COLLINSON LIMITED V G JOHN AND LD EDUMUNDS HC NAP CIV-2009-441-348 7 October 2009 (NZ High Court)
OROPI PARK LTD V A & R BETHLEHEM HEIGHTS LTD HC TAU CIV 2009-470-000287 8 October 2009 (NZ High Court)
REDHILL DEVELOPMENT (NZ) LTD AND ORS V R J GREEN AND ANOR HC AK CIV 2009-404-005417 22 October 2009 (NZ High Court)
CANAM CONSTRUCTION (1955) LTD V LAHATTE AND ANOR HC AK CIV 2009-404-461 30 October 2009 (NZ High Court)
GILL CONSTRUCTION COMPANY LIMITED V ROSS BUTLER HC WN CIV-2009-406-203 2 November 2009 (NZ High Court)
PETTERSON AS LIQUIDATOR OF KARA GROUP LTD (IN LIQUIDATION) V GATLEY AND ANOR HC AK CIV 2009-404-3117 9 November 2009 (NZ High Court)
BAVERSTOCK DEVELOPMENTS LIMITED V HOUSING NEW ZEALAND LIMITED HC AK CIV 2009-404-004917 23 November 2009 (NZ High Court)
SANDRA LYNN MORRISON-LOVE V THERMOCRETE LIMITED HC NWP CIV-2009-443-156 23 November 2009 (NZ High Court)
CONCRETE STRUCTURES (NZ) LIMITED V NEW ZEALAND WINDFARMS LIMITED AND ANOR HC CHCH CIV 2009 409 002301 24 November 2009 (NZ High Court)
NORTHERN HOLDINGS LIMITED V EAGLEN HOMES CONSTRUCTION LIMITED HC AK CIV 2009-404-004075 16 December 2009 (NZ High Court)
CUBE BUILDINGS SOLUTIONS LIMITED V THOMAS FREDERICK MAZLIN KING AND JUDITH RUTH KING HC CHCH CIV 2009 409 000034 17 December 2009 (NZ High Court)
2008
ARNOLD JENSEN 2005 LTD v BILLS & OTHERS CIV-2008-009-54 5 June 2008 (NZ District Court)
SHAUN DAMIEN JENKIN AND ANOR v JAMES A HANNA AND MARIA G HANNA CIV-2008-006-000101 23 June 2008 (NZ District Court)
STAINLESS FITTINGS & FABRICATIONS LTD v STAN ASH BUILDERS LTD CIV-2007-055-61 25 July 2008(NZ District Court)
PEARSON GROUP LIMITED v KALPANA PATEL CIV-2008-085-000962 24 October 2008 (NZ District Court)
AMC CONSTRUCTION LIMITED v FREWS CONTRACTING LIMITED CA CA145/2008 25 September 2008 (NZ Court of Appeal)
DONOVAN DRAINAGE AND EARTHMOVING LIMITED v HALLS EARTHWORKS LIMITED (IN LIQUIDATION) CA CA463/07 23 May 2008 (NZ Court of Appeal)
SHEREE ANN TAYLOR V MELLIS BUILDERS LTD HC NAP CIV 2007-441-411 11 February 2008 (NZ High Court)
T R WELSH AND ANOR V GUNAC SOUTH AUCKLAND LTD HC AK CIV 2006-404-7877 11 February 2008 (NZ High Court)
LAYWOOD & ANOR V HOLMES CONSTRUCTION WELLINGTON LIMITED HC AK CIV 2006-404-4152 15 February 2008 (NZ High Court)
PARKER CONSTRUCTION MANAGEMENT (NZ) LIMITED (IN LIQUIDATION) V HORIZON INVESTMENTS LIMITED HC WN CIV 2007-485-1963 20 February 2008 (NZ High Court)
M SPENCER V JED RICE BUILDING CONTRACTORS LIMITED HC AK CIV 2007-404-007539 21 February 2008 (NZ High Court)
HOLMES CONSTRUCTION WELLINGTON LTD V REES HC AK CIV 2006-404-004129 3 March 2008 (NZ High Court)
PAGE & MACRAE LIMITED V REAL COOL LIMITED AND REAL COOL HOLDINGS LIMITED HC TAU CIV 2007-404-5774 29 April 2008 (NZ High Court)
Enforcement of a determination – Jurisdiction – Charging Orders
CIVIL CONSTRUCTION GROUP LIMITED v DHUEZ LIMITED (IN REC) HC AK CIV-2006-404-4336 4 June 2008 (NZ High Court)
Payment claim – Failure to identify claim as under Act
TAYLER V LAHATTE AND ANOR HC AK CIV 2007-404-6843 24 June 2008 (NZ High Court)
