By Richard Pidgeon

The New South Wales Supreme Court in Parkview Constructions Pty Limited v Futuroscop Enterprises Pty Limited [2023] NSWSC 178 provides insight into the date of practical completion under an AS 4902-2000 contract.

Background

Parkview Constructions Pty Limited (Parkview) as contractor was engaged by the principal, Futuroscop Enterprises Pty Limited (Futuroscop) to build a Travelodge hotel and a Wilson’s carpark in Mascot, Sydney. The AS 4902-2000 form contract was entered into in September 2015 and work began on 1 March 2016. The date for practical completion was 4 September 2017. The ‘works’ did not distinguish between the completion of the two buildings.

The superintendent of works provided a retrospective certificate of practical completion for Building A (the Travelodge) on 12 September 2017, subject to Parkview rectifying certain items, and a separate certificate for Building B (the carpark) on 25 September 2017, on the same basis. The first certificate expressly stated that it excluded Building B. The ‘works’ under the contract were not defined in a separable way and the superintendent could not issue a certificate for practical completion for only one building.[1] 

The Superintendent was conferred with an extensive role and powers under the Contract, including approving variations and extensions of time, giving directions to the Contractor, approving progress claims and – critically in this case – certifying practical completion and liquidated damages.

In September 2017 the Council approved interim occupation of both buildings (which later became final) and Futuroscop took possession of the site and began taking rental from that time. This was strong evidence, as it turned out, of practical completion, given the definition of practical completion:[2]

Practical completion is that stage in the carrying out and completion of WUC [works under construction] when:

(a)   the Works are complete except for minor defects:

(i)   which do not prevent the Works from being reasonably capable of being used for their stated purpose;

(d)   the Contractor has done all things that it is required to do under the Contract to enable the Principal to obtain a certificate of occupation from the applicable Authority;

A dispute arose as to the release of security provided by Parkview and liquidated damages claimed by Futuroscop. Parkview commenced proceedings on 11 December 2018,[3] seeking to restrain Futuroscop from having recourse to the security. A crossclaim was issued in March 2019 by Futuroscop for liquidated damages and the costs of rectification of alleged defects. During the proceeding Futuroscop presented a lengthy defects list to Parkview, some 382 items,[4] which it said prevented practical completion from occurring.

Parkview claimed the ‘works’ had reached practical completion as per the conditional certificates. Futuroscop denied Parkview could have recourse to either its first or second bank guarantees due to the delayed and defective building works, and also withheld a GST payment.[5] During the proceeding the first bank guarantee was released “without prejudice” by Futuroscop.

Judge’s findings

Justice Rees held that the “conditional” certificates had no contractual effect and could not be read in the composite.  She was called upon to determine the date of practical completion herself and thus the defects liability period which ran for 12 months after practical completion. Further, her Honour was called to determine whether the contract was effectively a code and prevented common law damages for patent defects from being claimed by Futuroscop.

The terms of the contract were pivotal.  Further, Justice Rees ruled that the superintendent had breached his duties to act reasonably and in good faith. The Court interprets commercial contracts objectively by what a reasonable businessperson would have understood [the] terms to mean:[6] The actual subjective intentions of the parties are irrelevant.[7] The superintendent had not issued a certificate for practical completion in September 2017 or the ensuring five plus years. Parkview complained that the superintendent should administer the contract and not just pass on Futuroscop’s complaints. This resonated with the judge, who was sympathetic to Parkview’s evidence.

The Court found that unless a contract specifically provides for a certifier to issue a “conditional” certificate, the issue of such a certificate may be ineffective.[8] In this case the certificates had no contractual effect. This finding went Futuroscop’s way but the Court then moved to determine the practical completion date of its own accord. This favoured Parkview.

The Court ruled that the contract provided a code which established the rights, obligations and liabilities of the parties, and mechanisms by which completion of the ‘works’ was to be achieved to practical completion and during the defects liability period.

