Recently, a subcontractor in the UK was relieved of adverse ground conditions risk, despite contract amendments that sought to allocate that risk to the subcontractor- and it all hinged on an analysis of appendices to the contract. Appending documents to a contract without giving due consideration to how they work with the main contract terms is a risky business. While often it is important for such documents (often technical) to be included in a contract, parties need to turn their minds to any potential inconsistencies, ambiguities or misunderstandings that should be addressed prior to signing the contract.

 

Common practice in the industry

It is common for contracts to include appendices containing additional documents relevant to the contract. In the construction industry, P&G Specification, Site Plans, Drawings & Specifications as well as Contract Price composition information are all commonly appended to a contract. Anything appended to the contract becomes part of the contract and therefore is legally binding on the parties.

To mitigate the risk of inconsistencies in the contract, parties will often include a ‘priority clause’ which sets out the order of precedence for the contract documents. Usually the main contractual terms take priority, with more technical documents being of lower priority. Parties rely on a priority clause to resolve any possible inconsistencies between information and terms found in different parts of a contract. The issue is that a priority clause doesn’t come into play if no inconsistency is found in the first place.

The risk of appended documents has recently been demonstrated in cases in the UK which serve as a reminder of the need for contracting parties to be careful in New Zealand.

 

What the law has to say

The principles of contract interpretation have been well laid out in cases over the years. Contractual terms are to be read in the light of the contract as a whole and its overall purpose. When interpreting a contract, the court seeks to determine the parties’ intention by reference to “what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean….in their documentary and factual context”.[1] On applying this legal principle, courts have shown themselves to be slow to find inconsistencies in a contract. As a result, priority clauses, while helpful in providing some ‘order’ in a contract, are rarely applied by the courts. This means that a term or condition buried in a ‘lower priority’ contract document will be given effect, so long as the meaning is not inconsistent with higher priority documents.

 

Recent UK case law

In Clancy Docwra Limited v E.ON Energy Solutions Limited[2] (CDL v E.ON), CDL was a subcontractor carrying out trenching works in Central London.  It discovered a number of underground objects requiring additional resources and work to excavate. A dispute arose as to who bore the risk of unforeseen adverse ground conditions. CDL argued that addressing adverse ground conditions was outside the scope of the subcontract works, as spelled out in the tender clarification documents appended to the subcontract. E.ON, the contractor, argued that the risk of unforeseen adverse ground conditions lay with CDL under the main conditions of the contract, which took priority in the priority of documents clause in the subcontract.

The Court sided with CDL, finding that E.ON bore the risk of unforeseen ground conditions. The priority clause didn’t even come into play as the Court found there to be no inconsistencies within the contract. Instead, the Court held that the construction work in question did not form part of the scope of subcontract work because this work had been expressly excluded in the appended documents. This meant that E.ON could not rely on the broad risk allocation clause in the main contract terms nor could it rely on the priority clause to avoid bearing the risk and cost of this additional work.

CDL v E.ON demonstrates how parties cannot rely on a priority clause to address contractual interpretation issues where there is no inconsistency found. The case highlights the importance of parties taking time to really understand what the documents being appended to the contract actually mean and how they affect the application of the main contract terms. In this case, it was evident that the post-tender clarifications put the risk of adverse ground conditions on E.ON, whether or not this is what E.ON intended its commercial position to be.

An earlier UK case, MT Højgaard AS v E.ON Climate and Renewables[3] (MT Højgaard v E.ON) is more commonly known for its discussion of fitness for purpose; however also highlights the risk of appending technical documentation to a contract without being fully aware of its contents. Again, the Court in this case found no inconsistencies within the contract documents and instead used the basic principles of contractual interpretation to determine the contract’s effect.

Here the contractor, MT Højgaard, argued that an onerous obligation requiring the foundations of an offshore windfarm be designed to ensure a lifetime of 20 years, should not be given effect because it was only found in a relatively obscure part of the tender documents and not spelled out in the prioritised contract conditions on design quality. However, the Court found that because the terms of the contract clearly included the tender documents, the parties must have intended that the onerous obligation would be given contractual effect.

