Whakaaturia Mai Te Moni: E Whitu Ngā Mea Hei Maharahara Ina Whakarite Ana I Te Kereme Utu

Kei te tatari tonu koe kia utua te nama i tukuna e koe i ngā tau kua pahure ake nei? Kua oti katoa i a koe ngā mahi engari kāore he mea hei whakaatu? Ka pā kino pea ngā nama kāore i utua ki ngā kaihanga me ngā kaimahi kirimana. He waimarie, kei te whakaratohia e te Construction Contracts Act 2002 ngā huarahi hei āwhina i te tere o te utu o ngā nama. Anei ngā mea e whitu hei maumahara māu ina tukuna ana tō nama (e mōhiotia ana ko te kereme utu), kia tino whiwhi ai koe i te mea e tika ana kia utua e koe:
Kaituhi(ngā): Amy McDonald

1. Me tuhituhi te kereme utu

He mea nui tēnei! Ahakoa he kirimana tuhituhi, he kirimana ā-waha, he kirimana rānei e rua, kāore e ranea te waea atu, ahakoa te roa, te whaimana rānei. He haumaru te tuku īmēra! Ki te ruarua koe, tuhia.

2. Me mārama te hononga ki te kirimana hanga

Me whai taipitopito i roto i tō kereme utu hei tautuhi i te kirimana hanga e pā ana te utu.

Me whakarite kia rawaka ngā mōhiohio i homai i roto i te kereme utu hei tautuhi i te kirimana hanga motuhake e keremehia ana e koe kia utua, inā koa mēnā he maha ā kōrua kaupapa me tō kiritaki.

He maha ngā wā, mā te tautuhi i te wāhi mahi motuhake ka rawaka hei tautuhi i te kirimana motuhake.

3. Whakarāpopototia te mahi i oti me te wā i oti ai

Tāutuhia te mahi hanga me te wā e pā ana ki te utu.

I roto i ngā kaupapa nunui, kua whakaritea pea e koe ngā utu ahunga whakamua kua whakaritea: me tohu i roto i te kereme utu te wā e keremehia ana e koe te utu. I roto i ngā mahi iti ake, he nui te tautuhi i te mahi i mahia me te wā i oti ai.

Ahakoa pēhea, kia tino mārama te whakaahuatanga o ngā mahi, me te tautuhi anō hoki i te wā i mahia ai.

4. Tāpirihia te moni me te rā mō te utu

Me whakamārama mārama te moni i tonoa me te rā e tika ana kia utua.

Ko te moni e tohua ana i roto i te kereme utu me rite tonu ki te moni e nama ana ki a koe, kaua ki te moni noa iho.

Me whakatakoto hoki te rā kua tohua ki tētahi rā motuhake hei whakaiti i te pōhēhētanga. Tirohia tō kirimana, ngā T&C rānei, kia kite ai mēnā kua whakaritea e koe he wā utu paerewa mō ngā kereme utu.

Mena kāore anō kia whakatūria e koe tētahi mea motuhake, ko te wā taunoa i raro i te Ture he 20 ngā rā mahi. Me hoatu e koe ki tō kiritaki he 20 ngā rā mahi hei utu.

5. Whakaaturia te āhua o te tatau i te moni

Me mārama te whakamārama me pēhea koe i tae atu ai ki te moni e nama ana i roto i te kereme.

Me mārama te whakaahuatanga o ngā mahi i mahia, me te tikanga i whakamahia hei tatau i te moni e utua ana. Mō ngā mahi iti ake, he tino māmā noa iho te tatau: kua oti te papa o te wharepaku, kua oti rānei i a koe te 60% o ngā mahi e hiahiatia ana mō te whakahoutanga o te kīhini.

6. Kīia kei raro i te Ture te kereme

Kotahi te rārangi – Kaua e wareware ki te tāpiri i tēnei rerenga kōrero katoa:

" He Kereme Utu tēnei i raro i te Ture Kirimana Hanga 2002 ".

7. Me haere tahi mai me tētahi pānui tuhituhi e mōhiotia whānuitia ana ko te Puka 1:

E whakaahua ana tēnei pānui i te tukanga whakautu ki te kereme utu, me te whakamārama i ngā hua o te kore whakautu, te kore utu rānei. E whakamārama ana hoki me pēhea te whakautu atu. Tērā pea ka rerekē tēnei pānui i ia wā, i ia wā. Kia tino whakamahia tonutia te putanga hou.

Hei whakamutunga, tirohia te whārangi Aratohu me ngā Rauemi i tō mātou paetukutuku mō ētahi atu kōrero. Ki te hiahia koe ki te haere tika ki te pūtake, ka taea e koe te pānui atu i te paetukutuku ture mana .

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

Kane v Venues NSW: Te Kōrero mō te Rerewē

Ko te take o Venues NSW v Kane [2023] NSWCA 192, e pā ana ki te hinganga o tētahi kaitautoko i roto i te wāhi o raro o te papa tākaro o te taha hauauru o te...
Whānui

Te whakamātautau i ngā wai: E whai whakaaro ana te Kōti Matua o New South Wales ki te mātāpono ārai

Ka whakaū anō te Kōti ka taea te whakakore i te mātāpono ārai e ngā tikanga o te kirimana....
Whānui

Ko te tangata inihua te kawenga: Kua whakakorehia e te Kōti Matua te herenga kua whakaritea mō ngā kaiinihua

I roto i te keehi IAG New Zealand Limited v Degen, [1] i arotake anō te Kōti Matua (te Kōti) mēnā i herea a IAG e te kawenga ki te...