SAINT-ALEXIS AND ANOR V HANNA HC BLE CIV 2008 406 108 24 June 2008 (NZ High Court)
SUGULOGOVALE & SANIELO SUANIU V HI-QUAL BUILDERS LIMITED HC AK CIV 2008-404-001576 26 June 2008 (NZ High Court)
BLOSSOM WOOL LIMITED V J W PIPER HC AK CIV 2008-404-000161 30 June 2008 (NZ High Court)
Application to set aside statutory demand – Genuine dispute – Arguable basis for dispute – Role of Court in statutory demand hearings – Requirements for a Contract – Costs awarded on 2B basis
BENTZEN FARM LTD V BAYLEY & ANOR HC WHA CIV-2008-488-653 22 September 2008 (NZ High Court)
BEVAN CHARLES BERG V FRANIX CONSTRUCTION LTD CIV 2008-404-003421 24 SEPTEMBER 2008
BILL HAMILTON AND ANOR V DISPUTES TRIBUNAL AND ANOR HC DUN CIV 2007-412-000861 8 October 2008 (NZ High Court)
BILLS AND ANOR V ARNOLD JENSEN (2005) LIMITED HC CHCH CIV 2008-409-001349 10 October 2008 (NZ High Court)
MA COLES V B BARNETT HC NAP CIV 2008-441-422 10 October 2008 (NZ High Court)
Application for Summary Judgment – Payment Claim – Payment Schedule – Charge up contract
PEARSON GROUP LIMITED V KALPANA PATEL DC WN CIV-2008-085-000962 24 OCTOBER 2008.pdf
AKV2 LIMITED V AUCKLAND CONCRETE HOMES LIMITED HC AK CIV 2008-404-005972 24 October 2008 (NZ High Court)
HEB CONTRACTORS LIMITED V REDHILL DEVELOPMENT(NZ) LIMITED HC AK CIV 2008-404-004398 7 November 2008 (NZ High Court)
ARNOLD JENSEN (2005) LIMITED V TREVOR JAMES BILLS AND ANOR HC CHCH CIV 2008-409-001349 26 November 2008 (NZ High Court)
AUMUA V LAMBETH CONSTRUCTION LIMITED (TRADING AS FIX IT BUILDING SERVICES) HC AK CIV 2008-404-007791 16 December 2008 (NZ High Court)
2007
ESOON LIMITED V GRIEVE AND JOLLANDS AND ANOR HC AK CIV 2006-404-6687 7 February 2007 (NZ High Court)
HOLMES CONSTRUCTION WELLINGTON LTD V REES & ANOR HC AK CIV 2006-404-4219 9 February 2007 (NZ High Court)
METALCRAFT INDUSTRIES LTD V CHRISTIE HC WHA CIV 2006-488-645 15 February 2007 (NZ High Court)
HORIZON INVESTMENTS LTD V PARKER CONSTRUCTION MANAGEMENT (NZ) LTD & BARBARA HUNT CIV 2007-485-332 4 APRIL 2007 (NZ High Court)
WINSLOW PROPERTIES LTD V WOODING CONSTRUCTION LTD HC AK CIV 2006-404-4969 4 April 2007 (NZ High Court)
BERGIN V NORTH SHORE CITY COUNCIL & ORS HC AK CIV 2006-404-2295 5 April 2007 (NZ High Court)
INSITE DESIGN & DEVELOPMENT LTD V JOHN SADLER HC AK CIV 2006-404-357 27 April 2007 (NZ High Court)
CORPORATE JET SERVICES LTD V RUSSELL STEWART WARD & ORS HC AK CIV 2006-404-357 18 May 2007 (NZ High Court)
SILVERPOINT INTERNATIONAL LTD & ORS V WEDDING EARTHMOVERS LTD HC AK CIV 2007-404-104 30 May 2007 (NZ High Court)
CARLOS CONCEPTS LTD V ROCKFORD CONSTRUCTION SERVICES LTD HC AK CIV 2006-404-6516 31 May 2007 (NZ High Court)
BLUEMOVER ONE LIMITED V THE BREEN CONSTRUCTION COMPANY LIMITED AND ORS HC DUN CIV 2006 412 001022 3 July 2007 (NZ High Court)
HALLS EARTHWORKS LIMITED (IN LIQUIDATION) V DONOVAN DRAINAGE AND EARTHMOVING LIMITED HC WHA CIV 2007-488-000144 18 July 2007 (NZ High Court)
HALLS EARTHWORKS LIMITED (IN LIQUIDATION) V DONOVAN DRAINAGE AND EARTHMOVING LIMITED HC WHA CIV 2007-488-000144 10 August 2007 (NZ High Court)
