Ngā tāpiritanga kirimana: kaua e arohia, ko koe anake te tūponotanga

Nō nā tata nei, i whakawāteatia tētahi kaimahi kirimana iti i te UK i te mōrearea kino o ngā āhuatanga whenua, ahakoa ngā whakatikatika kirimana i whai kia tohaina taua mōrearea ki te kaimahi kirimana iti - ā, i whakawhirinaki katoa ki te tātari i ngā tāpiritanga ki te kirimana. He mahi mōrearea te tāpiri tuhinga ki tētahi kirimana me te kore e whai whakaaro ki te āhua o tā rātou mahi me ngā tikanga matua o te kirimana. Ahakoa he mea nui kia whakaurua aua tuhinga (he maha ngā wā he hangarau) ki roto i tētahi kirimana, me tahuri ngā rōpū ki ō rātou whakaaro ki ngā rerekētanga, ngā koretake, ngā māramatanga rānei e tika ana kia arohia i mua i te hainatanga o te kirimana.
Kaituhi(ngā): Sarah Sinclair rāua ko Katie Keir
Mahere Hoahoa

Ngā mahi noa i roto i te umanga

He mea noa mō ngā kirimana te whakauru i ngā āpitihanga kei roto ngā tuhinga tāpiri e pā ana ki te kirimana. I roto i te umanga hanga, ko ngā Whakatakotoranga a P&G, ngā Mahere Pae, ngā Tuhi me ngā Whakatakotoranga me ngā mōhiohio hanganga Utu Kirimana ka tāpirihia katoatia ki te kirimana. Ko ngā mea katoa e tāpirihia ana ki te kirimana ka noho hei wāhanga o te kirimana, nō reira he herenga ture ki ngā rōpū.

Hei whakaiti i te mōrearea o ngā rerekētanga i roto i te kirimana, ka whakaurua e ngā rōpū he 'rārangi matua' e whakatakoto ana i te raupapa o ngā tuhinga kirimana. Ko ngā tikanga matua o te kirimana ka matua, ā, ko ngā tuhinga hangarau he iti ake te matua. Ka whakawhirinaki ngā rōpū ki tētahi rārangi matua hei whakatau i ngā rerekētanga pea i waenga i ngā mōhiohio me ngā kupu e kitea ana i roto i ngā wāhanga rerekē o te kirimana. Ko te raruraru, kāore he rārangi matua e whai wāhi mai mena kāore he rerekētanga i kitea i te tuatahi.

Kua whakaaturia tata nei te mōrearea o ngā tuhinga tāpiri i roto i ngā kēhi i te UK, hei whakamahara i te hiahia kia tupato ngā rōpū kirimana i Aotearoa.

Ngā kōrero a te ture

Kua tino whakatakotoria ngā mātāpono o te whakamārama kirimana i roto i ngā take i ngā tau kua pahure ake nei. Me pānui ngā kupu o te kirimana i runga i te tirohanga o te kirimana katoa me tōna kaupapa whānui. I te whakamārama i tētahi kirimana, ka whai te kooti ki te whakatau i te hiahia o ngā rōpū mā te tohutoro ki "te tikanga o te reo o te kirimana e whakamahia ana e te tangata whai whakaaro nui, he mōhiotanga whānui kua wātea ki ngā rōpū... i roto i tō rātou horopaki tuhinga me ngā horopaki pono". [1]

I te whakamahinga o tēnei mātāpono ture, kua whakaatuhia e ngā kōti he puhoi ki te kimi i ngā rerekētanga i roto i tētahi kirimana. Nō reira, ahakoa he āwhina ngā rarangi matua ki te whakarato i ētahi 'tikanga' i roto i tētahi kirimana, he onge te whakamahinga e ngā kōti. Ko te tikanga o tēnei ka whai mana tētahi kupu, tētahi tikanga rānei i roto i tētahi tuhinga kirimana 'tino matua', mena kāore te tikanga i te rerekē ki ngā tuhinga tino matua.

