Kei te haere mai te whakahoutanga ki te whakahaere i ngā miihini

I whakahaerehia e te Manatū Pakihi, Auahatanga me te Mahi (MBIE) tētahi hui kōrero i te tau 2021 hei whakahou i te pūnaha ture mō ngā kaihangarau. Ka neke atu ngā whakahoutanga mai i te kaupapa whakamana tūao ki tētahi pūnaha whakahaere ōkawa.
Kaituhi: Sam Dorne

Ngā ture o nāianei

He nui ngā ture whakahaere mō te peeke, te inihua, ngā tākuta, ngā rōia, te kai, te kawe waka, te rererangi me ngā rongoā i Aotearoa. Ko ngā miihini, arā, te hunga e kawenga ana mō ngā mahi hanga i Aotearoa (ngā whare, ngā rori, ngā piriti), kāore i te nuinga o te wā he ture whakahaere.

Engari, ko te mea e whakahaerehia ana i tēnei wā he kaupapa whakamana tūao mai i te whakahaere ngaio matua o te umanga – arā, ko te Hangarau o Aotearoa.

I tēnei wā, kāore he here mō ngā miihini ki te whakahaere, ki te tirotiro rānei i tētahi mahi miihini i runga i ngā whare. Ko ngā tohu mātauranga e tukuna ana e ēnei whakahaere ngaio, kāore i te hangaia hei whakarite i te pūkenga me te wheako mō ngā mahi mōrearea nui, kāore hoki e aukati i ngā miihini ki te mahi i ngā wāhanga kei waho o ō rātou tohungatanga. Kāore he tirotiro ture e pupuri ana i ngā miihini ki te kawenga, ā, ahakoa ka whakakorea e te tinana whakahaere tā rātou whakamanatanga, kāore he mea hei aukati i taua tangata ki te haere tonu ki te hoahoa i tētahi whare.

I roto i tētahi kōrero e haere tahi ana me ngā huringa ture kua whakaarohia, i mea a MBIE:

Ahakoa he tino ngaio te nuinga o ngā miihini o Aotearoa, me whakapai ake te pūnaha ture miihini. I te tau 2021, i kōrero a MBIE mō tētahi tikanga hou kua whakaarohia hei whakarite kia matatau ngā miihini, kia tika te whanonga, ā, kia whai kawenga hoki. Ko te whāinga o te tikanga hou he whakaiti i te tūponotanga o ngā mahi miihini hapa, me te whakapai ake i te whakapono o te marea ki te umanga. [1]

He hītori poto mō ngā raruraru hangarau o Aotearoa

He mārama ngā hua o te korenga o tētahi anga ture. He maha ngā take nui kua puta ake i roto i ngā tau, ā, nā ngā paerewa hangarau ngoikore i whai wāhi atu ki ēnei:

  • I te marama o Pēpuere 2011 i hinga te whare CTV i te wā o te rū whenua i Ōtautahi, ā, i mate ai te 115 tāngata. Whai muri i tētahi rangahau, i kitea he iti noa te wheako o te kaihoahoa, ā, i kitea ko tana kaiwhakahaere, he kaihoahoa matua (kei te mahi tonu ia tae noa mai ki tēnei rā), kāore i te tino tika tana tirotiro.
  • Ko te raruraru turuturu o ngā whare e haere tonu ana, e whakaponohia ana ko te ngoikore o te hangarau me te tirotiro he take nui i uru atu ai ki te tata ki te 11 piriona tāra te uara o ngā utu whakatika me te whakakapinga.
  • I whakaatuhia e tētahi rangahau i te tau 2019 e 1100 ngā whare he raima, he maitai whakapakari rānei he hapa, he ngaro rānei.
  • I te tau 2016, i mate te tokowhā o ngā tāngata, ā, neke atu i te 5000 i pāngia e te poke o te wai o Havelock North. Nā te pakaru o te hanganga i hua mai i te poke o te campylobacter, i pakaru ai te wai i Havelock North.

Te whakahoutanga kua whakaarohia

I te tīmatanga o tēnei tau i whakaae te Kāwanatanga ki te whakauru i tētahi ture hei whakatū i tētahi pūnaha whakahaere taumata-rua, me te whakatū i tētahi kaiwhakahaere hou hei tirotiro me te whakamana i ngā ture.

