Arotake tirohanga ārai

I roto i te keehi Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited , [1] i tukuna e tētahi rōpū o ngā kaipupuri whare noho he tukanga arotake ture e rapu ana kia whakakorehia te whakataunga a te Kaunihera o Tāmaki Makaurau ki te tuku whakaaetanga rauemi i runga i te kore whakamōhiotanga mō tētahi whanaketanga i tautohetia e ngā kaipupuri kua ngaro i ētahi o rātou ō rātou tirohanga whanga.
Kaituhi(ngā): Maria Cole
Tirohanga o te Pourewa Rangi

Papamuri

He rōpū whakauru te Wynyard Quarter Residents Association Inc (te Rōpū ) kei roto i ōna mema ngā kaipupuri whare noho i roto i tētahi whare nui i te rohe o Wynyard Quarter, kei te taha o te whanga i waenganui o Tāmaki Makaurau. E mōhiotia ana te whare nui ko 30 Madden, ā, e 150 ngā whare noho kei roto.

Kua whakahaerehia e Orams Group Ltd ( Orams ) ngā pakihi moana arumoni i te rohe mai i te tau 1987. Kei te taha o te wai tōna whare i tērā taha o te tiriti mai i te whare 30 Madden. E mōhiotia ana te pakihi ko te Kāinga Moana o Orams. Kei reira ngā wāhi rokiroki maroke mō ngā poti, ngā wāhi mō te mahi tiaki me te whakahou i ngā waka tere, ā, neke atu i te 30 ngā pakihi moana motuhake kei reira.

I te Whiringa-ā-rangi 2018, i tono a Orams ki te Kaunihera o Tāmaki Makaurau mō ngā whakaaetanga hei whakawhanake anō i te whenua e whakahaerehia ana āna pakihi. I uru atu ki tēnei te whakahoro i ētahi whare o mua me te whakatū i ētahi whare hou e rima, e rua o ēnei i hiahiatia he whakaaetanga rauemi nā te mea he 'teitei rawa'. Ko te whakawātea rohe i te rohe ka whakaaetia kia eke noa ngā whare ki te 18 mita te teitei, ā, i hiahia a Orams ki te hanga i ētahi e rua ki te 25 mita te teitei. Ko tētahi o ngā whare teitei rawa ( Whare 1A ) me tū ki tērā taha tonu o te huarahi mai i 30 Madden, ā, ko te tuarua ( Whare 2 ) kei roto ko ngā whare waka nui e rua hei wāhi kawe waka me te hiki kawe 620 tana i raro iho i te huarahi.

I te tono a Orams mō ngā whakaaetanga, kāore anō kia hangaia te 30 Madden engari kua whakaaetia. Ko te kaiwhakawhanake matua o 30 Madden he kamupene e whakahaerehia ana e te Kaunihera, ko Eke Panuku Development Auckland Ltd ( Panuku ). Nā Panuku te whenua e tika ana kia hangaia te 30 Madden, ā, kua uru atu ia ki tētahi whakaaetanga me tētahi atu rōpū, a Willis Bond Ltd ( Willis Bond ) hei whakaoti i ngā mahi whakawhanake. He nui ngā whare noho 30 o Madden i hokona ki ngā kaihoko i mua i te otinga o te whare. Ko Panuku anō hoki te rangatira o te whenua e whakahaerehia ana te Orams Marine Village, ā, i uru atu hoki ia ki tētahi whakaaetanga me Orams mō te whakawhanaketanga o te papa.

Ki te whakamōhio, ki te kore rānei: te ture

E whakaratohia ana e te Ture Whakahaere Rauemi 1991 te whakaritenga mō te tono whakaaetanga whakamahere. [2] E rua ngā momo whakamōhiotanga: te tūmatanui me te iti. Kei roto i ia momo he maha ngā mahi e whakamahia ana. Ki te kore e tukuna he whakamōhiotanga tūmatanui, ka aromatawaihia te tuku whakamōhiotanga iti, ā, me whakamōhio tetahi tangata e pāngia ana i roto i tētahi o ngā mahi. Ka kiia he tangata pāngia te tangata mēnā ka whakatau te mana whakaae he iti noa iho, he nui ake rānei ngā pānga kino o te mahi ki te tangata (engari kaua e iti iho i te iti).

