Written by Richard Pidgeon

A family became dissatisfied with a house removal firm who had shifted their home from Remuera to Katikati. In Stott v Uplifting Homes Ltd [2023] NZHC 1514, the High Court determined the level of compensation after the contract was cancelled.

Background

In July 2019 the plaintiffs Mr Stott and his partner Ms Savageau (plaintiffs) bought an early 20th century wooden bungalow from the Hamilton-based Uplifting Homes Ltd (Uplifting) for $158,000 (inclusive of GST), to be relocated from Remuera to Katikati. The sale price also included building consent plans to be drawn and submitted on the plaintiffs’ behalf with no changes to the original floor plan and using existing roofing materials.[1]

The home was transported in October 2019. Its resiting was complicated by the Western Bay of Plenty District Council’s insistence on the provision of extra bracing, foundation work and roof structure because of the higher Katikati wind zone.

Under the contract the parties agreed to the following relevant terms and conditions as summarised:

  • Uplifting was responsible for ensuring that the relocation of the building is carried out in a professional, workman-like manner for the duration of this contract in accordance with the conditions of trade.[2]
  • All work carried out by Uplifting…will comply with the New Zealand Building Code and NZS 3604:2011, the New Zealand standard means of compliance with the Building Code for the structure of timber-framed buildings.[3]
  • The home would be resited with existing materials only and Uplifting was not responsible for damage when the home was on the temporary piles.

The contract was therefore for a building work under a residential building contract and the warranties under the Building Act 2004 were implied as was the time for completion under the Consumer Guarantees Act 1993.

The plaintiffs were distressed and devastated by the state of the house on its receipt and the likelihood it would suffer further damage while on the temporary foundations at their Katikati property.[4] There was disagreement as to storm damage and the normal incident of damage as part of the relocation. Uplifting’s agent Prestige Builders met with the plaintiffs and made a number of concessions and promises.

Pending building consent being obtained, the home was placed on temporary foundations on the Katikati site. After building consent was obtained on 13 May 2020 (after the Covid-19 lockdown was lifted), Uplifting re-established the house on permanent foundations in July 2020 and relined and reroofed the house, albeit incompletely.

Uplifting’s attendances on the site thereafter were sporadic. Prestige Builders arranged work on the roof which in January 2021 the plaintiffs’ builder expressed concerns about. The builder’s report noted poor rejoining of the house and that a considerable amount of work would be needed to remedy defects. There were areas of severe timber decay and the roofing and piles were problematic. Quantity surveyors engaged by the plaintiffs assessed the cost of these works to exceed $520,000 (including GST); alternatively, demolition and make good costs of $24,000–$33,000 (including GST).[5] The Judge later ruled this expectation was unrealistic.

Nothing was done by Uplifting after mid-November 2020, and by mid-June 2021 reasonable time for completion had passed.[6] Justice Jagose did note:

[60] … it is relevant the Savageau/Stotts pleaded such purpose to be “of such a nature and quality as to render [the building] suitable for occupation by the plaintiffs as their family home”. That contention cannot be maintained: on any view, after the building was to be re‐erected on site, very substantial works remained the Savageau/Stotts’ obligation to render the house suitable for occupation. … Nor had Uplifting any obligation to protect the building from weather or other damage on its temporary platform on site: clauses 16 and 18 of the contract made it plain such was not Uplifting’s liability.

By letter of 9 April 2021, the plaintiffs’ solicitors wrote to Uplifting alleging its poor work quality and contractual breaches and seeking reimbursement of the plaintiffs’ expenses together with removal of the home from the site. Ultimately on 19 July 2021 the plaintiffs’ solicitors gave notice to Uplifting’s solicitors that they cancelled the 22 July 2019 contract, relying on breaches of the Consumer Guarantees Act (section 28 as to reasonable skill and care, section 29 as to fitness for particular purpose and section 30 as to time for completion). Alleged breaches of the Building Act 2004 were also referred to, namely section 362I(1). Proceedings were issued on 27 August 2021.

On 24 May 2022 the plaintiffs sold their Katikati property for $1.25 million on conditions including the house’s removal, which was demolished accordingly. They moved to Nelson.

The plaintiffs went to trial claiming $33,000 in wasted costs and $35,000 in general damages on the basis of breach of contract entitling cancellation. They relied on the Building Act 2004, Consumer Guarantees Act 1993 and Contract and Commercial Act 2017.

