Jo O’Dea

In the recent Australian case of Gemcan Constructions Pty Ltd v Westbourne Grammar School [2022] VSC 6, the Supreme Court of Victoria considered a number of issues concerning a construction payment dispute between the parties.  Technically this case was the enforcement claim culmination of a number of problems. 

NOTE:  This case is an Australian case.  It concerned two relevant pieces of legislation there, the Commercial Arbitration Act 2011 (CCA) and the Building and Construction Industry Security of Payment Act (2002), (“SOP” Act).  The relevant equivalent law in New Zealand is the Arbitration Act 1996 and the Construction Contracts Act 2002, which are broadly similar but with some quite significant differences.  For the purposes of both the legislation and the case law there are enough similarities to conclude that the outcome of the dispute would be similar in New Zealand.

Background

On 25 July 2016, Gemcan Constructions Pty Ltd (Gemcan) and Westbourne Grammar School (WGS) entered into a construction contract for various works at a WGS campus. Disputes about the work and payments occurred, and for this the parties sought a determination under the SOP Act.  WSG then sought a judicial review of the determination.

Judicial review (2017)

WGS sought judicial review of the payment determination in the Supreme Court of Victoria and was successful in having it quashed. His Honour Robson J held that the adjudicator had committed a jurisdictional error in finding that a notice from WGS purporting to take works remaining to be performed under the Contract out of the hands of Gemcan (the take-out notice) was invalid because it had not been validly served on the Builder.

Shall we arbitrate?(2020)

In addition to payment disputes, the parties weren’t even able to agree that they had a valid dispute resolution clause. Gemcan sought to refer the disputes to arbitration under the relevant clause of the contract.  WGS opposed this, arguing that the contract did not constitute a binding agreement to arbitrate because it did not contain details of how the arbitrator would be appointed and which arbitration rules would apply. 

In determining this point in favour of Gemcan, the Court found that the contract contained a valid arbitration agreement allowing the Court to decide on the appointment of an arbitrator pursuant to section 11 of the CAA.  Gemcan then commenced arbitration proceedings against WGS.

The Arbitration (2021)  

At arbitration, Gemcan obtained an award in its favour for the payment claim under the SOP Act. One of the arguments raised by Gemcan was that the take-out notice was invalid on the basis that Gemcan was not in substantial breach of the contract. WGS argued that Gemcan was precluded from making that argument (“estopped”) because the validity of the take-out notice had already been determined by Robson J in the judicial review proceeding.

The arbitrator found that the decision of Robson J was limited to considering whether the adjudicator had erred in determining that the take-out notice had been validly served. Gemcan was not estopped from arguing in the arbitration that the notice was otherwise invalid on the basis that it was not in breach of the contract. The consequence of this was that the take-out notice was invalid in substance and that WGS had not, therefore, validly taken the work away from Gemcan.

The Supreme Court (2022)

Gemcan then applied for enforcement of the arbitration award and WGS applied to have the award set aside on the basis that it was in conflict with public policy. WGS argued that the arbitrator was “estopped” from finding that Gemcan was not in substantial breach of contract. WGS argued that the principles of res judicata and issue estoppel applied.

Res judicata means that something has been adjudicated by a competent court and therefore cannot be pursued further by the same parties. Issue estoppel prevents a party attempting to relitigate an issue of fact or law previously determined in legal proceedings. WGS also arguing that an Anshun estoppel applied.  This type of estoppel is a form of issue estoppel which operates to prevent a party from bringing a claim in proceedings which should have been (but weren’t) brought in earlier proceedings.

The two main issues were:

  • whether there was an issue estoppel (or an Anshun estoppel); and
  • if so, whether the arbitration award should be set aside because the failure by the arbitrator to apply the issue estoppel or Anshun estoppel made it contrary to public policy.

Justice Riordan concluded that the issue considered in the judicial review case was whether the take-out notice was invalid because it was served after the WGS had already taken the work away from Gemcan.  Robson J’s decision that the adjudicator was mistaken to find that the take-out notice was invalid was only made in respect of the procedural requirements for service of the take-out notice. Robson J did not make any finding about the substantive content of the take-out notice – that is, whether Gemcan was in breach of the contract. In the circumstances, Justice Riordan found that there was no issue estoppel which prevented the arbitrator from determining that Gemcan was not in substantial breach of the contract and that the Take Out Notice was therefore invalid.

