Ngā Huringa Kua Whakatakotoria ki te Pūnaha Pupuri Hanganga

Kaituhi(ngā): Hannah Stanley
Tātaitanga Whare
Ahakoa te whakaurunga o te pūnaha pupuri ki roto i te Ture Kirimana Hanga 2002 (te Ture) i te tau 2017 [1] , he maha tonu ngā pupuri a ngā kaimahi kirimana iti kāore i tiakina, ā, kua hurahia ngā āputa maha i roto i te ture. I kitea ēnei ngoikoretanga e te korenga o Ebert Construction me te hua o ngā tautohe a ōna Kaiwhiwhi mō ngā tohutohu mō te whakahaere i tētahi pūkete pupuri kāore i te rawaka [2] . I te tau 2020, i panuitia e te Kāwanatanga ētahi huringa hei whakapakari i te pūnaha pupuri i roto i te Ture. Kua whakaurua ēnei huringa ki roto i tētahi whakatikatika hou ki te Ture [3] e tirohia ana i raro nei.
Te Whanga o Queenstown

Te tikanga pupuri o nāianei

Ko ngā moni pupuri he moni e puritia ana e tētahi rōpū ki tētahi kirimana hanga mai i tētahi moni e utua ana ki tētahi atu rōpū. Ko te tikanga he āhuatanga i waenganui i tētahi kaiwhakatū (te kaiutu) me tētahi kaiwhakatū iti (te kaiwhiwhi). Ka puritia e te kaiutu tētahi ōrau o ngā moni e utua ana hei momo pūtāhui, hei whakarite hoki kia mahia te mahi ki tētahi paerewa tika [4] me te whakatutuki i ngā herenga i raro i te kirimana. Ko ngā moni pupuri ka utua i te nuinga o te wā ina pau te wā nama, ā, ka roa pea mō ētahi marama.

E mea ana te Ture kāore te moni pupuri e kiia he mea pupuri i runga i te whakawhirinakitanga, engari me pupuri noa i runga i te whakawhirinakitanga [5] . He maha ngā wā ka konatunatua ngā moni pupuri ki te whakapaipai mahi a te kamupene hanga (nā te mea he mea tika kia haere tonu ai ngā kaupapa o nāianei me/ranei ngā kaupapa o muri mai). Kāore tēnei e tupu mēnā he whakaritenga whakawhirinakitanga tikanga kei te whakamahia. [6] E pā ana ki tēnei, kāore he whakaritenga o te kaupapa o nāianei i raro i te Ture kia puritia te moni pupuri ki roto i ngā pūkete peeke motuhake. Nō reira, ina tae ki te wā ki te utu i ngā moni pupuri ki te kaiwhiwhi, tērā pea kāore te moni e wātea ana, hei tauira, tērā pea kua riro te kamupene hanga ki te mana whakahaere i muri i te tīmatanga o te kaupapa.

Ahakoa he nui te mōrearea o ēnei āhuatanga ki ngā kaiwhiwhi, kei reira tonu ngā whiu kāore e tika ana mō ngā rōpū kāore e tutuki i ngā whakaritenga o te whakawhirinakitanga i raro i te Ture. I tēnei wā, he tino māmā te mawhiti atu i te kore tutuki i ngā whakaritenga, ā, ko te mutunga iho, ka waiho te kaiwhiwhi kia kore e utua.

Te Pire hou

I te 1 o Hune 2021, i whakaurua te Pire Whakatikatika mō ngā Kirimana Hanga (Moni Pupuri) (te Pire). E whakaaro ana te Pire kia whakapakarihia te pūnaha pupuri moni o nāianei mā te tūtohu i ētahi huringa nui. Ko te nuinga o ngā huringa kua tūtohutia e aro ana ki te whakapai ake i te tiakitanga (te kore rānei o taua tiakitanga) e tukuna ana ki ngā kaiwhiwhi.

