Ka whakamutua e te kaihanga te kirimana me te "aroha mai e hoa...kei te tino piki haere ngā utu"

I te mea kei roto te umanga hanga i te korenga o ngā kaimahi me ngā taonga, me te pikinga o ngā utu, he whakamaharatanga tika tēnei a te whakataunga a te Kōti o Kuīnirani mō ngā mātāpono kua whakatūria mō te whakakorenga kirimana. He whakatūpato te whakataunga ki ngā rōpū kia whakaaroaro rua i mua i te whakamutu i tētahi kirimana hanga, i te tohu rānei i te hiahia kia kaua e haere tonu.

I roto i te keehi Addinos Pty Ltd v OJ Pippin Homes Pty Ltd [2022] QDC 205 , i kitea e te Kōti Takiwā o Queensland (te Kōti) ehara i te mea ture te whakatau a te kaihanga ki te whakamutu i tētahi kirimana hanga whare nā te mea kāore i taea e ia te utu i ngā utu ahumahi e piki haere ana. I kitea e rātou ko te kaihanga te kawenga mō te whakakorenga, ā, i whakahaua kia utua e ia tata ki te $160,000 ki te kaiwhakawhanake mō te mate me te kino, tata ki te $35,000 mō te huamoni me ngā utu anō hoki.
Kaituhi: Kate Holland

Ngā meka

I tukuna e tētahi kaiwhakawhanake whenua o Addinos Pty Ltd ( Addinos ) he kirimana ki tētahi kamupene hanga whare, arā, ko OJ Pippin Homes Pty Ltd ( Pippin ) hei whakahaere i ngā mahi tae atu ki te whakahoro, te keri me te hanganga o ētahi whare tāone (ngā Mahi ). I raro i te kirimana hanga, i hiahiatia a Pippin kia tīmata te Mahi i roto i ngā rā 14 i muri i te whiwhinga o ngā whakaaetanga katoa e tika ana.

I roa te whakaroa o te kaupapa, tae atu ki ngā whakaroa i te whiwhinga i ngā whakaaetanga e hiahiatia ana mō te whakahoro, te putorino me te hanga whare. I muri i ngā marama 12, ko te whakahoro anake i oti. I taua wā, kua tino piki ake ngā utu o te umanga hanga, ā, kua ngaro i a Pippin ētahi o āna kaimahi.

I te raru o te kaha me te pikinga o ngā utu o te kaupapa, ka ī-mēra a Pippin i tētahi reta ki a Addinos e kī ana kei te whakamutua e rātou te kirimana hanga o ngā whare taone. I whakamārama a Pippin nā te pikinga o ngā utu tēnei: ​​ka whakamutua e Pippin … te kirimana hanga… kua tino piki ake ngā utu hanga mai i te wā i whakaritea ai te utu mō te kaupapa, tata ki te 12 marama ki muri…

I muri mai i te reta, ka tukuna e te kaiwhakahaere o Pippin, e Mr Hastie, he karere kuputuhi ki te kaiwhakahaere whanaketanga o Addinos, e mea ana: Kāore e taea e au te hanga i tēnei kaupapa, aroha mai e hoa … kua ngaro i a mātou ētahi o ā mātou kaiwhakahaere tino mātau … kei te tino piki haere ā mātou utu mō ēnei [kaupapa iti] … Aroha mai mō te raruraru i pā mai …     

I whakautu a Addinos me te whakaae kua mutu te kirimana i te rā i tukuna ai te reta a Pippin, me te whakapae mō te whakakorenga hē: Ko tāu reta, me tāu whakarēreatanga o te kirimana me ngā mahi, he whakakorenga hē me te takahi i te kirimana… i mutu te kirimana nā tāu reta…

I utua e Addinos tētahi atu kaihanga hei whakaoti i ngā Mahi, ā, i whakaara i tētahi kereme ki a Pippin mō ngā mate me ngā kino, tae atu ki te pikinga o ngā utu hanga, te huamoni e pā ana ki te whakaroa me ngā utu peeke.

I a ia e tiaki ana i te kereme, i kī a Pippin kāore i angitu ko Addinos te tuatahi i whakakahore i te kirimana, nā te mea kāore i whiwhi i ngā whakaaetanga e hiahiatia ana i te wā tika. 

Te whakatau

Kāore i uaua ki te Kōti te whakatau he whakakorenga te whakakorenga o Pippin.

I kite te Kōti kāore he rarangi i roto i te kirimana hanga e whakamana ana i te whakamutu i runga i te pikinga o ngā utu. Nō reira, i whakataua e te Kōti ehara te pūtake mō te whakamutu i roto i te reta a Pippin me te tuhinga a Mr Hastie i te pūtake ture hei whakamutu.

I whakaū anō te Kōti i ngā mātāpono kua whakatūria mō te whakakorenga – ka puta tēnei ina whakaatu tetahi rōpū i te hiahia kia kaua e herea e te kirimana. I whakaatu te reta me te tuhinga a Pippin i te hiahia o Pippin kia kaua e herea e te Kirimana, nō reira kua whakakorea e Pippin te kirimana.

I whakakorea e te Kōti te tautohe a Pippin i mea ko Addinos te tuatahi ki te whakakore nā te korenga i whiwhi i ngā whakaaetanga. I kite te Kōti ko te reta me te karere kuputuhi a Pippin i kōrero noa mō ngā take a Pippin ake – te pikinga o ngā utu hanga me te hurihanga o ngā kaimahi. Mā te whakamahi i te whakamātautau kotahi mō te whakakorenga i mua, kāore i kitea e te Kōti he taunakitanga e whakaatu ana kua whakaatu a Addinos i te hiahia kia kaua e herea e te Kirimana, nō reira kāore a Addinos i whakakore.

Whakamutunga

Kei te whakararu tonu te COVID, te korenga o ngā kaimahi me ngā take mekameka tuku i te rāngai hanga, ā, kei te piki haere tonu ngā utu. Me karo ngā rōpū e raru ana i raro i ēnei pēhanga i te whakatau wawe ki te whakamutu, ki te whakaatu rānei i te hiahia kia kaua e oti tētahi kaupapa – mā te mahi pēnā ka waiho pea rātou kia tuwhera ki ngā kereme whakakore utu nui.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whare noho o Cliffside
Whānui

Ko te "tikanga ine" ki te aroha ki tō hoa tata: te whakararuraru tūmataiti me ngā tūponotanga ā-taiao

Kua hinga tētahi kaipupuri whenua o Ōtautahi, kei te take o tētahi whenua pari koretake i hokona e te Karauna whai muri i ngā rū whenua o Canterbury, i tana...
Whānui

Te mōrearea ahi – kei te wera haere ngā tautohe mō te whakakikorua hapa

I Ingarangi me Wales, ko te Kōti Hangarau me te Hanga i roto i te keehi Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 Hōngongoi...