INSITE DESIGN & DEVELOPMENT LTD V JOHN CAMERON SADLER HC AK CIV2006-404-4528 13 September 2007 (NZ High Court)
COMMERCIAL RECEIVABLES LTD V WILLIAM JOHN THOMPSON & ORS HC AK CIV 2006-404-3036 14 September 2007 (NZ High Court)
AUCKLAND WATERPROOFING V TPS CONSULTING HC AK CIV-2007-404-005890 11 December 2007 (NZ High Court)
LAYWOOD & REES V HOLMES CONSTRUCTION WELLINGTON LIMITED HC AK CIV 2006-404-4152 13 December 2007 (NZ High Court)
2006
STEELE v SEREPISOS SC 68/2005 4 September 2006 (NZ Supreme Court)
sale and purchase agreement – jurisdiction of CCA – construction work under agreement – construction contractSALEM LTD v TOP END HOMES LTD CA CA169/05 4 April 2006 (NZ Court of Appeal)
CASATA v GENERAL DISTRIBUTORS LTD SC26.2005 SCNZ 15 March 2006 (NZ Supreme Court)
PARKER CONSTRUCTION MANAGEMENT (NZ) LTD V ADEN ELECTRICAL LIMITED HC WN CIV2005-485-1334, 13 February 2006 (NZ High Court)
JIAN HUA PROPERTY LTD V FREEMONT DESIGN & CONSTRUCTION LTD HC AK CIV 2005-404-5526 16 February 2006 (NZ High Court)
WILLIS TRUST COMPANY LTD AND ANOR V R JOHN GREEN AND ANOR HC AK CIV-2006-404-809 1 March 2006 (NZ High Court)
GULF HARBOUR INVESTMENTS LIMITED V Y GULF HARBOUR LIMITED (FORMERLY GLOBAL YACHT FINISHERS LIMITED) HC AK CIV 2006-404-386 16 March 2006 (NZ High Court)
JIAN HUA PROPERTY LTD V FREEMONT DESIGN & CONSTRUCTION LTD HC AK CIV 2005-404-5526 29 March 2006 (NZ High Court)
CONCRETE STRUCTURES (NZ) LTD V PALMER & ANR HC ROT CIV 2004-463-825 6 April 2006 (NZ High Court)
Stellar Projects Limited v Nick Gjaja Plumbing Limited HC AK CIV 2005-404-6984 10 April 2006 (NZ High Court)
Appeal against determination being entered as a judgment in the District Court – Section 72 District Courts Act 1947 – Section 73 and Section 74 of Construction Contracts Act – Appointment of Adjudicator by Authorised Nominating Authority
There was no standing to act as adjudicator as the proper appointment process had not been followed with no agreement made between the party nor any appointment made by an authorised nominating authority. Therefore, no basis for the entry of judgment in the District Court.
Appeal allowed. Determination has no effect in law or in equity.
TGC PROPERTIES LTD V FREEMONT DESIGN & CONSTRUCTION LTD HC AK CIV 2005-404-7165 10 April 2006 (NZ High Court)
Application to set aside statutory demand – Failure to issue a valid Payment Schedule – Does the Act prevent parties disputing that there is a debt due – Demand set aside on basis of dispute<?p>
DOWNER CONSTRUCTION (NEW ZEALAND) LTD V SILVERFIELD DEVELOPMENTS LTD HC 11 MAY 2006.pdf (NZ High Court)
QC CONSTRUCTION LTD V APT TILING LTD HC AK CIV 2006-404-00676 & CIV 2006-404-0086 19 May 2006 (NZ High Court)
WILLIS TRUST COMPANY LTD & ANOR V GREEN & ANOR HC AK CIV 2006-404-809 25 May 2006
MARSDEN VILLAS LTD V WOODING CONSTRUCTION LTD HC AK CIV 2006-404-2136 25 May 2006 (NZ High Court)
Suspension of Construction Work under the Act – Time period for issue of Payment Claims – Service of Claims and Schedules – Failure to provide valid Payment Schedule.