Whakaaetanga rauemi i tukuna i runga i te kore whakamōhiotanga

I whakatūria e te Kaunihera tētahi Komihana hei whakatau i te tono a Orams. Kua whiwhi a Orams i ngā pūrongo hei tautoko i tana tono, tae atu ki tētahi Aromatawai i ngā Pānga Taiao pūrongo (AEE pūrongo) o tana tono. I tāpirihia ki tēnei pūrongo tētahi aromatawai i whakaritea e tētahi umanga kaitohutohu taiao i whakarāpopoto i ngā pānga tirohanga pea o te Whare 2 mēnā ka hangaia kia rite ki ngā whakaritenga teitei rawa kua whakaarohia. I runga i te whakarāpopototanga a te kaitohutohu, i kī te pūrongo AEE ko te Whare 2 ka:
he iti noa iho ngā pānga kino ki te āhua o te tāone, ā, ka whai wāhi atu ki tētahi āhua hanga i roto i te Rohe o Wynyard, he mea whai wāhi pai ki te tirohanga o te Tāone, me te mea hoki e tika ana mō te whanaketanga hou o te Rohe o Wynyard.

I te tau 2019, i whakatau te Komihana kāore e hiahiatia kia whakamōhiotia te tono a Orams mō te whakaaetanga rauemi, i te marea, i te wā poto rānei, ā, i whakaaetia te tono. Nō reira, ka tīmata ngā mahi a Orams.

Te pānga o ngā mahi ki ngā rangatira o 30 Madden

I te tau 2022, i kite ngā kainoho o 30 Madden i te teitei rawa o ngā whare e whakatūria ana e Orams. Nā tēnei i ara ake ai ngā āwangawanga o te Rōpū ki a Orams i te marama o Hūrae 2022, ā, i te marama o Noema 2022, i tukuna e rātou ngā mahi mō te arotake ā-ture i te whakataunga a te Komihana e kī ana ka taea te haere tonu te tono whakaaetanga rauemi i runga i te kore whakamōhiotanga. [3]

Ko te amuamu a te Rōpū, kāore te Komihana i tautuhi, i whai whakaaro hoki ki te whakahekenga o te uara o te ataahua tirohanga ka pā ki ngā kainoho o muri mai o te whare 30 Madden nā ngā mahi hanga. I kīia i puta mārama tēnei take i roto i te pūrongo a te AEE. I hiahia kia whakakorehia te whakatau a te Komihana hei hapa, me te whakahau kia whakaarohia anō e te Kaunihera te whakatau kia whakaaetia te tono whakaaetanga rauemi kia haere tonu i runga i te kore whakamōhiotanga.

Arotake Whakawā me te mana whakatau a te Kōti ki te tuku awhina

Kāore i uaua ki te Kōti te whakatau he hapa te tukanga whakatau a te Komihana, me te kī anō i roto i ētahi atu take:
Kāore he kōrero i roto i te whakatau a te Komihana e kī ana i tahuri ia ki te ngaronga o te ataahua tirohanga ka pā ki ngā kainoho o ngā whare noho ka hangaia i te taha o te Whare 2 mā te whakaiti, te ngaro rānei o ō rātou tirohanga.
Engari kāore i mutu i reira te take. I te kitenga he hapa te tukanga whakatau, ka tahuri te Kōti ki te take me whakamahi rānei i tōna mana ki te whakakore i te whakatau. I kī te Kaiwhakawā ka tukuna e te Kōti he awhina i te nuinga o te wā mēnā kua kitea he hapa ka taea te arotake, engari ko tērā kei a ia te mana whakatau ki te whakakore i te awhina mēnā he take pai mō te mahi pera. He mea pouri mō te Rōpū, i whakaaro tana Kaitohutohu he maha ngā take e tika ai te whakamahi a te Kōti i tōna mana whakahaere kia kaua e tukuna he awhina.

Ngā pānga o te whakaroa i te wero

I tirotirohia ngā pānga o te whakaroa o te Rōpū ki te kī ka werohia te whakaaetanga, ā, i muri mai ka tukuna ngā whakaritenga. I kite te Kōti kua oti te Whare 2, ā, kua tino whakahaerehia, ā, i whakaarohia ko te whakakorenga i te whakaaetanga rauemi i tēnei wā mutunga ka pā kino ki a Orams. Nā te mea kāore e taea e te Whare 2 te whakahaere pērā i te mea i whakaarohia mēnā kāore e mau tonu tōna teitei o nāianei.