Justice Rees said that technical language is to be avoided in construing the contract:[9]

In determining the meaning of the language of commercial contract, and unilateral contractual notices, the law therefore generally favours a commercially sensible construction. The reason for this approach is that a commercial construction is more likely to give effect to the intention of the parties. Words are therefore interpreted in the way in which a reasonable commercial person would construe them. …

Where the superintendent had failed to determine the practical completion date, there was nothing in the contract to prevent the Court from stepping in (or an arbitrator) and determining that date.  Indeed, the contract itself permitted this. The Court held that the date of practical completion was important (finding it was 25 September 2017) as the contractual terms provided:

  • The superintendent could direct Parkview to remedy defects for the defects liability period of 12 months at Parkview’s cost; failing which Futuroscop would undertake the rectification at Parkview’s cost
  • A further 12 months defects liability period for rectified work
  • Within 42 days of the expiry of the last defects liability period a final certificate was to be issued as to the amounts owed between Parkview and Futuroscop, and this would equate to conclusive evidence of an accord and satisfaction
  • Patent defects, such as most of those focused on in the proceedings were exceptions to those discovered in the defects liability period and could not be claimed under common law damages; rather, they were covered solely under the contract and the contractual time limits applied.

The superintendent had not specified a separate defects liability period.

Court orders were made for payment under the contract to Parkview and a modest amount for rectification of certain proved defects. Parkview was liable to pay some liquidated damages, but in an amount Justice Rees calculated, putting aside the superintendent’s calculations. Costs were payable on an overwhelming basis to Parkview as the substantively successful party following a six-day hearing.

Conclusion

The contractual documentation and certification needs to be effectively drafted and implemented to avoid the Australian courts from having to step in to stipulate the date for practical completion. If a dispute of this nature were to happen in New Zealand, the Building Disputes Tribunal is well placed to provide a cost-effective remedy to avoid protracted and expensive court proceedings.

 

[1] Parkview Constructions Pty Limited v Futuroscop Enterprises Pty Limited [2023] NSWSC 178 at [23].

[2] Above, at [186].

[3] Above, at [173].

[4] Above, at [269].

[5] Above, at [42].

[6] Parkview Constructions Pty Limited v Futuroscop Enterprises Pty Limited [2023] NSWSC 178 at [190];Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640 at 656; [2014] HCA 7 at [35].38

[7] Parkview Constructions Pty Limited v Futuroscop Enterprises Pty Limited [2023] NSWSC 178 at [190]; Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104 at 116; [2015] HCA 37 at [50].

[8] Parkview Constructions Pty Limited v Futuroscop Enterprises Pty Limited [2023] NSWSC 178 at [205]; Official Assignee of Hutson v The New Zealand Antimony Company (Ltd) (1890) 10 NZLR 143.

[9] Parkview Constructions Pty Limited v Futuroscop Enterprises Pty Limited [2023] NSWSC 178 at [208]; Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749, 771.

Obstructed view review

Written by Maria Cole Introduction In Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited,[1] a group of apartment owners filed judicial review proceedings seeking to overturn an Auckland Council decision to grant resource...

The losing streak is over: English rugby wins… right to bring claim against contractor

Written by Alexander Lyall Nearly 10 years on, English rugby finally has a victory related to the 2015 Rugby World Cup. In FM Conway Ltd v Rugby Football Union,[1] a company contracted by the English Rugby Football Union (the RFU) for maintenance works at Twickenham...

Keep calm and carry on: English Court of Appeal overturns controversial High Court ruling and clarifies guiding principles in serial adjudications

By Kate Holland The English High Court caused concern earlier this year when it held that an adjudicator had breached natural justice by holding himself bound by a previous adjudicator’s findings. Now, in Sudlows Ltd v Global Switch Estates 1 Limited,[1] the Court of...

Moving home

Written by Richard Pidgeon A family became dissatisfied with a house removal firm who had shifted their home from Remuera to Katikati. In Stott v Uplifting Homes Ltd [2023] NZHC 1514, the High Court determined the level of compensation after the contract was...

Big loss for insurer in legal battle with Napier Council over leaky building clause

Written by Sam Dorne In a recent case, the Supreme Court of New Zealand ruled in favour of the Napier City Council in an insurance claim involving building defects including weathertightness or “leaky building” issues, in what is seen as a return to the status quo...

