By Alexander Lyall

Parliament has recently enacted legislation allowing for comprehensive changes to the Construction Contracts Act 2002. The Construction Contracts (Retention Money) Amendment Act 2023 passed its third reading on Wednesday 29 March and received Royal assent on April 5.

The legislation concerns the use and protection of retention money held by head contractors. It intends to strengthen current requirements for the purpose of giving subcontractors added security.

Current requirements

The Construction Contracts Act 2002 (the CCA) currently requires that when a head contractor (referred to in the CCA as party A) holds retention money for a subcontractor (referred to in the CCA as party B), it must be done in a trust with the subcontractor as the beneficiary. The sum may be held in cash, liquid assets, or a financial instrument.

Changes

Clarification on what is retention money

Sums of money will be deemed to be retention money regardless of whether they have actually been retained, or whether a portion of the sum has already been paid to the subcontractor. The effect of this change will be seen in situations where the head contractor becomes insolvent. A subcontractor who has been partially paid should no longer be in a better position than one who has not.

Retention money held in trust

The Construction Contracts (Retention Money) Amendment Act 2023 (the Act) clarifies that retention money is automatically held on trust by the head contractor. This removes the necessity for an explicit intention to be made that the retention money will be stored in the trust.

Once the retention money is paid to the subcontractor, it will no longer be trust property. This may also occur when the funds are used by the head contractor to rectify errors.  

Holding retention money

The head contractor is to hold retention money in either a bank account or make it the subject of a suitable financial instrument, such as insurance or a payment bond.

The requirements for such maintenance will be set once the retention money is held in the bank account. In this event:

  • the account must be used only for the purpose of holding the retention money; and
  • the head contractor must inform the bank that the account is a trust account for the purposes of holding retention money.

Status of retention money to be reported

The head contractor will be mandated to give the subcontractor specified information at the time the sum is held. From that point, the relevant information should be given to the subcontractor every third month, at least. To be included in that information are:

  • the latest amount withheld, the particular construction contract to which that pertains, its date of retention; and
  • the total amount of retention money that the head contractor holds for the subcontractor.

In these situations, it is necessary for the head contractor to communicate this information:

  • if a bank has been selected, the head contractor will then need to communicate the name of that bank, as well as the respective branch and name of the bank account;
  • if the account in which the sum is stored has a separate ledger, the name of the subcontractor’s ledger and the total balance held for the subcontractor; and
  • if the head contractor is using a financial instrument, the name of the issuer, information relevant for identifying the instrument, and the amount protected.

A penalty will apply if the information given is either false or misleading.

Liquidation or receivership

If the head contractor is placed into either liquidation or receivership, the liquidator or receiver will use a trust to hold the retention money. The responsibilities held by the head contractor are then transferred to the liquidator or receiver. The Act seeks to change the current situation for liquidators and receivers where they must make an application to the court for directions. It does so by clarifying that liquidators and receivers will not be liable for any improper or unlawful action taken prior to their appointment.

Compliance

One of the biggest changes to the CCA is that it now includes penalty provisions for noncompliance. These penalties are:

  • a fine of up to $200,000 for failure to keep retention money in a way described by the CCA;
  • a fine of up to $50,000 for failure to keep proper accounting; and
  • a fine of up to $50,000 for failure to provide regular reports of retention money.

Each director can also be personally liable for failure to properly hold retention money if the head contractor is a company. A director in this situation could find themselves with a fine of up to $50,000. Of note, this penalty refers to a single breach. It is not one penalty for several breaches. If a director were to be prosecuted for ignoring the CCA’s directions for five different subcontractors, then the sum of that penalty would be increased fivefold.

The Ministry of Business, Innovation and Employment will be able to investigate and enforce retentions money offences. Further penalties may be incurred if the head contractors do not provide the Ministry with information required to assist investigations.

The legislation will come into effect in October 2023, providing construction companies time to review their financial strategies.

Obstructed view review

Written by Maria Cole Introduction In Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited,[1] a group of apartment owners filed judicial review proceedings seeking to overturn an Auckland Council decision to grant resource...

The losing streak is over: English rugby wins… right to bring claim against contractor

Written by Alexander Lyall Nearly 10 years on, English rugby finally has a victory related to the 2015 Rugby World Cup. In FM Conway Ltd v Rugby Football Union,[1] a company contracted by the English Rugby Football Union (the RFU) for maintenance works at Twickenham...