Justice Riordan also found that an Anshun estoppel did not arise because Gemcan’s failure to allege before Justice Robson (in the judicial review proceeding) that there was no substantial breach of contract entitling WGS to issue the take-out notice was not unreasonable. To find otherwise would be contrary to the objectives of the SOP Act, which is designed to ensure prompt payment and cashflow through a quick adjudication process, subject to final determination of disputes at a later time. Requiring parties to raise complex substantive matters during adjudication or on judicial review of an adjudication determination would defeat the purpose of the legislative scheme.

Despite finding that an estoppel did not arise, Riordan J went on to consider whether an error by the arbitrator could result in the arbitration award being in conflict with the public policy.

He noted that that the public policy exception should be narrowly construed.  In noting this, and having regard to the approach of minimum intervention in arbitral proceedings enshrined in the CAA, Riordan J found that a failure by an arbitrator to apply an issue estoppel was capable of engaging the public policy ground.  BUT that ground would not be effective unless there had been a real practical injustice or unfairness in the making of the award.

His Honour concluded that even if he had found the arbitrator was in error, there had been no real practical injustice or unfairness.  

Conclusion

Here, the Court seems to have followed the “spirit” of the legislation in reaffirming that where there is a payment dispute mechanism, this mechanism will operate to do just that. A determination (about payment) under the SOP Act does not finalise the rights between the parties, and in most cases the parties will have agreed a final dispute resolution mechanism under the relevant building contract – which they must use.

To decide whether or not there is any issue estoppel, the court will look at the facts of the case to decide whether there has been real unfairness or practical injustice.  If there has been a judicial review of an adjudicator’s determination under the SOP Act, it is unlikely a court will find there has been real unfairness and practical injustice in circumstances where matters outside the scope of the judicial review are not argued before the court.

In New Zealand, it is not uncommon for a claimant to bring an adjudication over a payment dispute on the basis of default liability (ie, technical non-compliance with the payment regime under the CCA) and on the merits in the alternative. Adjudicators have the power to determine any dispute arising under a construction contract (not just payment disputes) and since December 2015, determinations concerning the parties’ rights and obligations are enforceable in accordance with section 59A of the CCA (see section 58(2)).

The question as to whether res judicata (an issue estoppel) arises in the context of successive adjudications is a different issue. The leading New Zealand authority on res judicata in the adjudication context is the decision of the High Court in Body Corporate 200012 v Keene QC [2017] NZHC 2953 at [81]-[83].

More recently in Haskell Construction Limited v Ashcroft [2020] 3 NZLR 113 (HC) at [77] Grice J stated that…the focus should be on what was actually determined in the earlier adjudication decision. That determines how much or how little remains available for consideration by the subsequent adjudicator…Any analysis of commonality must be undertaken bearing in mind the robust and time limited process for adjudications. Unless it is clear the matters in the claim have all been uncontestably dealt with or should have been in the earlier adjudication this Court should be cautious about interfering with the adjudicator’s decision. It should not undertake a fine analysis of the issues raised in the earlier adjudication. The adjudicator, not this Court, is in the best position to undertake that analysis and reach a decision informed by the information put before him and the parties’ submissions.

 

 

Obstructed view review

Written by Maria Cole Introduction In Wynyard Quarter Residents Association Incorporated v Auckland Council and Orams Group Limited,[1] a group of apartment owners filed judicial review proceedings seeking to overturn an Auckland Council decision to grant resource...

The losing streak is over: English rugby wins… right to bring claim against contractor

Written by Alexander Lyall Nearly 10 years on, English rugby finally has a victory related to the 2015 Rugby World Cup. In FM Conway Ltd v Rugby Football Union,[1] a company contracted by the English Rugby Football Union (the RFU) for maintenance works at Twickenham...

Keep calm and carry on: English Court of Appeal overturns controversial High Court ruling and clarifies guiding principles in serial adjudications

By Kate Holland The English High Court caused concern earlier this year when it held that an adjudicator had breached natural justice by holding himself bound by a previous adjudicator’s findings. Now, in Sudlows Ltd v Global Switch Estates 1 Limited,[1] the Court of...

Moving home

Written by Richard Pidgeon A family became dissatisfied with a house removal firm who had shifted their home from Remuera to Katikati. In Stott v Uplifting Homes Ltd [2023] NZHC 1514, the High Court determined the level of compensation after the contract was...

Big loss for insurer in legal battle with Napier Council over leaky building clause

Written by Sam Dorne In a recent case, the Supreme Court of New Zealand ruled in favour of the Napier City Council in an insurance claim involving building defects including weathertightness or “leaky building” issues, in what is seen as a return to the status quo...