Ngā ture kēhi o te UK i ngā wā tata nei

I roto i te keehi Clancy Docwra Limited v E.ON Energy Solutions Limited [2] ( CDL v E.ON ), he kaimahi kirimana iti a CDL e mahi ana i ngā mahi keri i Central London. I kitea e rātou he maha ngā taonga o raro whenua e hiahia ana ki ētahi atu rauemi me ngā mahi hei keri. I puta he tautohe mō te hunga e pāngia ana e te mōrearea o ngā āhuatanga kino o te whenua kāore i kitea i mua. I tautohe a CDL ko te aro atu ki ngā āhuatanga kino o te whenua kei waho i te whānuitanga o ngā mahi kirimana iti, e ai ki ngā tuhinga whakamārama tono i tāpirihia ki te kirimana iti.

I tautohe a E.ON, te kaiwhakatū, ko te mōrearea o ngā āhuatanga kino o te whenua kāore i te tūmanakohia kei a CDL i raro i ngā tikanga matua o te kirimana, i whakanuia i roto i te wāhanga matua o ngā tuhinga o te kirimana iti.

I tautoko te Kōti i a CDL, me te whakatau ko E.ON te kawenga mō ngā āhuatanga o te whenua kāore i kitea i mua. Kāore te rarangi matua i whai wāhi mai i te mea i kitea e te Kōti kāore he rerekētanga i roto i te kirimana. Engari, i whakatau te Kōti kāore te mahi hanga e pā ana ki te wāhanga o te whānuitanga o te mahi kirimana iti nā te mea kua whakakorea rawatia tēnei mahi i roto i ngā tuhinga tāpiri. Ko te tikanga o tēnei kāore e taea e E.ON te whakawhirinaki ki te rarangi whānui mō te tohatoha mōrearea i roto i ngā tikanga matua o te kirimana, kāore hoki e taea te whakawhirinaki ki te rarangi matua hei karo i te kawenga mō te mōrearea me te utu o tēnei mahi tāpiri.

E whakaatu ana te keehi CDL v E.ON me pēhea e kore ai e taea e ngā rōpū te whakawhirinaki ki tētahi rarangi matua hei whakatika i ngā take whakamaoritanga kirimana mena kāore he rerekētanga i kitea. E whakaatu ana te keehi i te hiranga o te whai wā o ngā rōpū ki te mārama ki te tikanga tuturu o ngā tuhinga e tāpirihia ana ki te kirimana me te pānga ki te whakamahinga o ngā tikanga matua o te kirimana. I tēnei keehi, i kitea ko ngā whakamārama i muri i te tuku tono ka waiho te mōrearea o ngā āhuatanga whenua kino ki a E.ON, ahakoa koinei te mea i whakaarohia e E.ON mō tōna tūranga arumoni.

I mua ake nei, ko tētahi kēhi o te UK, ko MT Højgaard AS v E.ON Climate and Renewables [3] ( MT Højgaard v E.ON ) e mōhiotia whānuitia ana mō tana matapakinga mō te pai o te kaupapa; heoi anō, e whakaatu ana hoki i te mōrearea o te tāpiri tuhinga hangarau ki tētahi kirimana me te kore e tino mōhio ki ngā ihirangi. Anō, i roto i tēnei kēhi, kāore i kitea e te Kōti he rerekētanga i roto i ngā tuhinga kirimana, ā, i whakamahia e ia ngā mātāpono taketake o te whakamaoritanga kirimana hei whakatau i te pānga o te kirimana.

I konei, i tautohe te kaiwhakatū, a MT Højgaard , kia kaua e whakamanahia tētahi herenga taumaha e kī ana me hoahoa ngā turanga o tētahi pāmu hau moana kia 20 tau te roa o te oranga, nā te mea i kitea noa iho i roto i tētahi wāhanga pōuriuri o ngā tuhinga tono, ā, kāore i whakamāramahia i roto i ngā tikanga kirimana matua mō te kounga hoahoa. Heoi, i kitea e te Kōti nā te mea i roto i ngā tikanga o te kirimana ngā tuhinga tono, me kī i whakaaro ngā rōpū kia whakamanahia te herenga taumaha e te kirimana.

