Te whakapūmautanga o te utu mō te whakatau i ngā tautohe mō te hanga whare me te hanganga: Te whakawhānui atu ki te Kaupapa Kereme Uara Iti a te BDT Adjudication

Ko tētahi o ngā arai matua ki te whakatau tautohe ko te utu: kāore tetahi e hiahia ana ki te mōrearea ki te whakapau moni nui atu i te moni i whakahokia mai e rātou. I te mea kei te piki haere tonu te pikinga o ngā utu me ngā utu hanga, kei te whakawhānui ake a BDT i tana Kaupapa Kereme Uara Iti (LVC) mō te whakatau kia mōhio ai ka taea e te tini o te tangata te whakamahi i tēnei tukanga whai hua me te whai kiko.
Kaituhi(ngā): Belinda Green

He aha te take o te whakatau?

Ko te whakataunga ture i raro i te Ture Kirimana Hanga te tukanga whakatau tautohe e whakamahia whānuitia ana i Aotearoa hei whakatau i ngā tautohe hanga whare me te hanganga.

He maha ngā take i tino rongonui ai te whakatau. He tere: ko te nuinga o ngā tautohe ka whakatauhia i roto i te iti iho i te ono wiki mai i te tīmatanga o te tukanga. He whai hua anō hoki: kāore koe e hiahia ki te tiki whakaaetanga mai i te taha kē ki te tīmata i te whakatau, ā, kua whakaritea te tukanga e te Ture, nō reira kāore koe e moumou taima ki te whakaae ki ngā ture ka pā. Ko te taahiraa tuatahi o te tukanga ko te tuku Pānui Whakatau ki te taha kē ki te tautohe. (He mea nui kia mārama te whakatakoto a te Pānui Whakatau i te tautohe – tirohia tā mātou tauira Pānui Whakatau mō ētahi atu aratohu).

He whai hua hoki te whakatau whakawa: ahakoa he iti pea ngā utu tuatahi mō te tuku i tētahi whakawakanga kōti, he maha ngā momo utu me ngā utu e pā ana ki te tukanga. Kāore he utu huna i roto i tētahi whakatau whakawa. Kaua hoki e wareware ki ngā utu ture: he tino uaua ki te whakahaere i tētahi keehi kōti me te kore he āwhina ture, engari ka taea te whakahaere i te whakatau e ngā rōpū tonu mēnā e hiahia ana rātou, me te tiki tohutohu ture anake ina hiahiatia i ngā wā motuhake i te huarahi ki te whakatau. Heoi anō, ka tūtohu tonu mātou kia tiki tohutohu ture motuhake mēnā kāore koe i te tino mōhio mō ō tika ture, ō herenga rānei, me te hiahia noa rānei i tētahi āwhina i te huarahi. Mā te whai wāhi ki tētahi tukanga mārama me te pumau, ka māmā ake hoki mō ngā rōia (ngā rōia me ngā tāngata noa) te whakarato ratonga whai hua ake.

I te katoa, he kaupapa whakatau tautohe "e tika ana mō te kaupapa" te whakatau whakawa, me te mōhio he maha ngā tautohe hanga whare me te hanganga he "iti te uara" te whakataurite, e hiahia ana rānei kia whakatauhia tonutia kia taea ai te haere tonu o te kaupapa, kia whakatauhia rānei he kereme utu.

He aha te Kaupapa LVC?

He whai hua te whakatau i ngā take utu. Ko tā te Kaupapa LVC e hoatu ana ki a koe ko te whakapumautanga utu. Mena ka uru tō tautohe ki te Kaupapa, ka utua he utu pumau mō te whakatau.

Ko taua utu pumau e hipoki ana i:

  • Te whakatūnga o tētahi kaiwhakawā mātau i roto i ngā hāora 24.
  • Te wā katoa e pau ana i te kaiwhakawā ki te whakaaro i te kereme me te whakatau i tā rātou whakataunga, me ngā utu, ngā whakapaunga rānei e pā ana ki a rātou i te mahi pera.
  • Te urunga atu ki tētahi Kai-rehita BDT kua tohua, māna e whakahaere te tukanga, ā, ka taea e ia te whakautu i ō pātai mō te tukanga, te tohutohu rānei i a koe ki te huarahi e kitea ai ā mātou rauemi me ngā tauira whai hua (he maha kei te ipurangi i runga i tā mātou paetukutuku i konei ).
  • Te arotake i te whakataunga i mua i te tukunga ki ngā rōpū, kia mōhio ai ka tukuna he whakataunga kounga me ngā tohutohu mārama.