The contractor also tried to argue that because the prioritised conditions of the contract imposed other obligations with respect to the quality of the design and build, the parties must not have intended that a more stringent obligation in the tender documents would be given effect. This argument was rejected as it would render meaningless the requirement that the foundations be designed to ensure a lifetime of 20 years. The contractor had therefore breached the contract and was liable for the cost of remedying the foundations.

 

Application to New Zealand

There is no analogous New Zealand case law to draw from. However, given the New Zealand courts follow the same approach to contract interpretation as the UK courts, it is highly likely that the UK cases mentioned above would apply to any analogous case heard in New Zealand. It is entirely possible that a case of this nature could arise in New Zealand, particularly in the construction context where numerous technical documents are regularly appended to construction contracts. Therefore, it pays for contracting parties in New Zealand to take heed of the issues raised in the UK cases to avoid facing the same pitfalls when applying their own contracts.

 

Lessons to be learnt

The above two cases do not lay down new law or revolutionise contract interpretation. However, they serve as an important reminder that even terms buried deep in technical documentation are part of the contract and so it is essential to know and understand them. Priority clauses will not save the day when the contractual terms in question are not inconsistent. To avoid potentially substantial financial consequences, parties should undertake comprehensive due diligence on a contract to identify inconsistencies, uncertainties or potential misunderstandings, between clauses especially where technical documentation prepared by the contractor or subcontractor is appended.

[1] Arnold v Britton [2015] UKSC 36, per Lord Neuberger at [15].

[2] Clancy Docwra Limited v E.ON Energy Solutions Limited [2018] EWHC 3124 (TCC).

[3] MT Højgaard AS v E.ON Climate and Renewables UK Robin Rigg East Ltd and another [2018] 2 All ER 22.

 

To read this article in BuildLaw click here 

 

About the Authors

Sarah Sinclair

Chair and Partner – Construction and Infrastructure

Katie Keir

Solicitor – Construction and Infrastructure

 

 

Obstructed view review

Written by Maria Cole Introduction In Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited,[1] a group of apartment owners filed judicial review proceedings seeking to overturn an Auckland Council decision to grant resource...

The losing streak is over: English rugby wins… right to bring claim against contractor

Written by Alexander Lyall Nearly 10 years on, English rugby finally has a victory related to the 2015 Rugby World Cup. In FM Conway Ltd v Rugby Football Union,[1] a company contracted by the English Rugby Football Union (the RFU) for maintenance works at Twickenham...

Keep calm and carry on: English Court of Appeal overturns controversial High Court ruling and clarifies guiding principles in serial adjudications

By Kate Holland The English High Court caused concern earlier this year when it held that an adjudicator had breached natural justice by holding himself bound by a previous adjudicator’s findings. Now, in Sudlows Ltd v Global Switch Estates 1 Limited,[1] the Court of...

Moving home

Written by Richard Pidgeon A family became dissatisfied with a house removal firm who had shifted their home from Remuera to Katikati. In Stott v Uplifting Homes Ltd [2023] NZHC 1514, the High Court determined the level of compensation after the contract was...

Big loss for insurer in legal battle with Napier Council over leaky building clause

Written by Sam Dorne In a recent case, the Supreme Court of New Zealand ruled in favour of the Napier City Council in an insurance claim involving building defects including weathertightness or “leaky building” issues, in what is seen as a return to the status quo...

BuildLaw Issue 51

September 2023Download PDF   CONTENTS BuildLaw in Brief Keep calm and carry on Mainzeal saga ends in the Supreme Court New Zealand: Insurance under Scrutiny Obstructed view review Case in Brief: Esk Valley marae injunction Res judicata and declarations relating...