I ngana anō te kaiwhakatū ki te tautohe nā te mea i whakatakotohia e ngā tikanga matua o te kirimana ētahi atu herenga e pā ana ki te kounga o te hoahoa me te hanganga, kāore pea i te whakaaro ngā rōpū kia whai mana tētahi herenga kaha ake i roto i ngā tuhinga tuku tono. I whakakahoretia tēnei tautohe nā te mea ka kore e whai tikanga te whakaritenga kia hangaia ngā turanga kia 20 tau te roa o te oranga. Nō reira, kua takahia e te kaiwhakatū te kirimana, ā, ko ia te kawenga mō te utu o te whakatika i ngā turanga.

Te Whanga o Tāmaki Makaurau

Tono ki Aotearoa

Kāore he ture take ōrite o Aotearoa hei whakamahi. Heoi, i te mea he rite tonu te huarahi e whaihia ana e ngā kōti o Aotearoa ki te whakamārama kirimana me ngā kōti o te UK, he tino tūponotanga ka pā ngā take o te UK kua whakahuatia ake nei ki tētahi take ōrite e whakarongohia ana i Aotearoa. He tino tūpono pea ka puta he take pēnei i Aotearoa, inā koa i roto i te horopaki hangahanga e tāpirihia ana ngā tuhinga hangarau maha ki ngā kirimana hangahanga. Nō reira, he mea tika kia tūpato ngā rōpū kirimana i Aotearoa ki ngā take i whakaarahia i roto i ngā take o te UK kia kore ai e pāngia e ngā mahanga ōrite i te wā e whakamahi ana i ā rātou ake kirimana.

Ngā akoranga hei ako

Kāore ngā take e rua o runga ake nei e whakatakoto ture hou, e huri rānei i te whakamāramatanga o te kirimana. Heoi, he whakamahara nui ēnei ahakoa ngā kupu kua tanumia hohonu ki roto i ngā tuhinga hangarau he wāhanga o te kirimana, nō reira he mea nui kia mōhiotia, kia mārama hoki ki aua kupu. E kore ngā rarangi matua e whakaora i te wā e kore ai ngā kupu kirimana e taupatupatu. Hei karo i ngā pānga pūtea nui pea, me whakahaere e ngā rōpū he tirotiro whānui mō te kirimana hei tautuhi i ngā taupatupatu, ngā āwangawanga, ngā māramatanga rānei, i waenga i ngā rarangi, inā koa ka tāpirihia ngā tuhinga hangarau i whakaritea e te kaiwhakarite, e te kaiwhakarite iti rānei.

Ngā Tohutoro

[1] Arnold v Britton [2015] UKSC 36, nā Lord Neuberger i [15].

[2] Clancy Docwra Limited v E.ON Energy Solutions Limited [2018] EWHC 3124 (TCC).

[3] MT Højgaard AS v E.ON Climate and Renewables UK Robin Rigg East Ltd me tētahi atu [2018] 2 All ER 22.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui

He mate nui mō te kaiinihua i roto i te pakanga ture me te Kaunihera o Napier mō te rarangi whare turuturu

I roto i tētahi kēhi tata nei, i whakatau te Kōti Matua o Aotearoa kia tautokona te Kaunihera o te Tāone o Napier i roto i tētahi kereme inihua e pā ana ki te hanga whare...
Whānui

Ngā whakaroa wā i roto i ngā kirimana hanga

I roto i tētahi kereme mō te whakaroa i te wā, he mea nui te whakaaro ki te whakapae mō te whakaroa i te aromatawai i te mea "tika me te whaitake".

I roto i te CAJ...
Whānui

Me nui atu ngā "taunakitanga" a ngā tohunga i ngā kōrero pākiki noa iho kia toa ai te rā

He tino ārai pea ngā take turuturu i roto i tētahi whare. He whakataunga tata nei nā te Taraipiunara Ā-Iwi me te Whakahaere o Kuini Irirangi (te Taraipiunara)...