Ngā herenga o te kaupapa whakatau ātete huarere i whakamatautauria i roto i te keehi a te Kōti Matua

I roto i te keehi Body Corporate 355492 v Te Tumu Whakahaere o te Manatū Pakihi, Auahatanga, me te Mahi [2024] NZHC 1422, te Poari Whakahaere o te whanaketanga Oak Shores i 327 Frankton Road, Queenstown, i tono kia whakawāteahia ngā whakataunga a te Tumu Whakahaere o te Manatū Pakihi, Auahatanga me te Mahi ( MBIE ) i raro i te Weathertight Homes Resolution Services Act 2006 (WHRS Act), i hangaia hei āwhina i ngā kaipupuri whare e pāngia ana e ngā take ārai huarere e puta mai ana i te raruraru o ngā whare turuturu. Ina koa, i whai a MBIE ki te whakakore i ngā wāhanga o te whanaketanga Oak Shores kāore i tutuki i ngā paearu whakauru mō te pūtea whakatikatika ahakoa i whakaurua pea ki roto i te pūrongo a te kaiuru motuhake taketake.
Kaituhi: Sam Dorne
Ngā pata ua e neke haere ana

Ture WHRS

I mua i te tirohanga ki ngā āhuatanga motuhake o te keehi, he mea tika kia tirohia tuatahitia te Ture WHRS.

I whakatūria te Ture WHRS ki Aotearoa hei āwhina i te whakatika i ngā take e pā ana ki te raruraru o ngā whare turuturu wai rongonui i pā ki te maha o ngā whare anga rakau i hangaia mai i te tau 1988 ki te 2004.

Kei roto i te Ture WHRS he tikanga mō ngā kaipupuri whare ki te whiwhi āwhina pūtea hei whakatika i ngā hapa ātete huarere. Kei roto i tēnei ko te whakatau i te tika mō te pūtea me te whānuitanga o te tautoko pūtea e wātea ana. Ka whakaratohia he tukanga hanganga mō te whakatau i ngā tautohe i waenga i ngā kaipupuri whare me ngā kaihanga whare, i ētahi atu rōpū kawenga rānei e pā ana ki ngā hapa ātete huarere, ā, ka whakatūhia he tūranga matua mō MBIE ki te tirotiro me te whakahaere i te tukanga whakatau.

Ko te Ture WHRS e kapi ana i ngā whare noho anake. Ina koa, e pā ana ki:

  • Ngā Whare Noho: Kei roto i ēnei ko ngā whare takitahi me ngā whare maha-whare, pērā i ngā whare taone me ngā whare noho, he ātete ki te huarere.
  • Ngā Whare Maha-Wāhanga: Ka pā anō hoki te Ture ki ngā whare taitara wāhanga (hei tauira, ngā whare noho, ngā whanaketanga āhua whare noho rānei), mena ka tutuki i a rātou ētahi paearu i raro i te Ture.
Te Whanga o Queenstown
Piriti rakau o Queenstown

Te whanaketanga o Ōki Takutai

E whitu ngā wāhanga matua me ngā wāhi whānui o te whanaketanga o Oak Shores.

I te 20 o Mei 2013, i tono te Rōpū Whakahaere mō Oak Shores i tētahi pūrongo a te kaiaromatawai mai i a MBIE nā runga i ngā take ārai-huarere. I roto i te pūrongo kua oti, i whakaotia i te 20 o Hānuere 2015, i tohuhia te tika mō te kereme mō te whanaketanga katoa. Heoi, i te 18 o Pēpuere 2015, i whakaarahia e MBIE ngā āwangawanga mō te tika o ngā wāhanga o te poraka 4 hei whare noho nā te mea ko te whakaaetanga hanga taketake he whare arumoni. I te mutunga, i tuhi a MBIE i tētahi reta e whakatau ana i te tika, ā, i kore ai e whakaurua te poraka 4.

I tautohe te Rōpū Whakahaere i te whakataunga o Pēpuere 2016 me whakauru ngā poraka e whā o Oak Shores ki roto i te kereme whai mana. Ko te utu whakatikatika mō te poraka 4 e matapaetia ana he $12 miriona, me te āwhina pūtea pea e kapi ana i te 25% o tēnei moni.

I tonoa te Kōti Matua kia whakatau mēnā i hipokina e te whakataunga whakauru te whare katoa, ngā poraka 1, 2, me te 3 anake rānei, ā, mēnā hoki i tika i raro i te ture te tango i te poraka 4.

