Kua mutu te rarangi hinganga: kua toa te whutupōro Ingarihi… he tika ki te kawe kereme ki te kaiwhakatū kirimana

Tata ki te 10 tau i muri mai, kua toa te whutupōro Ingarihi i te Ipu o te Ao Whutupōro 2015. I roto i te whakataetae FM Conway Ltd v Rugby Football Union , [1] i ngana tētahi kamupene i kirimanahia e te English Rugby Football Union (te RFU ) mō ngā mahi tiaki i Twickenham ki te whakawhirinaki ki te meka i inihua tahitia kia kore ai te RFU me te kaiinihua e tono utu mō ngā kino. I ārai te Kōti Pīra o Ingarangi (te Kōti ) i ngā kereme a te kaiwhakatū, i kitea kāore i te whai whakaaro arumoni ki te kī ka taea e tētahi rōpū te karo i te kawenga mō āna ake mahi hapa nā te mea he inihua tahitia.

E ai ki te Kōti, he mea noa te inihua-tahi i roto i te umanga hangahanga, ā, ka raru pea. Ka whakaratohia e te whakataunga he kōrero whai hua mō te huarahi e taea ai e ngā rōpū te whakatau ko wai kei te inihuahia, ā, mō te aha.
Kaituhi(ngā): Alexander Lyall

Papamuri

I roto i te whakarite mō te Ipu Whutupōro o te Ao 2015, i tukuna ki te RFU te mahi ki te whakarite kia tau ngā papa tākaro kua tohua o Ingarangi mō ngā kēmu. Ko te mahi nui ko te pakari o Twickenham. Hei wāhanga o te mahi, i utua e te RFU a Clark Smith Partnership Limited ki te hoahoa i ngā paipa hei tautoko i ngā taura hiko ngaohiko teitei puta noa i te papa tākaro. Kātahi ka utua e te RFU te kamupene ratonga hanganga a FM Conway ki te tāuta i ngā paipa.

He rārangi o ngā whakaaetanga

I te whakawhitiwhiti kōrero a te RFU me FM Conway, i hainatia he raupapa whakaaetanga i waenganui i te tokorua.

Ko te tuatahi he reta whakamana (te reta ). E rua ngā wāhanga he mea tino hira. I roto i te wāhanga 3 i kīia ko te whāinga o ngā rōpū he haina i tētahi kirimana i runga i te JCT Standard Building Contract Without Quantities 2011 (te kirimana JCT ). He mea nui tēnei nā te mea kei roto i te kirimana JCT he kaupapa here inihua mō ngā tūponotanga katoa. I taua wā, i roto i te wāhanga 21 i kīia ko te reta hei whakakapi i tētahi atu tohutohu, whakaaetanga rānei kei roto i ētahi atu tuhinga reta.

I tēnei wā, i whakarite hoki te RFU kia inihuatia ki a Royal & Sun Alliance Limited (te kaiinihua ). I whakaae te RFU me FM Conway mā te RFU e hoko inihua mā FM Conway. I whakaritea angitu tēnei, ā, i uru atu a FM Conway ki te RFU i runga i te kaupapa here inihua (te kaupapa here ).

I roto i te rarangi 1(f) o te kaupapa here he kupu i whakakore i ngā mana whakakapinga. I raro i te kaupapa here o te whakakapinga, ka taea e te kaiinihua te whakahoki mai i tana mate mā te whai ture i te rōpū nāna i puta te kino i herea te kaiinihua ki te hipoki. I te mea kua whakakorea tēnei mana, ka tiakina e te kaupapa here te RFU me te FM Conway mai i te whai ture a te kaiinihua. Heoi, i whakamāramahia i muri mai i roto i te Kōti Matua me te Kōti Pīra, ka pā tēnei mēnā ehara rātou i te take o te kino i hipokina.

E toru marama i muri i te whakaritenga a te RFU i te inihua, ka hainatia e te RFU me FM Conway te kirimana JCT.

Ka whiua e FM Conway te pōro

I te tata mai o te Ipu Whutupōro o te Ao 2015, i kitea he wai me he paru i roto i ngā awaawa o Twickenham. Neke atu i te £4 miriona te utu mō ngā mahi maha hei whakakapi i ngā awaawa hapa, ā, i tono te RFU i tētahi kereme i raro i te kaupapa here. I utua e te kaiinihua te £3 miriona o tēnei, ā, nō reira i tono te RFU i te £1 miriona whakamutunga mai i a FM Conway.

I whakaarohia hoki e te kaiinihua ko FM Conway te kawenga, ā, i whakamahia e ia ōna mana whakakapinga ki a FM Conway hei whakahoki mai i tana mate. Nō reira, ka tīmata a FM Conway i ngā whakawakanga ki te RFU me te kaiinihua, me te tautohe he inihua tahi, ā, nā reira, kāore e taea e te RFU te tono utu mō ngā utu kino ki a ia, ā, kāore e taea e te kaiinihua te whai i ana mana whakakapinga.

I tautohetia te whānuitanga o tēnei hipoki i waenganui i ngā rōpū. I tautohe te RFU me te kaiinihua kāore ō rāua mana ki te kereme utu i whakakorea nā te mea kāore a FM Conway i hipokina e te kaupapa here. I whakaae te Kōti Matua ki tēnei, ā, i piira a FM Conway ki te Kōti Pīra.

I whakatau te Kōti Pīra i te RFU me te kaiinihua kia whiua

Tuatahi, kāore i kitea e te Kōti he raruraru mō te tautuhi i a FM Conway hei rōpū inihua. E toru ngā rōpū i tautuhia e te kaupapa here hei tāngata inihua , ā, e rua o ēnei wāhanga i pā ki ngā kaimahi kirimana.