Kua kore te tiwhikete tūao. Engari, me rēhita ngā kaihangarau katoa, ā, me noho ki raro i te tirotiro a te rōpū whakahaere hou.  

Mēnā he mahi mōrearea nui, he mahi nui hoki e pā ana ki te haumaru, ka whakaurua he pūnaha raihana "taumata teitei" hei taha o ngā whakahoutanga hou.

Pērā i te maha atu o ngā ahumahi, ka riro i te kaiwhakahaere hou te kawenga mō te whakatakoto i ngā paerewa iti rawa me te whakarite kia mau tonu ēnei paerewa puta noa i te wā mahi a te miihini, tae atu ki te whakatū i tētahi waehere matatika me te whakahaere i ngā amuamu me ngā take whiu – tae atu ki ngā mana ki te whakamutu, ki te whakakore rānei i te raihana mahi a te miihini.

I te hui whakawhitiwhiti kōrero a te iwi whānui i te tau 2021, e 81% o ngā tuku kōrero e 250 i whakaae kia whai mana ngā kaihangarau i raro i ngā ture mahi.

Te tautoko a te iwi whānui mō te whakahoutanga

Pērā i te umanga tonu, te ahua nei kei te tautoko te marea i ngā whakarerekētanga.

He Ahorangi Hangarau a Maan Alkaisi i Te Whare Wānanga o Canterbury. I mate tana wahine i te hinganga o te whare CTV, ā, ko ia te kaiārahi o te Rōpū Whānau CTV. I roto i tana tuku kōrero mō te pepa kōrero a MBIE mō ngā whānau, e whakapuaki ana ia i tōna pouri mō te korenga o tetahi i whakawakia mō te hinganga o te CTV, ahakoa ngā kitenga o te rangahau i mahi te miihini i raro i tana mana, ā, kāore i tirotirohia tika.

E ai ki a Ahorangi Alkaisi e tautoko kaha ana tana rōpū i ngā tono a te MBIE. Ka whakatakotohia e te kaupapa kua whakaarohia he aratohu pakari ake mō ngā kaihangarau me te paerewa mahi hangarau teitei ake. I tāpiri atu ia mā te pūnaha hou ka whakapai ake hoki i te kawenga takohanga.

Whakamutunga

I tēnei wā, he tokomaha ngā miihini tino matatau, tino mātau hoki. Heoi, nā te kore o ngā ture ā-ture, he uaua ki te tautuhi i te hunga kāore e tutuki i ngā whakaritenga taketake mō te mahi, ā, kāore e ārai i a rātou ki te mahi. Mā ngā whakahoutanga ēnei take e aro atu. He pai anake mō te marea te whakahaere ture whai niho tūturu. E oati ana ēnei whakahoutanga ki te whakamana i te nuinga o ngā miihini tino matatau, ā, ka haumaru ake te mahi miihini mō te katoa.

Kei te tuhia te Pire i tēnei wā, ā, e matapaetia ana ka whakaurua i te mutunga o te tau 2022/tīmatanga o te tau 2023, ā, kāore pea e whakaaetia e te Kuini tae noa ki te tau 2024. E ono tau pea te roa mō te whakatūnga o te pūnaha hou ina whakaaetia.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Papa hangahanga pango me te mā
Whānui

Kāore he āhuatanga o te mahi hapa i kore ai rātou e whai wāhi atu – kua kitea e te Kōti Matua o Aotearoa he mangere te kaihanga

I roto i te keehi Wilkins v 77 Degree Builders Limited , [1] i arotakehia e te Kōti Matua tētahi kereme a ngā kaipupuri whare i kīia ai kāore i te āta mahi te kaihanga whare...
Tohu Āwhina
Whānui

He mea hanga motuhake, he mea hanga motuhake rawa rānei – te take o tētahi rarangi ADR kāore i taea te whakamana

I roto i tētahi whakataunga Ingarihi tata nei, i whakatau te Kōti Hangarau me te Hanganga he wāhanga o tētahi kirimana hanga e kī ana kia tukuna e ngā rōpū he...
Whānui

Te herenga mō ngā kereme utu i raro i ngā kirimana hangahanga

Ko te whakataunga i roto i te Hirst v Dunbar [2022] EWHC 41 (TCC) e whai whakaaro ana ki te pānga o ngā whakaritenga utu i roto i tētahi kirimana hanga, ahakoa mā roto i...