The decision

The judge recognised the breaches of warranty were substantial,[7] because a reasonable client fully acquainted with the nature and extrent of the breach would not have entered into the residential building contract.[8] This permitted the plaintiffs to cancel.[9]

The relief fell to be considered on compensatory, rather than damages, principles: from identification of what the innocent party “actually lost by reason of the breach”, rather than their position if the contract had been performed.[10]

Justice Jagose commented:

  • Beyond the monies paid to Uplifting under the resiting contract, the plaintiffs’ other expenditure in connection with the contract’s performance prior to getting a building consent was at their own risk.
  • Uplifting affirmed the contract by commencing piling works in early June 2020, the Savageau/Stotts’ subsequent expenditure under the contract was attributable to their expectation Uplifting would perform its contractual obligations.[11]
  • The plaintiffs’ expectations were unrealistic in terms of the contract they entered with Uplifting. They appeared to have no prior comprehension of additional requirements for their home’s establishment on the new site beyond Uplifting’s transportation and reerection of the building there, which the contract firmly made their responsibility as work not specifically expressed.[12]
  • The damage following transportation was in line with expectations.
  • When the home was on its temporary pilings, Uplifting was not responsible for any damages that may occur to the building.[13]
  • It was to Uplifting’s credit that they responded to the plaintiffs’ persistent requests for help.
  • The plaintiffs tendered a list of specific “losses”. The rental claim was ruled as being too speculative to establish such loss as reasonably foreseeable.[14]
  • A 50% deduction on the compensation claimed was ruled appropriate to recognise Uplifting’s legitimate and compliant expenditure under the contract.[15]

The Judge deducted $22,400 which the plaintiffs had received under their insurance policy, but gave no recognition for the cost of demolition of the home nor for the plaintiffs’ building experts’ reports.

Following a six day hearing, Justice Jagose granted the plaintiffs compensatory damages in the sum of $94,911.53 for the actual loss by reason of Uplifting’s breaches under section 43(3)(3)(a) of the Contracts and Commercial Law Act 2017. The basis of the reduced quantum has the strict wording of the contractual requirements and the obligations imposed on each party.

Conclusion

In shifting a dream home, one must have reasonable expectations of having to expend thousands of dollars in making the home habitable once it is resited. It is necessary to review the contractual terms prior to engaging with the relocation firm. Judgment was obtained but was not entered for the full sum sought, and the costs and delay of the litigation make arbitration attractive, such as offered by the New Zealand Dispute Resolution Centre.

[1] Stott v Uplifting Homes Ltd [2023] NZHC 1514 at [11].

[2] Stott, above n 1, at [10].

[3] This was also a term of the building consent.

[4] Stott, above n 1, at [19].

[5] Stott, above n 1, at [37]

[6] Stott, above n 1, at [58].

[7] Section 362O of the Building Act 2004.

[8] Stott, above n 1, at [66].

[9] Stott, above n 1, at [68].

[10] Stott, above n 1, at [69]; and Forest Holdings Ltd v Mangatu Blocks Incorporation [2017] NZHC 448, [2017] NZAR 671 at [27]–[29], citing Maori Trustee v Clark [1984] 1 NZLR 578 (CA) at 584.

[11] Stott, above n 1, at [72].

[12] Stott, above n 1, at [78].

[13] Stott, above n 1, at [80].

[14] Stott, above n 1, at [74].

[15] Stott, above n 1, at [85].

Obstructed view review

Written by Maria Cole Introduction In Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited,[1] a group of apartment owners filed judicial review proceedings seeking to overturn an Auckland Council decision to grant resource...

The losing streak is over: English rugby wins… right to bring claim against contractor

Written by Alexander Lyall Nearly 10 years on, English rugby finally has a victory related to the 2015 Rugby World Cup. In FM Conway Ltd v Rugby Football Union,[1] a company contracted by the English Rugby Football Union (the RFU) for maintenance works at Twickenham...

Keep calm and carry on: English Court of Appeal overturns controversial High Court ruling and clarifies guiding principles in serial adjudications

By Kate Holland The English High Court caused concern earlier this year when it held that an adjudicator had breached natural justice by holding himself bound by a previous adjudicator’s findings. Now, in Sudlows Ltd v Global Switch Estates 1 Limited,[1] the Court of...