Keep calm and carry on: English Court of Appeal overturns controversial High Court ruling and clarifies guiding principles in serial adjudications

By Kate Holland The English High Court caused concern earlier this year when it held that an adjudicator had breached natural justice by holding himself bound by a previous adjudicator’s findings. Now, in Sudlows Ltd v Global Switch Estates 1 Limited,[1] the Court of...

Moving home

Written by Richard Pidgeon A family became dissatisfied with a house removal firm who had shifted their home from Remuera to Katikati. In Stott v Uplifting Homes Ltd [2023] NZHC 1514, the High Court determined the level of compensation after the contract was...

Big loss for insurer in legal battle with Napier Council over leaky building clause

Written by Sam Dorne In a recent case, the Supreme Court of New Zealand ruled in favour of the Napier City Council in an insurance claim involving building defects including weathertightness or “leaky building” issues, in what is seen as a return to the status quo...

BuildLaw Issue 51

September 2023Download PDF   CONTENTS BuildLaw in Brief Keep calm and carry on Mainzeal saga ends in the Supreme Court New Zealand: Insurance under Scrutiny Obstructed view review Case in Brief: Esk Valley marae injunction Res judicata and declarations relating...

Take a rain cheque – Full Federal Court of Australia reads common sense into insurance policy

By Alexander Lyall A decision by the Full Federal Court of Australia has provided clarification about the wording of an insurance policy for a construction project. In Acciona Infrastructure Australia Pty Ltd v Zurich Australian Insurance Limited [2023] FCAFC 47,[1] ...

Case update: English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

Disgruntled builders lose defective cladding dispute

By Sam Dorne In Goodman-Jones v Hughey & ors [2023] NZHC 604, two experienced builders brought a claim for damages for a perceived defective installation of cladding for a new build. Despite the action being brought against multiple defendants the Court found that...

BuildLaw Issue 50

June 2023Download PDF   CONTENTS BuildLaw in Brief: Recent key developments in the construction industry Bad faith and without substantial merit – What it means and what it takes Disgruntled builders lose defective cladding dispute High-rise blues Build-to-Rent:...

Craftiness is not an abuse of process

With cashflow a persistent concern for companies in the construction industry, a recent decision in the New South Wales Supreme Court may alleviate some of the stress. The decision should affirm to struggling parties that there is no problem with taking strategic...

Privileged glimpses: Curtain falls on art gallery’s nuisance ‘human zoo’ exhibit

By Kate Holland The UK Supreme Court has ruled that the London Tate Modern’s public viewing gallery overlooking the luxury glass-walled apartments nearby, is a visual intrusion amounting to the tort of nuisance. The decision in has attracted criticism for prioritising...

Waiver and estoppel arguments raised in interim payment dispute

By Sam Dorne The English Court of Appeal case of A & V Building Solutions Limited v J & B Hopkins Limited has highlighted issues parties face when there is ambiguity in relation to dates for requesting interim payment in construction contracts.[1] The case...

Doing business in Australia? Then you need to know when you still might have to pick up the whole tab

By Maria Cole If you have a commercial contract in Australia, it’s probably governed by Australian law, which includes the proportionate liability regime.[1] Broadly, proportionate liability means if there are multiple parties to a contract and things go wrong, a...

BuildLaw Issue 49

March 2023Download pdf   CONTENTS Diamond Glass slices damages in airport contract Case in Brief: Craftiness is not an abuse of process (Kennedy Civil Contracting Pty Ltd (Administrators Appointed) v Richard Crookes Construction Pty Ltd [2023] NSWSC 99) That...

Builder terminates contract with a “sorry mate…costs are going through the roof”

By Kate Holland With the construction industry in the grip of labour and supply shortages and spiralling costs, a recent decision of the Queensland court is a timely reminder of the established principles of contractual repudiation. The decision is a warning to...

Ripping up the Resource Management Act

By Adrian Sharma The Resource Management Act 1991 (RMA) is one of New Zealand’s most important pieces of legislation. It governs what can be built where, when, and how. But more than 30 years on from its introduction, and after numerous amendments, the controversial...

To bespoke or too bespoke – the case of an ADR clause that couldn’t be enforced

By Kate Holland In a recent English decision, the Technology and Construction Court held that a clause in a construction contract requiring the parties to refer a dispute to ADR was a condition precedent to commencing litigation in the courts. However, the Court also...

The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so file a payment schedule or pay up!

By Maria Cole A decision issued by the High Court last year caused a “head in hands” moment in the construction industry in relation to the payment claim regime. The High Court set aside a statutory demand which had been filed to enforce a payment claim as a debt due...