FREEMONT DESIGN & CONSTRUCTION LTD V NATURES VIEW JOINERY LTD TA NEBULITE WAIKATO HC HAM CIV 2006-419-269, 26 July 2006 (NZ High Court)
CONSTRUCTION SERVICE COMPANY (WELLINGTON) LTD (IN REC) V WELLINGTON WATERFRONT LTD HC WN CIV 2006-485-2287 13 September 2006 (NZ High Court)
Application for Summary Judgment – Principles of Summary Judgment – Failure to issue a Payment Schedule – Issue of Notice of Default – NZS3910:2003 – Section 79 of Construction Contracts ActKIZER BUILDERS LTD V OEC CONSTRUCTION LTD HC WN CIV 2006-485-2287 16 November 2006 (NZ High Court)
WINSLOW PROPERTIES LIMITED V WOODING CONSTRUCTION LIMITED HC AK CIV 2006-404-004969 14 December 2006 (NZ High Court)
WESTNORTH LABOUR HIRE LTD V S B PROPERTIES LTD HC AK CIV 2006-404-1858 19 December 2006 (NZ High Court)
MULES CONSTRUCTION LTD V WEDDING EARTHMOVERS LTD HC AK CIV 2006-404-4570 20 December 2006 (NZ High Court)
2005
SALEM LTD V TOP END HOMES LTD CA CA169/05 12 December 2005 (NZ Court of Appeal)
SALEM LTD v TOP END HOMES LTD CA 169/05 27 September 2005 (NZ Court of Appeal)
SOLIDCRETE TECHNOLOGY LTD v FIRST PACIFIC INVESTMENTS LTD CIV-2005-004-224 13 May 2005 (NZ District Court)
Payment claim – Form – Course of conduct – Payment schedule – ‘Indicate’ definition
GEORGE DEVELOPMENTS LTD v CANAM CONSTRUCTION LTD CA 244/04 12 April 2005 (NZ Court of Appeal)
CONCRETE STRUCTURES v PALMER HC CIV2004_463_825 6 APRIL 2005 (NZ High Court)
WEST CITY CONSTRUCTION LTD V TIMOTHY LAIRD EDNEY HC CIV-2005-404-001-066_1JULY2005 (NZ High Court)
MARSDEN VILLAS LIMITED V WOODING CONSTRUCTION LIMITED HC AK CIV-2006-404-002136 25may 2005 (NZ High Court)
TOP END HOMES v SALEM HC CIV 2005 488 000332 19 JULY 2005 (NZ High Court)
Plaintiff (builder) seeking summary judgment against defendant for work carried out on defendant’s property pursuant to a construction contract. Defendant failed to pay final payment claim sum submitted by plaintiff, or to submit a payment schedule within the time limit required under the CCA. Judgment in favour of plaintiff, summary judgment granted as Court satisfied that defendant had no reasonably arguable defence.
BROOKLYN HOLDINGS v ABLE HANDYMAN SERVICES HC CIV 2005-485-1362-13.SEPT.2005
10 GILMER LTD V TRACER INTERIORS AND CONSTRUCTION LTD HC WN CIV 2005-485-2009 6 December 2005 (NZ High Court)
Application to set aside a Statutory Demand – Relationship between s79 of Construction Contracts Act and s290 of Companies Act – Consequences of failure to issue a valid Payment Schedule
SCI DEVELOPMENT & CONSTRUCTION LTD V NZ BUILT LTD HC AK CIV 2005-404-3656 23 December 2005 (NZ High Court)
Application to set aside a statutory demand – s290 Companies Act 1993 – Counterclaim and set-off – Unliquidated Amount – s79 of Construction Contracts Act – Impact of ADR on Statutory Demand Process
2004
TUF PANEL CONSTRUCTION v CAPON CIV-2003-044-2801 15 March 2004 (NZ District Court)
O’CONNOR HOLDINGS LTD v ACE BUILDERS CONSTRUCTION LTD CIV-2004-084-24 2 September 2004 (NZ District Court)
Construction contract definition.