Ka whakatau te kaiwhakawā i runga i ngā tuhinga i tukuna mai e ngā rōpū (tae atu ki te kereme, te whakautu, me tetahi whakautu, whakautu rānei), ā, mā te tukanga ka puta he whakataunga e herea ana e ngā rōpū mēnā kāore te tautohe e whakatauhia mā te whakatau tautohe, mā te kōti rānei (e whakatauhia rānei mā te whakaaetanga i waenganui i ngā rōpū).

Nā te angitu nui o te Kaupapa LVC a BDT, kua whakaaetia tētahi kaupapa ōrite ki te UK e te Kaunihera Ahumahi Hanga i muri i tā mātou kōrerorero ki a rātou.

Hei tirotiro mēnā kei te tika koe mō te Kaupapa LVC, tirohia tēnei hononga .

He aha ngā momo tautohe e tika ana mō te Kaupapa LVC?

I te whakaurunga o te Kaupapa LVC, me iti iho i te $50,000 te uara o te kereme tae atu ki te GST kia whai mana ai. Kua piki ake te tono mō te whakatau i roto i ngā tau 10 kua hipa ake nei mā te 90%, ā, kua piki ake hoki ngā utu hanga i taua wā. Nō reira, mai i te 16 o Hepetema 2021, kua whai mana ngā kereme mō te uara i raro i te $100,000 ki te kaupapa. Mā tēnei ka nui ake te hunga ka taea te whakamahi i tēnei tukanga whai hua, whai hua hoki.

Hei whai mana, me kaua e neke atu i te toru ngā take e uru ana ki roto i tō tautohe, ā, me whakawhāiti hoki te roa o ngā tuhinga ka taea e koe te tuku hei tautoko i tō kereme.

I raro i aua herenga, ka taea te kawe i tetahi momo tautohe e puta ake ana i raro i tetahi kirimana hanga ki roto i te kaupapa utu pumau, ahakoa i kawea mai i runga i te nama kore utu, i runga rānei i ngā take tika,

Ko ngā tautohe e pā ana ki ngā hiranga e pā ana ki:

  • te kore utu mō te mahi i mahia;
  • te whakamaoritanga o te kirimana – ko ngā mea i whakaaetia e ngā rōpū;
  • te whānuitanga o te mahi;
  • te kounga o te mahi;
  • te kounga o ngā rauemi;
  • te wā e oti ai;
  • utu – te uara o te mahi i mahia i te korenga o tētahi whakaaetanga mārama mō te utu;
  • ngā whakatau tata me te utu tuturu;
  • ngā rerekētanga – mēnā he rerekētanga tūturu tētahi mahi ki te whānuitanga o te mahi kua whakaaetia me te uara o taua mahi rerekē;
  • mahi hapa;
  • te whānuitanga me te utu o te mahi whakatikatika;
  • te whakakore/te whakakorenga o te kirimana; ā,
  • ngā utu mō te takahi i te kirimana.

Kei te wātea ā mātou Kai-Rehita hei whakautu i ō pātai katoa, ā, ka taea e rātou te ārahi i a koe ki te huarahi tika mēnā e hiahia ana koe ki ētahi atu tohutohu.

Whakapā mai

Whakakīia te puka hei whakapā atu ki tā mātou tīma kia kite ai me pēhea mātou e āwhina ai, e whakapā mai rānei ki a mātou mō tētahi o ēnei e whai ake nei:

Waea: +64 9 486 7143

Waea Koreutu: 0508 WHARE

Waea Koreutu: 0508 284 534

Ngā Hāora Tari: Mane ki te Paraire 8:30 i te ata ki te 5:00 i te ahiahi (haunga ngā hararei tūmatanui)

Whakapā mai

Ētahi atu rauemi ka pai pea ki a koe

Mena i kitea e koe he whai hua tēnei tuhinga, ā, kei te hiahia koe ki te ako atu, he nui ngā rauemi kē atu kei runga i tā mātou paetukutuku. He whānuitanga ā mātou tuhinga me ngā aratohu mō ngā kaupapa maha, kua hangaia ia tuhinga hei whakarato i te māramatanga hohonu ake ki a koe mō te kaupapa. Ka akiaki mātou i a koe kia tūhuratia ēnei rauemi me te whakahōhonu ake i tō mōhiotanga.

Whānui , Whakatau

E 'rite' ana ngā kereme utu mō te moni pupuri ki ngā tikanga paerewa o te kirimana i Aotearoa?

Kāore te Ture Kirimana Hanga o Aotearoa 2002 ( CCA ) e kī mārama ana ka taea te whakamahi i ngā kereme utu hei whakahoki mai i te moni pupuri. Heoi anō,...
Whakataunga

I ara ake ngā tautohetohe mō te whakakorenga me te aukati i roto i te tautohe utu wā poto

Kua whakamāramahia e te keehi a te Kōti Pīra o Ingarangi mō A & V Building Solutions Limited v J & B Hopkins Limited ngā take e pā ana ki ngā rōpū...