BuildLaw Issue 51

September 2023Download PDF   CONTENTS BuildLaw in Brief Keep calm and carry on Mainzeal saga ends in the Supreme Court New Zealand: Insurance under Scrutiny Obstructed view review Case in Brief: Esk Valley marae injunction Res judicata and declarations relating...

Take a rain cheque – Full Federal Court of Australia reads common sense into insurance policy

By Alexander Lyall A decision by the Full Federal Court of Australia has provided clarification about the wording of an insurance policy for a construction project. In Acciona Infrastructure Australia Pty Ltd v Zurich Australian Insurance Limited [2023] FCAFC 47,[1] ...

Case update: English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

English Court of Appeal confirms ‘useless’ ADR procedure too uncertain to enforce

By Kate Holland In our December 2022 issue of BuildLaw, we reported on a case in the English High Court[1] about an unusual alternative dispute resolution (ADR) procedure in a construction contract that was held to be too uncertain to be an enforceable condition...

Disgruntled builders lose defective cladding dispute

By Sam Dorne In Goodman-Jones v Hughey & ors [2023] NZHC 604, two experienced builders brought a claim for damages for a perceived defective installation of cladding for a new build. Despite the action being brought against multiple defendants the Court found that...

BuildLaw Issue 50

June 2023Download PDF   CONTENTS BuildLaw in Brief: Recent key developments in the construction industry Bad faith and without substantial merit – What it means and what it takes Disgruntled builders lose defective cladding dispute High-rise blues Build-to-Rent:...

Craftiness is not an abuse of process

With cashflow a persistent concern for companies in the construction industry, a recent decision in the New South Wales Supreme Court may alleviate some of the stress. The decision should affirm to struggling parties that there is no problem with taking strategic...

Privileged glimpses: Curtain falls on art gallery’s nuisance ‘human zoo’ exhibit

By Kate Holland The UK Supreme Court has ruled that the London Tate Modern’s public viewing gallery overlooking the luxury glass-walled apartments nearby, is a visual intrusion amounting to the tort of nuisance. The decision in has attracted criticism for prioritising...

Waiver and estoppel arguments raised in interim payment dispute

By Sam Dorne The English Court of Appeal case of A & V Building Solutions Limited v J & B Hopkins Limited has highlighted issues parties face when there is ambiguity in relation to dates for requesting interim payment in construction contracts.[1] The case...

Doing business in Australia? Then you need to know when you still might have to pick up the whole tab

By Maria Cole If you have a commercial contract in Australia, it’s probably governed by Australian law, which includes the proportionate liability regime.[1] Broadly, proportionate liability means if there are multiple parties to a contract and things go wrong, a...

Parliament passes sweeping amendments to construction payment regime

By Alexander Lyall Parliament has recently enacted legislation allowing for comprehensive changes to the Construction Contracts Act 2002. The Construction Contracts (Retention Money) Amendment Act 2023 passed its third reading on Wednesday 29 March and received Royal...

BuildLaw Issue 49

March 2023Download pdf   CONTENTS Diamond Glass slices damages in airport contract Case in Brief: Craftiness is not an abuse of process (Kennedy Civil Contracting Pty Ltd (Administrators Appointed) v Richard Crookes Construction Pty Ltd [2023] NSWSC 99) That...

Builder terminates contract with a “sorry mate…costs are going through the roof”

By Kate Holland With the construction industry in the grip of labour and supply shortages and spiralling costs, a recent decision of the Queensland court is a timely reminder of the established principles of contractual repudiation. The decision is a warning to...

Ripping up the Resource Management Act

By Adrian Sharma The Resource Management Act 1991 (RMA) is one of New Zealand’s most important pieces of legislation. It governs what can be built where, when, and how. But more than 30 years on from its introduction, and after numerous amendments, the controversial...

To bespoke or too bespoke – the case of an ADR clause that couldn’t be enforced

By Kate Holland In a recent English decision, the Technology and Construction Court held that a clause in a construction contract requiring the parties to refer a dispute to ADR was a condition precedent to commencing litigation in the courts. However, the Court also...

The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so file a payment schedule or pay up!

By Maria Cole A decision issued by the High Court last year caused a “head in hands” moment in the construction industry in relation to the payment claim regime. The High Court set aside a statutory demand which had been filed to enforce a payment claim as a debt due...

