Kei raro nei he whakarāpopototanga o ngā wā whakatau tata i roto i ngā rā mahi.
Kia Mōhio Mai: Ahakoa kāore he rohe wā pumau mō ētahi o ngā mahi tukanga, i roto i te mahi, he maha ngā mahi ka oti wawe atu i te mea i whakaarohia, i whakaaetia rānei i raro i te Ture.
HEI TAUIRA – ka taea te mahi i ngā taahiraa 1 – 4 i roto i ngā haora 48 – (e rua ngā rā mahi, kaua e 12):
arā, ka taea e te kaitono te tuku i te pānui whakatau i te rā tuatahi, ā, ka tono ki te Taraipiunara Taupatupatu Hanga Whare kia whakaingoatia he kaiwhakawa i te rā mahi tuarua i muri i te tukunga o te pānui, ka taea e te kaiwhakawa te whakaū tonu i tōna hiahia me tōna kaha ki te mahi hei kaiwhakawa me te tuku i te pānui whakaae ki ngā rōpū, ā, ka taea e te kaitono te tuku tonu i tana kereme whakatau, i te rā mahi tuarua i muri i te tukunga o te pānui whakatau.
Ngā rā mahi | Ngā wā whakatau |
|---|---|
Rā 0 | Ka tukuna e te kaitono he pānui whakatau ki te kaiwhakautu. |
Rā 5 | Ka taea e ngā rōpū te whakaae ki tētahi kaiwhakawā i roto i ngā rā mahi e rima (ki te kore ngā rōpū e whakaae ki te whakaroa i tēnei wā), ka taea rānei e te kaitono te tono ki te Taraipiunara Tautohe Hanga Whare , hei mana whakaingoa whai mana, kia whakaingoatia he kaiwhakawā i waenga i ngā rā e rua me te rima i muri i te tukunga o te pānui whakatau. |
Rā 7 | Me whakaatu e te tangata e tonoa ana kia mahi hei kaiwhakawā, i roto i ngā rā mahi e rua mai i te tukunga o te tono, mēnā e pai ana ia ki te mahi i taua tūranga. Kātahi ka tukuna e BDT he pānui whakaae ki te mahi ki ngā rōpū. Kia tae mai te utu, ka tukuna e BDT he pānui whakaae ki te whakatūnga.
|
Rā 12 | Me tuku e te kaitono te tautohe mā te tuhituhi ki te kaiwhakawā i roto i ngā rā mahi e rima mai i te pānui whakaae (te Kereme). |
Rā 17 | Ka taea e te kaiwhakautu te tuku whakautu tuhituhi ki te kaiwhakawa i roto i ngā rā mahi e rima i muri i te whiwhinga o te kereme whakatau (ki te kore e whakaae ngā rōpū, ki te kore rānei e tukuna he wā anō e te kaiwhakawa) me ngā rōpū katoa ki te whakatau i mua tonu atu, i muri rānei i te tukunga atu ki te kaiwhakawa – (kāore he rohe wā mō te wā e whakaaetia ana e ngā rōpū, e whakaaetia rānei e te kaiwhakawa). |
Rā 22 | Ka taea e te kaitono te tuku whakautu ki te kaiwhakautu i roto i ngā rā mahi e rima i muri i te whiwhinga o te whakautu, me te tuku whakautu ki ngā rōpū katoa o te whakataunga i mua tonu atu, i muri rānei i te tukunga o te whakautu ki te kaiwhakautu. |
Rā 24 | Ka taea e te kaiwhakautu te tono, ā, ka tukuna ki a ia te mana ki te tuku whakautu mō te whakautu a te kaitono i roto i ngā rā mahi e rua i muri i te whiwhinga o te whakautu. |
Rā 37 | Ka whakatauhia e te kaiwhakawā te tautohe i roto i ngā rā mahi 20 i muri i te whiwhinga o te whakautu ki te kereme whakatau (engari ka taea te whakaroa ki te 30 rā mahi – neke atu rānei me te whakaae a ngā rōpū). |
Rā 39 |
Ka āhei ngā rōpū ki te whakamōhio i te kaiwhakawā mō ngā whakatikatika e hiahiatia ana i roto i te whakataunga, ā, me mahi e te kaiwhakawā aua whakatikatika i roto i ngā rā mahi e rua i muri i te tukunga o te whakataunga. Kia mōhio koe, kāore e taea te whakatika i tētahi whakataunga i muri i te paunga o aua rā mahi e rua. |
Rā 40 | Mena kāore te rōpū angitu i utu i te katoa o te moni kua whakatauhia hei utu māna, ka taea e te rōpū angitu (mēnā ko rātou te rōpū e mahi ana i te mahi hanga) te tuku pānui e whakaatu ana i te hiahia ki te whakamutu i te mahi, te tono ki te Kōti Takiwā kia whakamanahia te whakataunga mā te whakaurunga hei whakataunga, te tono kia whakahokia mai te moni kāore anō kia utua mai i te rōpū e tika ana kia utua hei nama e tika ana, me te tono mō tētahi ota utu ki te papa hanga mena ka whakaaetia e te kaiwhakawa. |
Rā 44 | Ka taea e te kaitono te whakamutu i te mahi mēnā kāore te kaiwhakautu i whai i te whakataunga a te kaiwhakawa i muri i ngā rā mahi e rima. |