BuildLaw Issue 48

December 2022Download pdf   CONTENTS The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so issue a payment schedule or pay up! Case in Brief: Builder terminates contract with a “sorry mate… costs are going through the roof” but...

Labelling an image as an ‘artist impression’ was found not to give a developer artistic licence in a claim of misleading and deceptive conduct over an ‘off-the-plan’ premium apartment

By Maria Cole Australian consumer protection law was given an outing in the Federal Court of Australia when a developer merely added the words ‘artist impression’ to a computer generated image it intended to use in its marketing materials for an ‘off-the-plan’...

Fire risk – defective cladding litigation heats up

By Sam Dorne In England and Wales, the Technology and Construction Court in Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 July 2022) has released the first decision arising out of a defective cladding dispute following the Grenfell Tower...

BuildLaw Issue 47

September 2022CONTENTS Competition not working well in residential building suppliesmarket Fire risk – defective cladding litigation heats up Case in Brief: Supreme Court of New South Wales finds forcemajeure clause offered no protection for loss and damage togoods in...

WA Supreme Court finds no implied licence to use home design plan

By Kate Holland In a recent Australian case, the WA Supreme Court was unwilling to interpret a contract between a home builder and their client to imply a licence allowing the client to use the builder’s design in whatever way they pleased. Although the case was...

Overhaul coming to the regulation of engineers

By Sam Dorne The Ministry of Business, Innovation and Employment (MBIE) undertook a consultation in 2021 to reform the regulatory regime for engineers. The reforms will move away from a voluntary accreditation scheme into a formal regulated regime.   Current...

Expert “evidence” needs to be more than just bald assertions to win the day

By Adrian Sharma Leakage issues in a building can be a real dampener. A recent decision of the Queensland Civil and Administrative Tribunal (the Tribunal) which considered conflicting expert evidence on water ingress issues in a newly built property highlighted the...

An adjudicator’s decision on a construction contract is definitely worth the paper it’s written on!

By Maria Cole It’s only in rare circumstances that the courts will interfere with the decision of an adjudicator on a construction contract. A recent decision out of the English Technology and Construction Court (TCC) considered arguments that an adjudicator acted in...

You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure

By Belinda Green.   We’ve known for a long time that a party can’t rely on a failure to satisfy a condition if the condition failed to satisfy because of their action. But we never really had an explanation of how bad that “failure” had to be until now. In its...

BuildLaw Issue 46

March 2022CONTENTS You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure Case in Brief: Unhelpful expert witness sees homeowners succeed in defective...

Vicarious liability and subcontractors

By Sam Dorne Liability in tort depends upon proof of a personal breach of duty, with one true exception, vicarious liability. The law of negligence is generally fault based; a defendant is personally liable only for the defendant’s own negligent acts and omissions....

Limitation for payment claims under construction contracts

By Sam Dorne The decision in Hirst v Dunbar [2022] EWHC 41 (TCC) considers the impact of payment provisions in a construction contract, whether through contract or implied terms, and the commencement of the limitation period for payment claims under the contract. It...

Extensions of time in construction contracts

By Jo O’Dea   In an extension of time claim, blame for the delay was a relevant consideration when assessing what was “fair and reasonable”.   In CAJ v CAI [2021] 5 GCA 102, the Singapore Court of Appeal considered the issue of extensions of time in...

BuildLaw Issue 45

March 2022CONTENTS Extensions of time in construction contracts Construction contract procedure and dispute resolution: There really is a reason to pay attention to the boring stuff Principals beware, constructive acceleration is here UK: Important announcement on the...

Testing the waters: New South Wales Supreme Court considers the prevention principle

By Hannah Aziz  Court provides further confirmation that the prevention principle can be excluded by the terms of a contract.   Introduction Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the...

Construction contract or product warranty? Not all collateral warranty disputes can be adjudicated

By Belinda Green Collateral warranties might be parasitic on a construction contract, but that doesn’t automatically mean they are one. The individual wording and circumstances need to be considered. In some cases, like in Toppan Holdings Limited v Simply Construction...

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Important Guidance on Contract Interpretation Issued by the Supreme Court

Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 The Supreme Court in Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 has provided important guidance on how extrinsic evidence and implied terms are used to aid interpretation of...

What are the cost implications of challenging an arbitral award through the courts?

By Maria Cole. A recent decision of the Singapore High Court shone a spotlight on indemnity costs and when they will, and won’t, be granted following the unsuccessful challenge of an arbitral award. The decision highlighted the opposite principles in place between...
Skip to content