He mea hanga motuhake, he mea hanga motuhake rawa rānei – te take o tētahi rarangi ADR kāore i taea te whakamana

I roto i tētahi whakataunga Ingarihi tata nei, i whakatau te Kōti Hangarau me te Hanganga he whakaritenga mua tētahi rarangi i roto i tētahi kirimana hanga e kī ana kia tukuna he tautohe e ngā rōpū ki te ADR hei tīmatanga mō te whakawakanga i roto i ngā kōti. Heoi, i whakatau anō te Kōti kāore e taea te whakamana i tēnei rarangi ADR, nā te mea kāore i te tino mārama, i te tino pono rānei te tukanga i whakatakotoria e ia.
Kaituhi: Kate Holland
Tohu Āwhina

Papamuri – ngā rōpū me te kaupapa

I roto i te keehi Children's Ark Partnerships Ltd v Kajima Construction Europe (UK) Limited me Kajima Europe Limited [2022] EWHC 1595 (TCC) i pā ki te whakawhanaketanga anō o tētahi hōhipera tamariki.

I te marama o Hune 2004, i uru atu a Children's Ark Partnerships Ltd ( Ark ) ki tētahi whakaaetanga whakawhanake me Brighton and Sussex University Hospital Trust (te Hospital Trust ) mō te whakawhanaketanga anō. Mā te kirimana i te rā kotahi (te Kirimana Hanga ), i utua e Ark a Kajima Construction Europe UK Limited ( Kajima ) ki te hoahoa me te hanga i te hōhipera.

He whakairo mata āhua-pōturi

He wāhanga ADR motuhake i roto i te Kirimana Hanga

I roto i te Kirimana Hanga he tikanga whakatau tautohe rerekē kua whakaritea (te rarangi ADR ) i whakaahuahia e te Kōti me ngā māngai o ngā rōpū he mea miharo, he mea rerekē hoki . I roto i te rarangi ADR i hiahiatia kia tukuna e te rōpū ngā tautohe katoa ki tētahi 'Komiti Hononga' e whai ana ki te whakatau i te tautohe i roto i ngā rā 10 o te tukunga. Ka kitea, ko ngā ngoikoretanga me te koretake o tēnei tikanga ADR kua whakaritea i puta ai he mate ki te ngana a Kajima ki te whakawhirinaki ki tēnei hei tauira mō te tīmatanga o te whakawakanga.

Te kitenga o ngā hapa me te hiahia kia whakatikatikahia

I roto i te Kirimana Hanga he rarangi here e kī ana kāore e taea te whakahaere i ngā whakawakanga ki a Kajima i muri i te paunga o ngā tau 12 mai i te rā i oti ai te kaupapa. Ko te tikanga kia pau tēnei wā here i te marama o Āperira 2019.

E ono marama i mua i te paunga o te wā here, ka kitea ngā hapa o te whakakikorua, ā, ka whakaae a Kajima ki te whakahaere i ngā mahi whakatikatika i runga i tana ake utu. Hei whakaiti i te whakararuraru i te hōhipera, ka whakaae a Kajima ki te mahi āta haere i ngā mahi whakatikatika, me te whakaroa i te wā here ki te 29 o Hakihea 2021, i te mea kei te haere tonu ngā whakatikatika.

Ka tīmata te tautohe a Ark i roto i te Kōti, ka tono a Kajima kia whakakorea, kia whakarērea rānei

I te mea kei te toe tonu ngā take, ā, kua tata te paunga o te wā whakawhāiti kua roa ake, i tukuna e Ark ngā tono ki te TCC i te 21 o Hakihea 2021. Engari i tono anō hoki ki te Kōti kia whakaroahia ngā tono kia taea ai te tuku i te tautohe ki te tukanga ADR o te Kirimana Hanga.

Hei whakautu, i tono a Kajima ki te Kōti kia whakakorehia, kia whakakorea rānei te kereme a Ark i runga i te whakaaro ko te rarangi ADR i roto i te Kirimana Hanga he whakaritenga mua mō te tīmatanga o te tautohe, engari kāore a Ark i tutuki.

Te tono a Kajima kia whakakorea/kia tahaki – he tauira rānei te rarangi ADR mō te whakawākanga ture?

I kitea e te Kōti, kia taea ai e Kajima te whakakapi i te rarangi ADR i roto i te Kirimana Hanga te whai i tētahi whakaritenga whai mana me tutuki i mua i te whakaputanga a Ark i ngā tukanga kōti, arā, he whakaritenga tauira . Ko ngā take i tika kia whakatauhia ko:

  • He whakaritenga tauira te rarangi ADR mō te tīmatanga o te tautohe ture?
  • Mena he whakaritenga tauira te rarangi ADR, i taea rānei te whakamana?
  • Mehemea i taea te whakamana i te tauira o te herenga ADR, i rahua rānei e Ark te whakatutuki i taua whakaritenga?

I te whakautu i ngā pātai o runga ake nei, i kitea e te Kōti he tauira whakaritenga te rarangi ADR engari kāore hoki e taea te whakamana. Nō reira, kāore i hiahiatia kia whakaarohia te take tuatoru.