BuildLaw Issue 48

December 2022Download pdf   CONTENTS The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so issue a payment schedule or pay up! Case in Brief: Builder terminates contract with a “sorry mate… costs are going through the roof” but...

Labelling an image as an ‘artist impression’ was found not to give a developer artistic licence in a claim of misleading and deceptive conduct over an ‘off-the-plan’ premium apartment

By Maria Cole Australian consumer protection law was given an outing in the Federal Court of Australia when a developer merely added the words ‘artist impression’ to a computer generated image it intended to use in its marketing materials for an ‘off-the-plan’...

Fire risk – defective cladding litigation heats up

By Sam Dorne In England and Wales, the Technology and Construction Court in Martlet Homes Ltd v Mulalley & Co Ltd [2022] EWHC 1813 (TCC) (14 July 2022) has released the first decision arising out of a defective cladding dispute following the Grenfell Tower...

BuildLaw Issue 47

September 2022CONTENTS Competition not working well in residential building suppliesmarket Fire risk – defective cladding litigation heats up Case in Brief: Supreme Court of New South Wales finds forcemajeure clause offered no protection for loss and damage togoods in...

WA Supreme Court finds no implied licence to use home design plan

By Kate Holland In a recent Australian case, the WA Supreme Court was unwilling to interpret a contract between a home builder and their client to imply a licence allowing the client to use the builder’s design in whatever way they pleased. Although the case was...

Overhaul coming to the regulation of engineers

By Sam Dorne The Ministry of Business, Innovation and Employment (MBIE) undertook a consultation in 2021 to reform the regulatory regime for engineers. The reforms will move away from a voluntary accreditation scheme into a formal regulated regime.   Current...

Expert “evidence” needs to be more than just bald assertions to win the day

By Adrian Sharma Leakage issues in a building can be a real dampener. A recent decision of the Queensland Civil and Administrative Tribunal (the Tribunal) which considered conflicting expert evidence on water ingress issues in a newly built property highlighted the...

An adjudicator’s decision on a construction contract is definitely worth the paper it’s written on!

By Maria Cole It’s only in rare circumstances that the courts will interfere with the decision of an adjudicator on a construction contract. A recent decision out of the English Technology and Construction Court (TCC) considered arguments that an adjudicator acted in...

You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure

By Belinda Green.   We’ve known for a long time that a party can’t rely on a failure to satisfy a condition if the condition failed to satisfy because of their action. But we never really had an explanation of how bad that “failure” had to be until now. In its...

BuildLaw Issue 46

March 2022CONTENTS You break it you bought it: Supreme Court confirms you can’t cancel a contract for failure to satisfy a condition if your own behaviour had a material effect on the failure Case in Brief: Unhelpful expert witness sees homeowners succeed in defective...

Vicarious liability and subcontractors

By Sam Dorne Liability in tort depends upon proof of a personal breach of duty, with one true exception, vicarious liability. The law of negligence is generally fault based; a defendant is personally liable only for the defendant’s own negligent acts and omissions....

Limitation for payment claims under construction contracts

By Sam Dorne The decision in Hirst v Dunbar [2022] EWHC 41 (TCC) considers the impact of payment provisions in a construction contract, whether through contract or implied terms, and the commencement of the limitation period for payment claims under the contract. It...

Extensions of time in construction contracts

By Jo O’Dea   In an extension of time claim, blame for the delay was a relevant consideration when assessing what was “fair and reasonable”.   In CAJ v CAI [2021] 5 GCA 102, the Singapore Court of Appeal considered the issue of extensions of time in...

BuildLaw Issue 45

March 2022CONTENTS Extensions of time in construction contracts Construction contract procedure and dispute resolution: There really is a reason to pay attention to the boring stuff Principals beware, constructive acceleration is here UK: Important announcement on the...

Testing the waters: New South Wales Supreme Court considers the prevention principle

By Hannah Aziz  Court provides further confirmation that the prevention principle can be excluded by the terms of a contract.   Introduction Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the...

Construction contract or product warranty? Not all collateral warranty disputes can be adjudicated

By Belinda Green Collateral warranties might be parasitic on a construction contract, but that doesn’t automatically mean they are one. The individual wording and circumstances need to be considered. In some cases, like in Toppan Holdings Limited v Simply Construction...

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Important Guidance on Contract Interpretation Issued by the Supreme Court

Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 The Supreme Court in Bathurst Resources Ltd v L & M Coal Holdings Ltd [2021] NZSC 85 has provided important guidance on how extrinsic evidence and implied terms are used to aid interpretation of...
Skip to content