Puritia i runga i te whakawhirinaki

E whakaaro ana te Pire kia puta he whakawhirinakitanga ture ina huri ngā moni hei moni pupuri [7] . E whakatau ana ko te moni pupuri he taonga whakawhirinaki, ahakoa kua piri te kaiutu ki te tikanga pupuri i raro i te Ture, kāore rānei [8] . I te mea kua waiho ngā moni pupuri hei taonga whakawhirinaki i raro i te ture, ka puritia motuhaketia te moni pupuri mēnā ka kore e taea te utu e te kamupene. He nui ake te tiaki a tēnei i te kaiwhiwhi i te tikanga o nāianei. Hei taonga whakawhirinaki, ka tiakina te moni pupuri kei konatunatua ki te whakapaipai mahi a te kamupene utu, ā, ka whai mana ngā ture o te ture noa me te tika e pā ana ki ngā whakawhirinaki.

Ka mutu te whakawhirinakitanga ina utua katoatia ngā moni pupuri ki te kaiwhiwhi, ina mutu rānei te utu mō tētahi atu take (hei tauira, kāore pea te kaiwhiwhi i mahi i te mahi ki te paerewa e tika ana). Mena ka whakatūria he kaiwhiwhi, he kaiwhakakore rānei, ka noho ko ia hei kaitiaki mō te moni pupuri, ā, ka mutu te kaiutu i te noho hei kaitiaki. [9] He mea nui tēnei hei tiaki i ngā kaiwhiwhi.

Ngā hara me ngā whiu

Kei roto i te Pire ngā whiu taumaha ake mō ngā kamupene me ngā kaiwhakahaere kāore e tutuki i ngā whakaritenga o te whakawhirinakitanga, ā, ko te kore tutuki i ngā whakaritenga ka kiia he hara i raro i te Ture. Ka taea te whiu i tētahi kamupene tae atu ki te $200,000 mō te kore tutuki i ngā whakaritenga [10] . Hei tāpiri, ka taea e ngā kaiwhakahaere o ngā kamupene kāore e tutuki i ngā whakaritenga te whakatau i a rātou anō kia whiua mō te whiu mōrahi o te $50,000 [11] . Hei ārai atu i te kore tutuki i ngā whakaritenga, ka whakaarohia he whakamāramatanga whānui mō te "kaiwhakahaere", mā te whakauru i te tangata e ahua ana kei te mahi i te tūranga kaiwhakahaere, ā, kei te mahi rānei i tētahi tūranga rite ki te tūranga kaiwhakahaere, ahakoa e whakamahia ana taua taitara, kāore rānei [12] . Ka nui ake te mōrearea ki ngā mema katoa o te whakahaere hanga.

Ngā pūkete peeke motuhake me ngā tuhinga whaimana

E hiahiatia ana e te Pire kia puritia te moni katoa o ngā moni pupuri e utua ana ki te kaiwhiwhi i roto i tētahi pūkete peeke o Aotearoa, i tētahi atu tuhinga rānei e whai mana ana [13] , pērā i tētahi kaupapa here inihua, i tētahi taurangi peeke rānei. [14] Kāore e taea te whakamahi i ia pūkete peeke motuhake mō tētahi atu kaupapa i tua atu i te pupuri i ngā moni pupuri, ā, me whakauru ngā kupu "pūkete whakawhirinaki moni pupuri" ki te ingoa o te pūkete.

Te pupuri tuhinga

E hiahiatia ana e te Pire kia puritia ngā tuhinga kaute tika kia taea ai te whakarite i ngā tauākī pūtea. [15] Me pupuri ngā pūkete pukapuka motuhake mō ia kaiwhiwhi utu (arā, mō ia kaimahi kirimana iti) me ia kirimana hanga takitahi. Ka pā anō hoki ngā herenga pupuri tuhinga rite ki ngā tuhinga e tutuki ana.

Ngā herenga whakaatu me te ripoata tonu

Kāore te Ture e whakatakoto ana i tētahi herenga mārama ki te ripoata i ngā taipitopito me te āhua o ngā moni pupuri ki te kaiwhiwhi. Nā tēnei ka noho pōuri te kaiwhiwhi mēnā kei te kaituku te nui tika o te moni pupuri e wātea ana hei utu i a rātou. E whai ana te Pire ki te whakatika i tēnei mā te tono kia tukuna ngā mōhiohio mō ngā moni pupuri ki te kaiwhiwhi i te wā e taea ai i muri i te pupuri i te moni, ā, i te iti rawa i ia toru marama i muri i tērā. [16] Ko tēnei pikinga o te māramatanga he painga pai anō mō ​​ngā kaiwhiwhi.