I waiho te rarangi ADR hei whakaritenga mō te whakawakanga ture?

I whakatau te Kōti ahakoa kāore i whakamahia e te Kirimana Hanga te kupu 'tauira whakaritenga' e pā ana ki te rarangi ADR, ko te kaupapa matua o ngā rarangi e tika ana i huihuia ko te tukanga ADR he tauira whakaritenga hei tīmatanga i ngā mahi i roto i ngā kōti. I te whakautua o tēnei me te whakaae, ka haere tonu te Kōti ki te whakaaro mēnā ka taea te whakamana i tēnei tauira whakaritenga ADR.

Whenua o Aotearoa

I taea rānei te whakamana i te whakaritenga ADR i mua?

I whakatau te Kōti, kia taea ai te whakamana, me mārama, me tino pono hoki te tukanga ADR mā te aro ki ngā paearu whaitake . [1] I aro te Kōti ki ētahi mana whakahaere e tūhura ana i ngā āhuatanga o te mārama me te tino pono [2] o tētahi tukanga ADR, kātahi ka whakarārangihia he raupapa o ngā ngoikoretanga o te tukanga ADR i tēnei take. Ko te mea tino nui i roto i tēnei tātaritanga ko te mea i roto i te Komiti Hononga e whakahaere ana i te ADR he māngai nō Ark me te Hospital Trust, engari kāore i uru mai he māngai nō Kajima.

I kitea e te Kōti kāore i te tino mārama, i tino mōhiotia rānei te tukanga ADR i konei nā te mea:

  • Kāore i kitea he whakamārama whai tikanga mō te tukanga hei whai. I taea e te Komiti Whakawhitiwhiti te hanga i āna ake ture me āna ake tukanga, engari kāore i kitea he taunakitanga mō ngā mea e tika ana kia whakaurua e aua ture me āna tukanga. Nō reira, kāore i kitea he whakapau kaha ki te whai wāhi ki tētahi tukanga ADR.
  • Kāore i te mārama me pēhea te tuku i tētahi tautohe ki te Komiti Whakawhitiwhiti Kōrero, ā, nō reira kāore i te mārama āhea ka tutuki ai te whakaritenga o mua.
  • Kāore i te mārama me pēhea te tautuhi, te whakatau rānei a te Komiti Whakawhitiwhiti i tētahi tautohe i te mea ehara a Kajima i te mema o te Komiti, ā, kāore he herenga, he tika rānei ki te whai wāhi atu ki te tukanga. Kāore hoki i te mārama he aha te pānga o tētahi whakataunga a te Komiti Whakawhitiwhiti ki a Kajima.
  • Kāore i te mārama he aha te tūranga o te Hospital Trust, hei mema mō te Komiti Whakawhitiwhiti.

Whakataunga

Ahakoa i kitea e te Kōti ko te rarangi ADR he whakaritenga tauira mō te tīmatanga o te tautohe, i kīia kāore te tukanga ADR e whakaahuatia ana i roto i te Kirimana Hanga i te tino mārama, i te tino pono rānei hei whakarite i tētahi whakaritenga tauira whai mana. I whakakorehia te tono a Kajima ki te whakakore, ki te whakakore rānei i te kereme a Ark nā te mea i 'rahua' te rarangi ADR. Nō reira, ka taea te haere tonu te tono a Ark.

Whakamutunga

E whakaatu ana te whakataunga a te TCC i te hiranga o te whiriwhiri i tētahi tikanga ADR pakari, e mōhiotia ana. He mea nui kia mārama, kia kore e ruarua tō kirimana mō te tikanga, ngā ture rānei ka whāia, kia taea ai e koe te whakawhirinaki me te whakamana i tō rarangi ADR ina hiahiatia. He mea whakamīharo, kua tukuna e te Kōti Pīra te whakaaetanga ki a Kajima ki te pīra. Kei te tumanako mātou ki te whakarongo me te tuku pūrongo mō te putanga.

Ngā Tohutoro

[1] Te whakahua i a Ohpen Operations UK Ltd v Invesco Fund Managers Ltd [2019] BLR 576 i [32(iii)].

[2] Holloway v Chancery Mead Ltd [2007] 117 ConLR 30 i [81]; me Tang v Grant Thornton International Ltd [2013] 1 All ER (Comm) 122 i [60].

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

Te mōrearea ahi – kei te wera haere ngā tautohe mō te whakakikorua hapa

I Ingarangi me Wales, ko te Kōti Hangarau me te Hanga i roto i te keehi Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 Hōngongoi...
Whare noho o Cliffside
Whānui

Ko te "tikanga ine" ki te aroha ki tō hoa tata: te whakararuraru tūmataiti me ngā tūponotanga ā-taiao

Kua hinga tētahi kaipupuri whenua o Ōtautahi, kei te take o tētahi whenua pari koretake i hokona e te Karauna whai muri i ngā rū whenua o Canterbury, i tana...