Ehara te pūnaha utu hangarau i te kaupapa matua i raro i te Ture Kirimana Hanga

I roto i te keehi Dem Home Ltd v New Gate Ltd [1], i whakaarohia e te Kōti Matua mēnā i tukuna tika te kereme utu i raro i te Construction Contracts Act 2002 (te CCA). He whakamaharatanga nui tonu te whakataunga kua hangaia te CCA hei pupuri i te rere o te moni i roto i te umanga hanga.
Kaituhi(ngā): Alexander Lyall

Papamuri

I utua e Dem Home Limited a New Gate Limited ki te hanga whare papa i Point England, Tāmaki Makaurau. I mua i te otinga o te hanganga, i whakapae a Dem Home mō te takahi kirimana a New Gate, ā, i whai kia whakakorehia te kirimana. I tukuna e New Gate he kereme utu mō te $242,500.50, engari i warewarehia e Dem Home. Nā te kereme utu i warewarehia i akiaki a New Gate ki te tuku tono ture ki a Dem Home. [2] Hei whakautu, i tono a Dem Home ki te Kōti Matua kia whakakorehia te tono ture. I whakahē a New Gate i te tono.

Ngā Take mā te Kōti Matua

E toru ngā take i tautuhia e te Dem Home i kore ai te kereme utu i raro i te CCA:

  1. Kāore te kereme utu i tutuki i ngā whakaritenga ōkawa.
  2. Kāore i whai mana a New Gate ki te tuku i te kereme utu i taua wā.
  3. I tukuna i muri i te whakakorenga a te Dem Home i te kirimana hanga.

Whakataunga a te Kōti Matua

Ko te kaupapa o te CCA te tīmatanga mō te Kōti Matua. I te kōrero mō Demasol v South Pacific Industrial Limited , [3] i whakarāpopototia e te Kōti Matua te huarahi hei whai. [4] Me whakakore e tetahi tātaritanga o te CCA te whakamaoritanga "hangarau" me te "ōkawa" rānei, nā te mea ka takahi tēnei i te hiahia o te Paremata kia mau tonu te rere o te moni i roto i te umanga hanga .  

I rahua te kereme utu ki te whakatutuki i ngā whakaritenga ōkawa?

Kei roto i ngā Wāhanga 20(2)(3) me te (4) o te CCA ngā whakaritenga kia whai mana ai tētahi kereme utu. Ko ētahi o ēnei ko te tuhi i te kereme utu, ā, e kī ana te kereme kei raro i te CCA te kereme.

I kitea e te Kōti he kereme tuhituhi te kereme. Kāore i te kōrero te kereme, ā, he maha ngā kōrero i roto e hono ana i te kereme ki te utu i tonoa. I tautohe anō a Dem Home he iti ngā momotuhi o ngā kōrero e tika ana, engari i te whakataurite i ngā rahi momotuhi, i kitea he hē tēnei.

I taua wā, kāore i taea e New Gate te tuku kereme utu?

I roto i tā rāua kirimana, i whakaae a New Gate me Dem Home e tika ana kia tukuna e New Gate he kereme utu ina oti ētahi mahi. I tautohe a Dem Home kāore tēnei i tupu.

I titiro anō te Kōti ki a Demasol . Ki tā rātou titiro, i tino whakakorehia e te whakataunga te huarahi i tangohia e te Dem Home hei whakamutu i te kereme utu. I tika kia whakahēngia te kereme utu e te Dem Home i roto i te ahua o tētahi maramataka utu. Nā te korenga o te Dem Home i whakaputa i te maramataka utu i roto i te wā i whakaritea, kāore i taea e ia te whakamahi i te take tautohetia hei ngana ki te whakakore i te tono ture. 

Kāore e whai mana te kereme utu mēnā i tukuna i muri i te whakakorenga o te kirimana e te Dem Home?

E rua ngā tautohe a New Gate hei whakautu i tēnei take. Ko te tuatahi, kāore te kirimana i whakakorea. Ko te tuarua, ahakoa kua whakakorea te kirimana, kei te whakamahia tonu te tikanga utu i roto i te CCA. Ahakoa kāore te Kōti i aro atu mēnā kua whakakorea te kirimana, i kitea anō e ia me whakautu ngā tautohe katoa mā te kereme utu.

I whakakorehia e te Kōti te tono a te Dem Home kia whakakorehia te tono ā-ture.

Ngā Tohutoro

[1] Dem Home Ltd v New Gate Ltd [2023] NZHC 2709.

[2] He tuhinga whaimana te tono ture i tukuna ki tētahi kamupene e kī ana he nama kei a ia. Mēnā kāore te kamupene e tutuki i te tono ture, ka taea te tūtaki ki te korenga o te moni i raro i te Wāhanga 16 o te Ture Kamupene 1993.

[3] Demasol v South Pacific Industrial Limited [2022] NZCA 480.

[4] Dem Home Ltd , i runga ake i te n 1, i te [25].

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

Ngā whakaroa wā i roto i ngā kirimana hanga

I roto i tētahi kereme mō te whakaroa i te wā, he mea nui te whakaaro ki te whakapae mō te whakaroa i te aromatawai i te mea "tika me te whaitake".

I roto i te CAJ...
Whānui

Ka whakamutua e te kaihanga te kirimana me te "aroha mai e hoa...kei te tino piki haere ngā utu"

I te mea kei roto te umanga hanga i te korenga o ngā kaimahi me ngā taonga, me te pikinga o ngā utu, he whakatau tata nei nā te kooti o Kuīnirani...
Te ara o te kura
Whānui

Tērā pea ka uaua haere ngā āhuatanga – ka whakakahore te Kōti Matua o Ingarangi ki te whakamutu i ngā tukanga i tukuna mai i roto i te takahi i tētahi whakaritenga ADR ka taea te whakamana

Me pēhea te whakatau a ngā kōti i ngā āhuatanga ina tīmata tetahi rōpū ki tētahi tautohe i ngā mahi ture e takahi ana i tētahi rarangi kirimana e kī ana...