Nā tēnei i whai whakaaro ai ki te whai huatanga o te tuku awhina. Nā te mea ehara te whakaiti i te teitei o te whare i te kōwhiringa whai hua mā Orams, i whakaarohia e tana Honor:

he iti noa iho, kāore rānei he tūmanako ka hua ake i te tukanga whakamōhiotanga te tono a te Kaunihera ki a Orams kia whakaitihia te teitei o te Whare 2 ki te taumata e tutuki ana i ngā whakaritenga. Ka pātaihia e tēnei āhuatanga te whai huatanga o te tono kia whakaarohia anō e te Kaunihera te take o te whakamōhiotanga.

Kātahi ka tirohia e te Mema Pāremata te maha o ngā ope kua ngaro ō rātou whakaaro, ā, i kitea e ia he iti noa iho pea te maha o aua ope.

Kei te mahara koe ki a Willis Bond rāua ko Panuku?

I kitea kua whiriwhiria kētia e Willis Bond ngā whakaaetanga whai hua mō ngā tāngata katoa o Orams me Panuku i te tau 2019, ā, i mōhiotia ēnei whiriwhiringa e te Rōpū. I te tau 2018, i āwangawanga a Willis Bond kei pāngia ngā tirohanga mai i ngā whare i roto i te rohe o 30 Madden e te whanaketanga kua whakaarohia e Orams. I tukuna he whakahē ki ngā rohe teitei kua whakaarohia mō te Whare 1A me te Whare 2.

Nā Panuku i whakahaere ngā whiriwhiringa i waenganui i a Orams rāua ko Willis Bond mō te teitei o ēnei whare, ā, ko te mutunga iho, ka tangohia e Willis Bond tana whakahē ki te teitei kua whakaritea mō te Whare 2 hei utu mō te whakaae a Orams ki te whakaiti i te teitei o te Whare 1A ki te 18 mita. I tāpirihia hoki e Panuku he mea whakareka, ā, i whakaae ki te whakaaro anō i te uara ka whakatakotoria ki te whenua ka riro i a Willis Bond mō te wāhanga tuarua o tōna whanaketanga i 30 Madden .

Whakamutunga

Ko te mutunga iho, i kitea e te Kōti kua pau te wā mō tētahi wero ki te tihi o te Whare 2, ā, ko ngā kainoho o 30 Madden e herea ana e ngā whakataunga a tō rātou mua i te taitara i te tau 2019. He mea nui te whai i ō rātou tika i te wā tika me te mōhio, engari kāore i te wātea i tēnei wā, nō reira kāore he awhina.

Ngā Tohutoro

[1] Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited [2023] NZHC 1938.

[2] Ngā Wāhanga 95 ki te 95G.

[3] Te Rōpū Kainoho o Wynyard Quarter , i runga ake i te n 1.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

Te aromatawai i ngā moni e utua ana i te korenga o tētahi kirimana: Electrix Limited v The Fletcher Construction Company Limited [2020] NZHC 918

I roto i tētahi whakataunga i tukuna i te 6 o Mei 2020, i whakahaua e te Kōti Matua a The Fletcher Construction Company Limited kia utua e ia tana kamupene kirimana iti a Electrix Limited mō...
Whānui

Kei te haere mai te whakahoutanga ki te whakahaere i ngā miihini

I whakahaerehia e te Manatū Pakihi, Auahatanga me te Mahi (MBIE) tētahi hui kōrero i te tau 2021 hei whakahou i te pūnaha ture mō ngā kaihangarau. Mā ngā whakahoutanga ka nekehia...
Whānui

Ngā mea e hiahiatia ana e ngā kaiwhakawā mai i ngā taunakitanga tohunga mō ngā kereme mō te whakaroa hangahanga

Ka taea e ngā taunakitanga a ngā tohunga mō ngā kereme whakaroa hangahanga te whakaū, te whakakore rānei i te take a tētahi rōpū. He nui ngā moni e pau ana ki te whakaputa i taua take. Heoi, he maha ngā pūrongo e tūtakihia ana e ngā kaiwhakawā...