Big loss for insurer in legal battle with Napier Council over leaky building clause

Written by Sam Dorne In a recent case, the Supreme Court of New Zealand ruled in favour of the Napier City Council in an insurance claim involving building defects including weathertightness or “leaky building” issues, in what is seen as a return to the status quo...

BuildLaw Issue 51

September 2023Download PDF   CONTENTS BuildLaw in Brief Keep calm and carry on Mainzeal saga ends in the Supreme Court New Zealand: Insurance under Scrutiny Obstructed view review Case in Brief: Esk Valley marae injunction Res judicata and declarations relating...

Take a rain cheque – Full Federal Court of Australia reads common sense into insurance policy

By Alexander Lyall A decision by the Full Federal Court of Australia has provided clarification about the wording of an insurance policy for a construction project. In Acciona Infrastructure Australia Pty Ltd v Zurich Australian Insurance Limited [2023] FCAFC 47,[1] ...

Case update: English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

Disgruntled builders lose defective cladding dispute

By Sam Dorne In Goodman-Jones v Hughey & ors [2023] NZHC 604, two experienced builders brought a claim for damages for a perceived defective installation of cladding for a new build. Despite the action being brought against multiple defendants the Court found that...

BuildLaw Issue 50

June 2023Download PDF   CONTENTS BuildLaw in Brief: Recent key developments in the construction industry Bad faith and without substantial merit – What it means and what it takes Disgruntled builders lose defective cladding dispute High-rise blues Build-to-Rent:...

Craftiness is not an abuse of process

With cashflow a persistent concern for companies in the construction industry, a recent decision in the New South Wales Supreme Court may alleviate some of the stress. The decision should affirm to struggling parties that there is no problem with taking strategic...

Privileged glimpses: Curtain falls on art gallery’s nuisance ‘human zoo’ exhibit

By Kate Holland The UK Supreme Court has ruled that the London Tate Modern’s public viewing gallery overlooking the luxury glass-walled apartments nearby, is a visual intrusion amounting to the tort of nuisance. The decision in has attracted criticism for prioritising...

Waiver and estoppel arguments raised in interim payment dispute

By Sam Dorne The English Court of Appeal case of A & V Building Solutions Limited v J & B Hopkins Limited has highlighted issues parties face when there is ambiguity in relation to dates for requesting interim payment in construction contracts.[1] The case...

Doing business in Australia? Then you need to know when you still might have to pick up the whole tab

By Maria Cole If you have a commercial contract in Australia, it’s probably governed by Australian law, which includes the proportionate liability regime.[1] Broadly, proportionate liability means if there are multiple parties to a contract and things go wrong, a...

Parliament passes sweeping amendments to construction payment regime

By Alexander Lyall Parliament has recently enacted legislation allowing for comprehensive changes to the Construction Contracts Act 2002. The Construction Contracts (Retention Money) Amendment Act 2023 passed its third reading on Wednesday 29 March and received Royal...

BuildLaw Issue 49

March 2023Download pdf   CONTENTS Diamond Glass slices damages in airport contract Case in Brief: Craftiness is not an abuse of process (Kennedy Civil Contracting Pty Ltd (Administrators Appointed) v Richard Crookes Construction Pty Ltd [2023] NSWSC 99) That...

Builder terminates contract with a “sorry mate…costs are going through the roof”

By Kate Holland With the construction industry in the grip of labour and supply shortages and spiralling costs, a recent decision of the Queensland court is a timely reminder of the established principles of contractual repudiation. The decision is a warning to...

Ripping up the Resource Management Act

By Adrian Sharma The Resource Management Act 1991 (RMA) is one of New Zealand’s most important pieces of legislation. It governs what can be built where, when, and how. But more than 30 years on from its introduction, and after numerous amendments, the controversial...

To bespoke or too bespoke – the case of an ADR clause that couldn’t be enforced

By Kate Holland In a recent English decision, the Technology and Construction Court held that a clause in a construction contract requiring the parties to refer a dispute to ADR was a condition precedent to commencing litigation in the courts. However, the Court also...

The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so file a payment schedule or pay up!

By Maria Cole A decision issued by the High Court last year caused a “head in hands” moment in the construction industry in relation to the payment claim regime. The High Court set aside a statutory demand which had been filed to enforce a payment claim as a debt due...

BuildLaw Issue 48

December 2022Download pdf   CONTENTS The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so issue a payment schedule or pay up! Case in Brief: Builder terminates contract with a “sorry mate… costs are going through the roof” but...