He huringa pai

Ahakoa kāore e kore ka piki ake te nui o te whakahaere e uru ana ki te whakahaere i ngā moni pupuri i roto i te Pire, ko te pikinga ake o te tiakitanga me te rere o ngā mōhiohio e tukuna ana e ia ki ngā kaiwhiwhi he tohu i ngā mahi pai, ā, he whakaata i ngā tikanga o tāwāhi. Kāore e taea e ngā kaiutu te whakamahi i te moni pupuri hei pūtea mahi, me te whakauru i ngā moni pupuri ki ētahi atu moni, nā te mea ka kiia ngā moni kei runga i te whakawhirinakitanga, ā, me pupuri hoki ki roto i ngā pūkete motuhake. Hei whakamutunga, ka whakaratohia he nui ake te haumarutanga ki ngā kaiwhiwhi ina tae mai ki ngā moni pupuri, ā, ka iti ake te tūponotanga kāore rātou e whiwhi moni pupuri i te mutunga o te wā nama.

Ngā taahiraa e whai ake nei

Kua tukuna te Pire ki te Komiti Waka me te Hanganga. Ko te rā kati mō ngā tukunga ko te 23 o Hūrae 2021, ā, ko te rā kati mō te pūrongo ko te 11 o Noema 2021. Mēnā ka paahitia te Pire, ka whai mana i roto i ngā marama e ono i muri i te whakaaetanga a te kingi, ā, pērā i ngā huringa pupuri taketake, e whakaarohia ana ko te nuinga o ngā whakaritenga hou ka pā noa ki ngā kirimana hanga i uru atu i muri i te whai mana o te Pire. Heoi, ko ngā huringa e pā ana ki te tūranga o te kaiwhakakore/kaiwhiwhi ka pā tika ki ngā whakakorenga/kaiwhiwhi katoa, ahakoa te wā i uru atu ai te kirimana.

Ngā Tohutoro

[1] Ko te pūnaha pupuri taonga i Aotearoa e whakahaeretia ana e ngā wāhanga 18A ki te 18I o te Ture Kirimana Hanga 2002 i whai mana i te 31 o Poutū-te-rangi 2017.

[2] Bennett & Ors v Ebert Construction Limited (i roto i te whakawhiwhinga me te whakakorenga) [2018] NZHC 2934.

[3] Pire Whakatikatika mō ngā Kirimana Hanga (Moni Pupuri).

[4] Bennett i [33].

[5] Te Wāhanga 18C o te Ture Kirimana Hanga 2002.

[6] Bennett i [71].

[7] Te Rārangi 18C(2) o te Pire.

[8] Te Rārangi 18C(4)(b) o te Pire.

[9] Te Rārangi 18J(2) o te Pire.

[10] Te Rārangi 18DA(1)(a) o te Pire.

[11] Te Rārangi 18DA(1)(b) o te Pire.

[12] Te Rārangi 18DA(3)(a) o te Pire.

[13] Te Rārangi 18D(2) o te Pire.

[14] Te Rārangi 18E o te Pire.

[15] Te Wāhanga 18FC(2)(a) o te Pire.

[16] Te Wāhanga 18FC(1) o te Pire.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

I hinga te kereme a te rōpū mahi mō te paninga Harditex

Kua rahua te tuarua o ngā kereme ā-rōpū [1] i kawea mai e tētahi rōpū o ngā kaipupuri whare 144 nō rātou ngā kāinga i whakakikoruatia ki te muka-sima Harditex. Ko te...
Whānui

Kua mutu te rarangi hinganga: kua toa te whutupōro Ingarihi… he tika ki te kawe kereme ki te kaiwhakatū kirimana

Tata ki te 10 tau i muri mai, kua toa te whutupōro Ingarihi i te Ipu o te Ao Whutupōro o te tau 2015. I roto i te whakataetae FM Conway Ltd...