BuildLaw Issue 51

September 2023Download PDF   CONTENTS BuildLaw in Brief Keep calm and carry on Mainzeal saga ends in the Supreme Court New Zealand: Insurance under Scrutiny Obstructed view review Case in Brief: Esk Valley marae injunction Res judicata and declarations relating...

Take a rain cheque – Full Federal Court of Australia reads common sense into insurance policy

By Alexander Lyall A decision by the Full Federal Court of Australia has provided clarification about the wording of an insurance policy for a construction project. In Acciona Infrastructure Australia Pty Ltd v Zurich Australian Insurance Limited [2023] FCAFC 47,[1] ...

Case update: English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

Disgruntled builders lose defective cladding dispute

By Sam Dorne In Goodman-Jones v Hughey & ors [2023] NZHC 604, two experienced builders brought a claim for damages for a perceived defective installation of cladding for a new build. Despite the action being brought against multiple defendants the Court found that...

BuildLaw Issue 50

June 2023Download PDF   CONTENTS BuildLaw in Brief: Recent key developments in the construction industry Bad faith and without substantial merit – What it means and what it takes Disgruntled builders lose defective cladding dispute High-rise blues Build-to-Rent:...

Craftiness is not an abuse of process

With cashflow a persistent concern for companies in the construction industry, a recent decision in the New South Wales Supreme Court may alleviate some of the stress. The decision should affirm to struggling parties that there is no problem with taking strategic...

Privileged glimpses: Curtain falls on art gallery’s nuisance ‘human zoo’ exhibit

By Kate Holland The UK Supreme Court has ruled that the London Tate Modern’s public viewing gallery overlooking the luxury glass-walled apartments nearby, is a visual intrusion amounting to the tort of nuisance. The decision in has attracted criticism for prioritising...

Waiver and estoppel arguments raised in interim payment dispute

By Sam Dorne The English Court of Appeal case of A & V Building Solutions Limited v J & B Hopkins Limited has highlighted issues parties face when there is ambiguity in relation to dates for requesting interim payment in construction contracts.[1] The case...

Doing business in Australia? Then you need to know when you still might have to pick up the whole tab

By Maria Cole If you have a commercial contract in Australia, it’s probably governed by Australian law, which includes the proportionate liability regime.[1] Broadly, proportionate liability means if there are multiple parties to a contract and things go wrong, a...

Parliament passes sweeping amendments to construction payment regime

By Alexander Lyall Parliament has recently enacted legislation allowing for comprehensive changes to the Construction Contracts Act 2002. The Construction Contracts (Retention Money) Amendment Act 2023 passed its third reading on Wednesday 29 March and received Royal...

BuildLaw Issue 49

March 2023Download pdf   CONTENTS Diamond Glass slices damages in airport contract Case in Brief: Craftiness is not an abuse of process (Kennedy Civil Contracting Pty Ltd (Administrators Appointed) v Richard Crookes Construction Pty Ltd [2023] NSWSC 99) That...

Builder terminates contract with a “sorry mate…costs are going through the roof”

By Kate Holland With the construction industry in the grip of labour and supply shortages and spiralling costs, a recent decision of the Queensland court is a timely reminder of the established principles of contractual repudiation. The decision is a warning to...

Ripping up the Resource Management Act

By Adrian Sharma The Resource Management Act 1991 (RMA) is one of New Zealand’s most important pieces of legislation. It governs what can be built where, when, and how. But more than 30 years on from its introduction, and after numerous amendments, the controversial...

To bespoke or too bespoke – the case of an ADR clause that couldn’t be enforced

By Kate Holland In a recent English decision, the Technology and Construction Court held that a clause in a construction contract requiring the parties to refer a dispute to ADR was a condition precedent to commencing litigation in the courts. However, the Court also...

The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so file a payment schedule or pay up!

By Maria Cole A decision issued by the High Court last year caused a “head in hands” moment in the construction industry in relation to the payment claim regime. The High Court set aside a statutory demand which had been filed to enforce a payment claim as a debt due...

BuildLaw Issue 48

December 2022Download pdf   CONTENTS The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so issue a payment schedule or pay up! Case in Brief: Builder terminates contract with a “sorry mate… costs are going through the roof” but...