Te whakataunga a te Kōti Matua

He maha ngā take rerekē i whakaarahia ki te Kōti Matua hei whakahē i te whakataunga. Heoi, nā te tautohe tuatahi i whakatakotohia i ārahi te Kōti Matua ki te tirotiro i ngā mana o MBIE ki te aromatawai i ngā paearu whakauru me te pehea i whakatauritea ai ēnei ki te pūrongo a te kaiaromatawai.

I tautohe te Rōpū Whakahaere ko te wāhanga anake e tika ana mō te puka whakauru ko te whakatau whakamutunga e kī ana he tika te kereme, ā, e pā ana ki te raruraru whānui .

Heoi, i whakakorea e te Kōti Matua tēnei tautohe. I whakatauhia e ngā whakaritenga ture he here i te tūranga o te kaiwhakatau, ā, kāore e taea te whakakore i ngā paearu whare noho. I whakatau te Kōti Matua: [1]

Kāore au e whakaae ana he tika te whakamārama i tēnei tuhinga, inā koa ka whakaarohia te horopaki ture. E ai ki te ture, ehara i te mea kei roto i te mana o te kaiwhakatau te whakakore i ngā whakaritenga "whare noho", ā, ehara tēnei i te mea i whakaarohia e ia. Kāore he mana whānui ki te whakahaere i ngā wāhanga matua kāore i te noho hei whare noho. Hei tauira, ko te taumata 3 he wharekai, he wāhi manaaki manuhiri, he wāhi noho mō ngā kaimahi, me ētahi atu wāhi huihuinga. Kāore te whakatakotoranga o taua taumata e rite ana ki te whakamahinga o taua wāhanga matua mō te whakamahinga matua o tētahi whare noho tūmataiti.

Karara Moana i Queenstown

I kī te Kōti ko te ariā o te whare katoa e pā ana ki ngā kaupapa here a te rōpū mahi, ina kereme ana te māngai mō ngā kaipupuri katoa o tētahi whare. Hei whakahaere i tētahi kereme, me whiwhi te māngai i te whakaaetanga mai i te 75% neke atu rānei o ngā kaipupuri whare noho. Ko te whāinga o tēnei whakaritenga he ārai i ngā kaipupuri takitahi kei tango i ngā tūranga taupatupatu, i ngā "kāore e whakaaetia".

I tēnei take, i kiia te kereme he tika mō te whare katoa, engari i herea noa ki ngā wāhanga e tika ana hei whare noho. Ko te whakatau ko te kereme he "tika" e pā ana ki te whānuitanga i whakamāramahia i roto i ngā tuhinga, ā, kāore e pā ki ngā wāhanga katoa i roto i te whare.

Whakamutunga

Hei whakarāpopototanga, ko te tika o ngā kereme e pā ana ki ngā whare turuturu e tino whakahaerehia ana e te whakaritenga me noho ngā wāhanga e pā ana ki tēnei he whare noho. Ahakoa ngā kereme whānui mō te tika o tētahi whare nui katoa, he mārama te whakamāramatanga ture mō tētahi whare noho, ā, kāore e taea te whakakore. Me hangai te aromatawai a te kaiwhakahaere ratonga hangarau me te whakataunga whakamutunga mō te tika ki ēnei whakaritenga, me te whakarite kia tika te whakarōpūtanga o ngā kereme, ā, kia kore ai ngā wāhanga kāore e noho ana e nohoia e whakaurua ki te tika.

Ngā Tohutoro

[1] I [77].

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

Kāore te Kōti Matua o WA i kite i tētahi raihana huna hei whakamahi i te mahere hoahoa whare

I tētahi kēhi o Ahitereiria tata nei, kāore te Kōti Matua o WA i pai ki te whakamārama i tētahi kirimana i waenganui i tētahi kaihanga whare me tā rātou kiritaki kia kīia ai...
Whare Pukapuka
Whānui , Whakatau

Ehara i te mahi rautaki mohio te tono i tētahi kaiwhakatau kia titiro puku: kāore e taea te whakamana i te whakatau a te kaiwhakawa nā te takahi i ngā ture kore whakahāwea.

I kawea e tētahi rōpū ( AZ ) ngā mahi ki te Kōti Hangarau me te Hanga o Ingarangi me Wales ( Kōti ) hei whakamana i te whakataunga a te kaiwhakawā ki te...
Mahere Hoahoa
Whānui

Ngā tāpiritanga kirimana: kaua e arohia, ko koe anake te tūponotanga

Nō nā tata nei, i whakawāteatia tētahi kaimahi kirimana iti i te UK i te mōrearea kino o te whenua, ahakoa ngā whakatikatika kirimana i whai kia tohaina taua mōrearea ki te...