Labelling an image as an ‘artist impression’ was found not to give a developer artistic licence in a claim of misleading and deceptive conduct over an ‘off-the-plan’ premium apartment

By Maria Cole Australian consumer protection law was given an outing in the Federal Court of Australia when a developer merely added the words ‘artist impression’ to a computer generated image it intended to use in its marketing materials for an ‘off-the-plan’...

Fire risk – defective cladding litigation heats up

By Sam Dorne In England and Wales, the Technology and Construction Court in Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 July 2022) has released the first decision arising out of a defective cladding dispute following the Grenfell Tower...

BuildLaw Issue 47

September 2022CONTENTS Competition not working well in residential building suppliesmarket Fire risk – defective cladding litigation heats up Case in Brief: Supreme Court of New South Wales finds forcemajeure clause offered no protection for loss and damage togoods in...

WA Supreme Court finds no implied licence to use home design plan

By Kate Holland In a recent Australian case, the WA Supreme Court was unwilling to interpret a contract between a home builder and their client to imply a licence allowing the client to use the builder’s design in whatever way they pleased. Although the case was...

Overhaul coming to the regulation of engineers

By Sam Dorne The Ministry of Business, Innovation and Employment (MBIE) undertook a consultation in 2021 to reform the regulatory regime for engineers. The reforms will move away from a voluntary accreditation scheme into a formal regulated regime.   Current...

Expert “evidence” needs to be more than just bald assertions to win the day

By Adrian Sharma Leakage issues in a building can be a real dampener. A recent decision of the Queensland Civil and Administrative Tribunal (the Tribunal) which considered conflicting expert evidence on water ingress issues in a newly built property highlighted the...

An adjudicator’s decision on a construction contract is definitely worth the paper it’s written on!

By Maria Cole It’s only in rare circumstances that the courts will interfere with the decision of an adjudicator on a construction contract. A recent decision out of the English Technology and Construction Court (TCC) considered arguments that an adjudicator acted in...

You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure

By Belinda Green.   We’ve known for a long time that a party can’t rely on a failure to satisfy a condition if the condition failed to satisfy because of their action. But we never really had an explanation of how bad that “failure” had to be until now. In its...

BuildLaw Issue 46

March 2022CONTENTS You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure Case in Brief: Unhelpful expert witness sees homeowners succeed in defective...

Vicarious liability and subcontractors

By Sam Dorne Liability in tort depends upon proof of a personal breach of duty, with one true exception, vicarious liability. The law of negligence is generally fault based; a defendant is personally liable only for the defendant’s own negligent acts and omissions....

Limitation for payment claims under construction contracts

By Sam Dorne The decision in Hirst v Dunbar [2022] EWHC 41 (TCC) considers the impact of payment provisions in a construction contract, whether through contract or implied terms, and the commencement of the limitation period for payment claims under the contract. It...

Extensions of time in construction contracts

By Jo O’Dea   In an extension of time claim, blame for the delay was a relevant consideration when assessing what was “fair and reasonable”.   In CAJ v CAI [2021] 5 GCA 102, the Singapore Court of Appeal considered the issue of extensions of time in...

BuildLaw Issue 45

March 2022CONTENTS Extensions of time in construction contracts Construction contract procedure and dispute resolution: There really is a reason to pay attention to the boring stuff Principals beware, constructive acceleration is here UK: Important announcement on the...

Testing the waters: New South Wales Supreme Court considers the prevention principle

By Hannah Aziz  Court provides further confirmation that the prevention principle can be excluded by the terms of a contract.   Introduction Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the...

Construction contract or product warranty? Not all collateral warranty disputes can be adjudicated

By Belinda Green Collateral warranties might be parasitic on a construction contract, but that doesn’t automatically mean they are one. The individual wording and circumstances need to be considered. In some cases, like in Toppan Holdings Limited v Simply Construction...

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Important Guidance on Contract Interpretation Issued by the Supreme Court

Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 The Supreme Court in Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 has provided important guidance on how extrinsic evidence and implied terms are used to aid interpretation of...

What are the cost implications of challenging an arbitral award through the courts?

By Maria Cole. A recent decision of the Singapore High Court shone a spotlight on indemnity costs and when they will, and won’t, be granted following the unsuccessful challenge of an arbitral award. The decision highlighted the opposite principles in place between...
Skip to content