Interaction between the CCA and standard conditions of contract
Amounts withheld as retention money are set in construction contracts, and typically range between five and ten per cent of the contract value. Retention money is usually paid 12 months after the completion of a contract.
The authors of Kennedy-Grant and Weatherall on Construction Law note that the standard conditions of construction contracts referred to in that commentary[1] all provide for the withholding from progress payments of retentions, and explain:[2]
The sums retained are returned to the contractor in the proportions provided in the various conditions over the period between practical completion/taking over and final payment. Whether such provisions will continue to be accepted in light of the retention money provisions … and particularly s 18I, which requires retention money to be paid upon fulfilment of all obligations under the contract and no later, remains to be seen.
What is being referred to is section 18I(1)(b) of the CCA, which renders void any term of a contract which attempts to make the date on which payment of retention money is payable later than the date on which party B has performed all of its obligations under the contract to the standard agreed under the contract.
The Victorian Supreme Court’s analysis
On and from each reference date under a construction contract, a person— (a) who has undertaken to carry out construction work under the contract; or (b) who has undertaken to supply related goods and services under the contract— is entitled to a progress payment under this Act, calculated by reference to that date.In Punton’s Shoes v Citi-Con, Punton’s had served a payment claim for 50% of the retention money being held by Citi-Con.[3] The Victorian Supreme Court found the terms of the contract made no provision for a payment claim by Punton’s for retention moneys and that the claim was not in the nature of a payment claim under the SoP Act. It held:
[110] …any implied right or entitlement there may be in the Contractor to return of a portion of retention moneys is different in character and distinct from either a claim under the Contract for the value of work carried out or an entitlement under the SoP Act for the value of construction work carried out and related goods and services.
[111] In distinction to a payment claim entitlement, the Contract does provide a mechanism to adjust the parties’ entitlements in relation to moneys deducted by way of retention. Any sum held by way of retention is to [be] taken into account in the Final certification process under …the Contract and thereby accounted for in the amount ultimately payable as between the Contractor and the Principal on the final reconciliation of each [party’s] entitlements under the Contract. The retention deduction, reduction, recourse and security related provisions of the Contract do not contemplate or accommodate payment claims by the Contractor for contract work undertaken or related goods and services supplied.
[112] …any implied entitlement to return of retention moneys upon the issue of the Certificate of Practical Completion under the Contract, or adjustment under [the Contract], is not in the nature of a progress payment entitlement in relation to work carried out by the Contractor in the performance of the Contract.
The decision makes the security of payment regime in Victoria inconsistent with other states and territories in Australia including NSW, Queensland, ACT, Tasmania, and South Australia in which retentions constitute a ‘claimed amount’ and are expressly allowed to be included in a payment claim. And, the WA and NT Acts both imply a term to the effect that an adjudicator may decide if retention money ceases to be payable to the contractor indicating that such sums may be claimed in a payment claim.
The CCA and ‘payments’ in New Zealand
A fact sheet prepared by MBIE explaining the 2015 amendments to the CCA states:[4]
The definition of ‘claimed amount’ has been reworked to make it clear a payment claim can specify any payment amount the payee believes to be due under the contract.
Additionally, a new definition for ‘payment’ has been inserted to make it clear that a payment means a progress payment for construction work[5] or any other type of payment a party to a construction contract is entitled to,[6] i.e.: a payment claim can specify amounts claimed for interest, retention money or other amounts due under the contract.
However, in Rintoul Group Ltd v Far North District Council,[7] Moore J made the following observation:
There are indications elsewhere in the CCA that Parliament did not intend funds held on retention to be treated as progress payments capable of being claimed under s 20. For example retentions may be held on trust and invested in accordance with the Trustee Act 1956. They may also be intermingled with other monies.
While merely an observation, it does indicate that the issue is perhaps not as clear cut as it at first appears. We have seen this before in relation to amendments to the CCA where those proposing the amendments understood they would create a ‘deemed’ trust situation for retention money being held. When this question came before the High Court in Bennett v Ebert Construction Ltd, Churchman J found otherwise:[8]
Although, at the committee stage, the then Minister for Building and Housing, the Hon Dr Nick Smith, said that the effect of the intended legislation was that the retention funds “… are deemed to be held in trust …”, it does not seem that the provisions in the legislation actually created a deemed trust.
Conclusion
References
[1] The NZS 2013 Contracts and NZS 3915:2005, cl 12.3; NZS 3902:2004, cl 14.2 and Box H; NZIA SCC 2018 and SCC SF 2016, cl 14.9 and NBC 2018 and NBC SF 2016, cl 14.8; FIDIC Red, Yellow and Silver Books, cl 14.3(c); FIDIC Green Book, cl 11.3.
[2] T Kennedy-Grant and B Weatherall, Kennedy-Grant and Weatherall on Construction Law [221,660] Retentions, LexisNexis NZ Ltd.
[3] Punton’s Shoes v Citi-Con [2020] VSC 514.
[4] Ministry of Business Innovation & Employment Building Performance website:
[5] Section 19(a) CCA.
[6] Section 19(b) CCA.
[7] Rintoul Group Ltd v Far North District Council [2019] NZHC 2577.
[8] Bennett v Ebert Construction Ltd (in rec and liq) [2018] NZHC 2934.
[9] Section 3 CCA.
[10] Inserted on 31 March 2015 by section 18 of the Construction Contracts Amendment Act 2015.