Take a rain cheque – Full Federal Court of Australia reads common sense into insurance policy

By Alexander Lyall A decision by the Full Federal Court of Australia has provided clarification about the wording of an insurance policy for a construction project. In Acciona Infrastructure Australia Pty Ltd v Zurich Australian Insurance Limited [2023] FCAFC 47,[1] ...

Case update: English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

Disgruntled builders lose defective cladding dispute

By Sam Dorne In Goodman-Jones v Hughey & ors [2023] NZHC 604, two experienced builders brought a claim for damages for a perceived defective installation of cladding for a new build. Despite the action being brought against multiple defendants the Court found that...

BuildLaw Issue 50

June 2023Download PDF   CONTENTS BuildLaw in Brief: Recent key developments in the construction industry Bad faith and without substantial merit – What it means and what it takes Disgruntled builders lose defective cladding dispute High-rise blues Build-to-Rent:...

Craftiness is not an abuse of process

With cashflow a persistent concern for companies in the construction industry, a recent decision in the New South Wales Supreme Court may alleviate some of the stress. The decision should affirm to struggling parties that there is no problem with taking strategic...

Privileged glimpses: Curtain falls on art gallery’s nuisance ‘human zoo’ exhibit

By Kate Holland The UK Supreme Court has ruled that the London Tate Modern’s public viewing gallery overlooking the luxury glass-walled apartments nearby, is a visual intrusion amounting to the tort of nuisance. The decision in has attracted criticism for prioritising...

Waiver and estoppel arguments raised in interim payment dispute

By Sam Dorne The English Court of Appeal case of A & V Building Solutions Limited v J & B Hopkins Limited has highlighted issues parties face when there is ambiguity in relation to dates for requesting interim payment in construction contracts.[1] The case...

Doing business in Australia? Then you need to know when you still might have to pick up the whole tab

By Maria Cole If you have a commercial contract in Australia, it’s probably governed by Australian law, which includes the proportionate liability regime.[1] Broadly, proportionate liability means if there are multiple parties to a contract and things go wrong, a...

Parliament passes sweeping amendments to construction payment regime

By Alexander Lyall Parliament has recently enacted legislation allowing for comprehensive changes to the Construction Contracts Act 2002. The Construction Contracts (Retention Money) Amendment Act 2023 passed its third reading on Wednesday 29 March and received Royal...

BuildLaw Issue 49

March 2023Download pdf   CONTENTS Diamond Glass slices damages in airport contract Case in Brief: Craftiness is not an abuse of process (Kennedy Civil Contracting Pty Ltd (Administrators Appointed) v Richard Crookes Construction Pty Ltd [2023] NSWSC 99) That...

Builder terminates contract with a “sorry mate…costs are going through the roof”

By Kate Holland With the construction industry in the grip of labour and supply shortages and spiralling costs, a recent decision of the Queensland court is a timely reminder of the established principles of contractual repudiation. The decision is a warning to...

Ripping up the Resource Management Act

By Adrian Sharma The Resource Management Act 1991 (RMA) is one of New Zealand’s most important pieces of legislation. It governs what can be built where, when, and how. But more than 30 years on from its introduction, and after numerous amendments, the controversial...

To bespoke or too bespoke – the case of an ADR clause that couldn’t be enforced

By Kate Holland In a recent English decision, the Technology and Construction Court held that a clause in a construction contract requiring the parties to refer a dispute to ADR was a condition precedent to commencing litigation in the courts. However, the Court also...

The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so file a payment schedule or pay up!

By Maria Cole A decision issued by the High Court last year caused a “head in hands” moment in the construction industry in relation to the payment claim regime. The High Court set aside a statutory demand which had been filed to enforce a payment claim as a debt due...

BuildLaw Issue 48

December 2022Download pdf   CONTENTS The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so issue a payment schedule or pay up! Case in Brief: Builder terminates contract with a “sorry mate… costs are going through the roof” but...