Heoi, ko te kaupapa matua o te take, e ai ki tā Lord Justice Coulson, ahakoa kua inihuatia a A rāua ko B i raro i te kaupapa here kotahi, ehara i te mea ko A rāua ko B anake kua hipokina mō te mate kotahi, kāore rānei e taea te kereme tetahi ki tetahi . I whakaae a Lord Justice Coulson he mea rerekē pea ahakoa he inihua tahi a FM Conway i raro i te kaupapa here, he rerekē tana hipoki. [2] Me te whakaaro ki tēnei, me whai whakaaro te kooti ki te hiahia o ngā rōpū me te pehea i uru ai ki te whānuitanga o te hipoki. I kōrero te Kooti me pēhea te mahi i tēnei.

Tirohia te kirimana matua hei whakaaroaro i te mana me te whāinga

I whakaae te Kōti Pīra ki te Kōti Matua kia whakaarohia tēnei kaupapa inihua he kaupapa here inihua whakakotahi; he tikanga hei wetewete i ngā take inihua-tahi i whakawhanakehia tuatahitia i roto i te General Accident Fire and Life Assurance Corporation Limited & Anor v Midland Bank Limited . [3] Ko te tikanga o tēnei me whakaaro ia tangata kua inihua-tahi me te mea he kaupapa here tā rātou ake. Kātahi ka whakamāramahia e te kirimana matua te hiahia o ngā rōpū mō te whānuitanga o aua kaupapa here. I roto i te Gard Marine Energy Limited v China National Chartering Co Limited & Anor , [4] i tautuhia e Lord Justice Coulson ko te take matua mō te take, i kiia te kirimana matua he mea nui ki te aromatawai i tēnei whānuitanga. Mena ko te hiahia o te kirimana matua he iti ake te kapinga, kātahi ka tukuna.

Te hiranga o te kirimana JCT

I tautohe a FM Conway kāore te kirimana JCT i rite te hiranga ki te kaupapa here, nā te mea kua hainatia te kaupapa here i ngā marama e toru i mua i te kirimana JCT. I whakatau a Lord Justice Coulson kāore he mātāpono i roto i te ture Ingarihi e kī ana kāore he pānga whakamuri o tētahi kirimana i tēnei ara. He pono rawa tēnei nā te mea i roto i te reta, i hainatia i te tīmatanga o tā rāua whanaungatanga, i tohutohu mārama a) me mahi te kirimana JCT hei whakaaetanga mā rāua; me te b) ko te reta, i whakaū i te kirimana JCT, ka whakakapi i tētahi atu whakaaetanga i waenganui i ngā rōpū. Ahakoa pēhea, i whai mana te Kōti Matua ki te whai pānga ki te kirimana JCT i muri mai.

I whakamāoritia hētia te whakaritenga whakawātea e FM Conway

I tautohe a FM Conway ka taea e ia te whakawhirinaki ki te rarangi 1(f) o te kaupapa inihua. Koinei te tautohe kaha rawa atu, ā, ko te tautohe tika rawa atu a FM Conway, me te whakaae a Lord Justice Coulson ka taea e ia te hinga i ngā tohu katoa engari ka toa i tēnei. Heoi, i roto i te tirohanga a Lord Justice Coulson, he rerekē tēnei i te whakaaro noa arumoni. Nā ōna ake hapa i ngaro ai te hipoki o FM Conway i raro i te kaupapa here. Nō reira, he hua tino whakamiharo mēnā ka taea e FM Conway te kimi hipoki nā tēnei whakakorenga. Ko te whiwhi hipoki tēnei mā te tatau o muri . I tangohia e Lord Justice Coulson te tātari i tangohia i roto i te National Oilwell v (UK) Ltd v Davy Offshore Ltd. [5] I roto i tēnei whakataunga, i whakatauhia he rite tonu te mahi a te rarangi whakakorenga ki te kaupapa arumoni o te kirimana, ā, kāore e taea te whakawhānui kia rite ki tētahi atu whāinga.

Whakamutunga

Ahakoa e whakaatu ana te whakataunga a te Kōti i ngā uauatanga o te inihua-tahi, e tohu ana hoki i ētahi mātāpono mārama. Kāore he pātai ka taea e ngā rōpū te noho i raro i te kaupapa here kotahi; engari ki te mea ko te kaupapa he rerekē ngā taumata hipoki, koinā te mea ka hoatu. Kua whakaū anō te Kōti i te whakaaro noa. Mena nā tētahi rōpū i puta te kino, ā, e kī ana te kaupapa here ka tangohia tana hipoki, kāore e taea e ia te whai hua mai i te whakakorenga o te whakakapinga. Arā, ka takahia e koe, ka hokona e koe.

Ngā Tohutoro

[1] FM Conway Ltd v Rugby Football Union [2023] EWCA Civ 418.

[2] He waimarie , e ai ki te pūrongo a Lord Justice Coulson, kei te ture te whakautu katoa ki tēnei raruraru .

[3] Accident Fire and Life Assurance Corporation Limited & Anor v Midland Bank Limited [1940] 2KB 388.

[4] Gard Marine Energy Limited v China National Chartering Co Limited & Anor [2017] UKSC 35, [2017] 1 WLR 1793.

[5] National Oilwell v (UK) Ltd v Davy Offshore Ltd [1993] 2 Lloyd's Rep 582.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

Ngā whakaroa wā i roto i ngā kirimana hanga

I roto i tētahi kereme mō te whakaroa i te wā, he mea nui te whakaaro ki te whakapae mō te whakaroa i te aromatawai i te mea "tika me te whaitake".

I roto i te CAJ...