Labelling an image as an ‘artist impression’ was found not to give a developer artistic licence in a claim of misleading and deceptive conduct over an ‘off-the-plan’ premium apartment

By Maria Cole Australian consumer protection law was given an outing in the Federal Court of Australia when a developer merely added the words ‘artist impression’ to a computer generated image it intended to use in its marketing materials for an ‘off-the-plan’...

Fire risk – defective cladding litigation heats up

By Sam Dorne In England and Wales, the Technology and Construction Court in Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 July 2022) has released the first decision arising out of a defective cladding dispute following the Grenfell Tower...

BuildLaw Issue 47

September 2022CONTENTS Competition not working well in residential building suppliesmarket Fire risk – defective cladding litigation heats up Case in Brief: Supreme Court of New South Wales finds forcemajeure clause offered no protection for loss and damage togoods in...

WA Supreme Court finds no implied licence to use home design plan

By Kate Holland In a recent Australian case, the WA Supreme Court was unwilling to interpret a contract between a home builder and their client to imply a licence allowing the client to use the builder’s design in whatever way they pleased. Although the case was...

Overhaul coming to the regulation of engineers

By Sam Dorne The Ministry of Business, Innovation and Employment (MBIE) undertook a consultation in 2021 to reform the regulatory regime for engineers. The reforms will move away from a voluntary accreditation scheme into a formal regulated regime.   Current...

Expert “evidence” needs to be more than just bald assertions to win the day

By Adrian Sharma Leakage issues in a building can be a real dampener. A recent decision of the Queensland Civil and Administrative Tribunal (the Tribunal) which considered conflicting expert evidence on water ingress issues in a newly built property highlighted the...

An adjudicator’s decision on a construction contract is definitely worth the paper it’s written on!

By Maria Cole It’s only in rare circumstances that the courts will interfere with the decision of an adjudicator on a construction contract. A recent decision out of the English Technology and Construction Court (TCC) considered arguments that an adjudicator acted in...

You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure

By Belinda Green.   We’ve known for a long time that a party can’t rely on a failure to satisfy a condition if the condition failed to satisfy because of their action. But we never really had an explanation of how bad that “failure” had to be until now. In its...

BuildLaw Issue 46

March 2022CONTENTS You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure Case in Brief: Unhelpful expert witness sees homeowners succeed in defective...

Vicarious liability and subcontractors

By Sam Dorne Liability in tort depends upon proof of a personal breach of duty, with one true exception, vicarious liability. The law of negligence is generally fault based; a defendant is personally liable only for the defendant’s own negligent acts and omissions....

Limitation for payment claims under construction contracts

By Sam Dorne The decision in Hirst v Dunbar [2022] EWHC 41 (TCC) considers the impact of payment provisions in a construction contract, whether through contract or implied terms, and the commencement of the limitation period for payment claims under the contract. It...

Extensions of time in construction contracts

By Jo O’Dea   In an extension of time claim, blame for the delay was a relevant consideration when assessing what was “fair and reasonable”.   In CAJ v CAI [2021] 5 GCA 102, the Singapore Court of Appeal considered the issue of extensions of time in...

BuildLaw Issue 45

March 2022CONTENTS Extensions of time in construction contracts Construction contract procedure and dispute resolution: There really is a reason to pay attention to the boring stuff Principals beware, constructive acceleration is here UK: Important announcement on the...

Testing the waters: New South Wales Supreme Court considers the prevention principle

By Hannah Aziz  Court provides further confirmation that the prevention principle can be excluded by the terms of a contract.   Introduction Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the...

Construction contract or product warranty? Not all collateral warranty disputes can be adjudicated

By Belinda Green Collateral warranties might be parasitic on a construction contract, but that doesn’t automatically mean they are one. The individual wording and circumstances need to be considered. In some cases, like in Toppan Holdings Limited v Simply Construction...

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Important Guidance on Contract Interpretation Issued by the Supreme Court

Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 The Supreme Court in Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 has provided important guidance on how extrinsic evidence and implied terms are used to aid interpretation of...
Skip to content