Labelling an image as an ‘artist impression’ was found not to give a developer artistic licence in a claim of misleading and deceptive conduct over an ‘off-the-plan’ premium apartment

By Maria Cole Australian consumer protection law was given an outing in the Federal Court of Australia when a developer merely added the words ‘artist impression’ to a computer generated image it intended to use in its marketing materials for an ‘off-the-plan’...

Fire risk – defective cladding litigation heats up

By Sam Dorne In England and Wales, the Technology and Construction Court in Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 July 2022) has released the first decision arising out of a defective cladding dispute following the Grenfell Tower...

BuildLaw Issue 47

September 2022CONTENTS Competition not working well in residential building suppliesmarket Fire risk – defective cladding litigation heats up Case in Brief: Supreme Court of New South Wales finds forcemajeure clause offered no protection for loss and damage togoods in...

WA Supreme Court finds no implied licence to use home design plan

By Kate Holland In a recent Australian case, the WA Supreme Court was unwilling to interpret a contract between a home builder and their client to imply a licence allowing the client to use the builder’s design in whatever way they pleased. Although the case was...

Overhaul coming to the regulation of engineers

By Sam Dorne The Ministry of Business, Innovation and Employment (MBIE) undertook a consultation in 2021 to reform the regulatory regime for engineers. The reforms will move away from a voluntary accreditation scheme into a formal regulated regime.   Current...

Expert “evidence” needs to be more than just bald assertions to win the day

By Adrian Sharma Leakage issues in a building can be a real dampener. A recent decision of the Queensland Civil and Administrative Tribunal (the Tribunal) which considered conflicting expert evidence on water ingress issues in a newly built property highlighted the...

An adjudicator’s decision on a construction contract is definitely worth the paper it’s written on!

By Maria Cole It’s only in rare circumstances that the courts will interfere with the decision of an adjudicator on a construction contract. A recent decision out of the English Technology and Construction Court (TCC) considered arguments that an adjudicator acted in...

You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure

By Belinda Green.   We’ve known for a long time that a party can’t rely on a failure to satisfy a condition if the condition failed to satisfy because of their action. But we never really had an explanation of how bad that “failure” had to be until now. In its...

BuildLaw Issue 46

March 2022CONTENTS You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure Case in Brief: Unhelpful expert witness sees homeowners succeed in defective...

Vicarious liability and subcontractors

By Sam Dorne Liability in tort depends upon proof of a personal breach of duty, with one true exception, vicarious liability. The law of negligence is generally fault based; a defendant is personally liable only for the defendant’s own negligent acts and omissions....

Limitation for payment claims under construction contracts

By Sam Dorne The decision in Hirst v Dunbar [2022] EWHC 41 (TCC) considers the impact of payment provisions in a construction contract, whether through contract or implied terms, and the commencement of the limitation period for payment claims under the contract. It...

Extensions of time in construction contracts

By Jo O’Dea   In an extension of time claim, blame for the delay was a relevant consideration when assessing what was “fair and reasonable”.   In CAJ v CAI [2021] 5 GCA 102, the Singapore Court of Appeal considered the issue of extensions of time in...

BuildLaw Issue 45

March 2022CONTENTS Extensions of time in construction contracts Construction contract procedure and dispute resolution: There really is a reason to pay attention to the boring stuff Principals beware, constructive acceleration is here UK: Important announcement on the...

Testing the waters: New South Wales Supreme Court considers the prevention principle

By Hannah Aziz  Court provides further confirmation that the prevention principle can be excluded by the terms of a contract.   Introduction Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the...

Construction contract or product warranty? Not all collateral warranty disputes can be adjudicated

By Belinda Green Collateral warranties might be parasitic on a construction contract, but that doesn’t automatically mean they are one. The individual wording and circumstances need to be considered. In some cases, like in Toppan Holdings Limited v Simply Construction...

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Important Guidance on Contract Interpretation Issued by the Supreme Court

Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 The Supreme Court in Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 has provided important guidance on how extrinsic evidence and implied terms are used to aid interpretation of...
Skip to content