Plumbing Disputes
Plumbing disputes may arise out of poor contractual documentation and/or defective work and/or materials. The Construction Contracts Act 2002 adjudication process applies to plumbing disputes.
On this page
How disputes may arise
The Building Disputes Tribunal provides the leading forum for the settlement of a wide range of building and construction disputes.
FAQ
Explore our FAQ section for quick insights and to find answers to common questions.
How disputes may arise
Plans often lack critical detail and specifications are often general and not project specific. Pipes and water management systems are often undersized and/or involve long and complicated runs and/or minimum or inadequate falls due to the presence (or lack) of other building elements. Quotations will often omit (deliberately or accidentally) items of work but not expressly state so on their face and may contain estimates for the plumbing works/fitting supply to be undertaken in the form of PC (Prime Cost) or Provisional Sums that are woefully inaccurate for the work/fittings that are in fact required to be undertaken/supplied. Owners will often choose to supply plumbing fittings but will have no idea as whether the fittings are suitable, and if so, what additional items other than basic pipework must be supplied in addition to the fitting itself and will expect the plumbing contractor to assist with selection, specification and delivery arrangements, and all at no charge. Owners will often request changes to the scope of work and specification as work progresses, whether at the pipe out stage or fit off stage, or anywhere in between. Not all plumbing fittings will function as expected, some will be simply faulty (due to manufacturing defects) and some will be damaged during the construction process.
On the other hand, mistakes and errors are a feature of any building related work and some plumbing contractors fail to have adequate quality assurance processes in place to ensure they achieve the agreed/specified scope of work to the specified standard, and/or to complete their work by the due date for completion.
FAQ
Find quick insights and helpful information on a variety of topics related to plumbing disputes
What are the types of plumbing disputes we regularly deal with?
- technical (in the legal sense) disputes – ie disputes that arise out of non-compliance with the technical requirements for making and responding to payment claims under the Construction Contracts Act 2002 (the Act); and
- merits based disputes – ie disputes about the merits of the parties’ arguments in terms of the construction contract that governs their relationship, or in the case of a contract with a residential occupier, the statutory warranties that are implied into every residential building contract under s362I of the Building Act regardless of whether there is a written building contract. Typical merits based plumbing disputes include disputes in relation to:
- non-payment for work undertaken;
- contract interpretation – what the parties actually agreed;
- scope of work;
- quality of work;
- quality of materials;
- time for completion;
- payment – the value of the work undertaken in the absence of express agreement as to price;
- estimates v actual cost;
- variations – whether certain work is in fact a variation to the agreed scope of work and the value of that varied work;
- defective work;
- scope and cost of rectification work;
- repudiation/cancellation of the contract; and
- damages for breach of contract.
What types of disputes arise in adjudications?
Default liability
The Construction Contracts Act 2002 provides for a regime under which a payee (the contractor who is seeking payment) can issue its invoice in the form of a payment claim which requires the payer (the person or company who has engaged the contractor to provide services) to respond with either payment in full or a payment schedule which meets the requirements of the Act.
If the payer fails to pay or issue a valid payment schedule, the payee is entitled to initiate an adjudication claim for payment in full on the basis of default liability. If the payee can establish that it has issued a valid payment claim and no valid payment schedule has been provided in response, an adjudicator must determine the matter in the payee’s favour and payment must be made within two working days of receipt of the adjudicator’s determination.
A default liability claim can only be brought by the payee not a payer.
Claim on the Merits
A claim on the merits may be brought as an alternative to a default liability claim or on a standalone basis.
If you are a respondent to a default liability claim, you may also wish to consider initiating your own adjudication on the merits.
Disputes on the merits are adjudication claims which consider the substantive rights and obligations of the parties in terms of the construction contract that governs their relationship, or in the case of a contract with a residential occupier, the statutory warranties that are implied into every residential building contract under s362I of the Building Act regardless of whether there is a written building contract. Typical merits based disputes include disputes in relation to:
- non-payment for work undertaken;
- contract interpretation – what the parties actually agreed;
- scope of work;
- quality of work;
- quality of materials;
- time for completion;
- payment – the value of the work undertaken in the absence of express agreement as to price;
- estimates v actual cost;
- variations – whether certain work is in fact a variation to the agreed scope of work and the value of that varied work;
- defective work;
- scope and cost of rectification work;
- repudiation/cancellation of the contract; and
- damages for breach of contract.
Get in touch
Fill in the form to contact our team to see how we can help or get in touch with us with either of the following:
Phone: +64 9 486 7143
Freephone: 0508 BUILDING
Freephone: 0508 284 534
Office Hours: Monday to Friday 8:30AM to 5:00PM (excl. public holidays)